149-05 79 Avenue is an elevator apartment building built in 1955 in Queens, 11367. It has 180 residential units across 6 floors. The owner of record is 149-05 Owners Corp. HPD has recorded 97 housing violations here, most recently on October 27, 2026. 13 of the 50 most recent violations are still open. City tax records listed 4 rent-stabilized apartments here in 2024.

HPD violations
97
DOB violations
63
ECB violations
29
HPD complaints
233

Available now in this building

What to know

Concern
3 open Class C

Immediately hazardous issues among recent violations are still open.

Watch
Last violation Oct 27, 2026

Date of the most recent HPD inspection that found a problem.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

Rent-stabilized units in 2024
4
About 2% of the building's 180 apartments
Down from 7 in 2018

Counts come from owners' rent-stabilization filings shown on NYC Department of Finance tax bills, as extracted by JustFix. They tell you a building has stabilized apartments, not which ones.

Stabilized units by tax-bill year

Think your apartment is stabilized? Request its rent history from HCR (free), then check your renewal with the renewal calculator.

Violations

Most recent first. The newest 10 per agency here; the full lists are a click away.

HPD housing violations · 97

  • ANon-hazardous

    Post a proper notice regarding rent stabilization law, in a form approved by the commissioner, in a conspicuous location within the common area at the buildings entrance. for more information about signage requirements, please visit: https://www.nyc.gov/site/hpd/services-and-information/required-signage.page

    Oct 27, 2026

    Open — Nov sent out
  • ANon-hazardous

    Paint with light colored paint to the satisfaction of this department west wall and east wall (labeled 2nd floor) at public hall, 1st story, section ''a'', at west

    Jun 29, 2026

    Open — Nov certified on time
  • BHazardous

    Properly repair or replace the broken or defective latch set at door (labeled as 7th floor) at compactor closet, 6th story, section at west

    Jan 29, 2026

    Closed — Violation dismissed
  • CImmediately hazardous

    Replace or repair the self-closing doors that is missing or defective latch set and hinges (labeled as 7th floor) at compactor closet, 6th story, section at west

    Jan 29, 2026

    Closed — Violation closed
  • BHazardous

    Properly secure the loose lock set at fire door at east wall leading to stair b (labeled as 7th floor) at public hall, 6th story, section at west

    Jan 29, 2026

    Closed — Violation dismissed
  • BHazardous

    Properly secure the loose lock set at fire door at west wall leading to stair a (labeled as 7th floor) at public hall, 6th story, section at west

    Jan 29, 2026

    Closed — Violation dismissed
  • BHazardous

    Properly repair or replace the broken or defective latch set at compactor closet at public hall, 4th story

    Oct 31, 2025

    Closed — Violation dismissed
  • CImmediately hazardous

    Replace or repair the self-closing doors that is missing or defective latch set at compactor closet at public hall, 4th story

    Oct 31, 2025

    Closed — Violation closed
  • BHazardous

    Repair, replace or provide an approved and operational carbon monoxide detecting device, installed in accordance with applicable law and rules missing in the entire apartment located at apt 427, 4th story, 1st apartment from north at east , section at west

    Oct 31, 2025 · Apt 427

    Closed — Violation dismissed
  • BHazardous

    Provide security in the event of a power outage by means of an acceptable mechanical heavy duty lock and latch set at vestibule door at public hall, 1st story

    Nov 25, 2024

    Closed — Violation dismissed
See all 97 HPD violations (10 shown here)

DOB building violations · 63

  • No report and / or late filing (facade) facade required

    Failed to file fisp cycle 9b technical report by 2/21/2023

    Feb 22, 2023

    Dob violation - active
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 18, 2021

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 18, 2021

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 18, 2021

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 8, 2020

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 8, 2020

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 8, 2020

    Dob violation - resolved
  • Elevator affirmation of correction elevatorrequired

    Vio issued to elevator - fail to correct defects on 2017 cat 1 insp/tst tst

    Sep 6, 2019

    Dob violation - dismissed
  • Elevator affirmation of correction elevatorrequired

    Vio issued to elevator - fail to correct defects on 2017 cat 1 insp/tst tst

    Sep 6, 2019

    Dob violation - dismissed
  • Elevator affirmation of correction elevatorrequired

    Vio issued to elevator - fail to correct defects on 2017 cat 1 insp/tst tst

    Sep 6, 2019

    Dob violation - dismissed
See all 63 DOB violations (10 shown here)

ECB violations · 29

  • Class - 2

    Failure to maintain building facade and appurtenances. note:at time ofinspection observed at 1)south elevation,exposure#1;inadequate ac unitsupport on 2nd fl. (i)object stored on fire escape on 5th fl. 2)north

    Aug 18, 2020 · Penalty $1,250

    Resolve
  • Class - 2

    Failure to file an acceptable cycle 7 technical report in compliance with code provisions: periodic inspection of exterior walls & appurtenances as required by article 28-302 & the dept of bldgs rules & regulat

    Oct 21, 2014 · Penalty $400

    Resolve
  • Class - 2

    03x10,39y02,59y02,56y02,56y13,16#11. 03x10-emergency phone not working16##-replace worn heatch door pivots on numerous floors.

    Aug 7, 2013

    Resolve
  • Class - 1

    Sec. 3314.10.9 tiebacks shall be installed perpendicular to the face of the bldg or opposing angle tiebacks shall be installed. single tieback installed at an angle are prohibited. noted: suspended scaffolding

    Aug 1, 2013 · Penalty $1,600

    Resolve
  • Class - 2

    77b11,03x10,41t07. 77b11-replace to guard to 21" as per apendix k-3. 03x10-emergency phone in elevator phone in elevator elevator not working.

    Aug 29, 2011

    Resolve
  • Class - 2

    39y02,56y02,56y13,03x10,77b11,21d06. 03x10-emergency phone in elevatornot working. 77b11-replace toe guard to 21" as per appendix k3. 21d06-keeper on basement door unsecured.

    Aug 29, 2011

    Resolve
  • Class - 2

    42n10-remove by passed fuse from controller. 77b11-replace toe guard to 21 as per appendix k3. 21d06-unsecured keeper on lobby door. 03x10-emergency phone not working in elevator.

    Aug 29, 2011

    Resolve
  • Non-hazardous

    83x10.(83-x-10)elevator out of service repair/restore to service. rule rs 18 11-02

    Aug 22, 2006 · Penalty $500

    Resolve
  • Non-hazardous

    66z02/66z13/41a10 41-properly secure carbon contacts, remove tie wrapsholding these contacts together.

    Aug 16, 2006

    Resolve
  • Non-hazardous

    08a01,51b07,38q03,16a10,21l10,58e10.51b07-spin outs,38q03,missing covers,16a10-top floor door damaged by the keeper,keeper missing & screw. 21l0-basement lock causes problems,stalling elevator in the basement.

    Jul 18, 2006

    Resolve
See all 29 ECB violations (10 shown here)

Complaints

  • Heat/hot water

    Apartment only

    Oct 30, 2026 · Apt 427

    Open
  • Heat/hot water

    Apartment only

    Oct 27, 2026 · Apt 427

    Close
  • Heat/hot water

    Apartment only

    Oct 25, 2026 · Apt 427

    Close
  • Heat/hot water

    Apartment only

    Oct 23, 2026 · Apt 427

    Close
  • Appliance

    Electric/gas range

    Jun 23, 2026 · Apt 220

    Close
  • General

    Ventilation system

    Jun 23, 2026 · Apt 220

    Close
  • General

    Cabinet

    Jun 23, 2026 · Apt 220

    Close
  • Heat/hot water

    Apartment only

    Apr 10, 2026 · Apt 635

    Close
  • Heat/hot water

    Entire building

    Jan 25, 2026 · Apt BLDG

    Close
  • Heat/hot water

    Entire building

    Jan 25, 2026 · Apt BLDG

    Close
See all 233 HPD complaints (10 shown here)

Sales history

DatePriceTypeUnits
Jul 16, 2026Non-market transferCoops - elevator apartments—
Jul 16, 2026$261,820Coops - elevator apartments—
Jun 22, 2026Non-market transferCoops - elevator apartments—
Mar 31, 2026$245,000Coops - elevator apartments—
Nov 13, 2025$235,000Coops - elevator apartments—

Building details

Building type
Elevator apartment building (D4)
Year built
1955
Floors
6
Residential units
180
Building area
185,406 ft²
Lot area
61,600 ft²
Zoning
R4
Community board
408
Council district
24
Block / lot
6690 / 16
Assessed value
$6,982,650
Landmark / historic district
No

HPD registration #401497, last renewed Sep 14, 2026.

Questions about 149-05 79 Avenue

Who owns 149-05 79 Avenue?

The owner of record in NYC Department of City Planning PLUTO data is 149-05 Owners Corp.

Does 149-05 79 Avenue have violations?

Yes. NYC HPD has recorded 97 housing violations at this property.

Is 149-05 79 Avenue rent stabilized?

NYC Department of Finance tax bills listed 4 rent-stabilized units here in 2024 (about 2% of its 180 apartments). To confirm a specific apartment, request its rent history from NYS Homes and Community Renewal.

When was 149-05 79 Avenue built?

City records list 1955 as the year it was built.

How many apartments are in 149-05 79 Avenue?

It has 180 residential units and 182 units in total.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.