91-03 Whitney Avenue
Queens, NY 11373BBL 4-01552-0043Map
Owner of record: 91 Whitney Avenue Construction LLC
91-03 Whitney Avenue is an elevator apartment building built in 2018 in Queens, 11373. It has 20 residential units across 8 floors. The owner of record is 91 Whitney Avenue Construction LLC. HPD has recorded 28 housing violations here, most recently on August 7, 2022. 1 of the 28 most recent violations are still open. City tax records listed 10 rent-stabilized apartments here in 2024.
- HPD violations
- 28
- DOB violations
- 2
- ECB violations
- 47
- HPD complaints
- 35
What to know
Immediately hazardous issues among recent violations are still open.
Date of the most recent HPD inspection that found a problem.
No balance due on recent ECB violations.
Rent stabilization
Counts come from owners' rent-stabilization filings shown on NYC Department of Finance tax bills, as extracted by JustFix. They tell you a building has stabilized apartments, not which ones.
Think your apartment is stabilized? Request its rent history from HCR (free), then check your renewal with the renewal calculator.
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 28
- ANon-hazardous
Post and maintain a proper notice on wall of the entrance story in english and spanish on the availability of the agencys housing information guide. a sample notice can be found at www.nyc.gov/hpd. at public hall
Aug 7, 2022
Closed — Violation dismissed - ANon-hazardous
Post, in a form approved by the commissioner, and maintain a notice in a common area of the building regarding the procedures that should be followed when a gas leak is suspected at public hall
Aug 7, 2022
Closed — Violation dismissed - ANon-hazardous
Post and maintain a proper sign on wall of entrance story showing the registration number assigned by the department and the address of the building. at public hall
Aug 7, 2022
Closed — Violation dismissed - ANon-hazardous
Post a proper notice of carbon monoxide detecting device requirements, in a form approved by the commissioner, in a common area of a class a multiple dwelling near inspection certificate or provide notice to tenants in a private dwelling.
Aug 7, 2022
Closed — Violation dismissed - ANon-hazardous
Post a proper notice of smoke detector requirements, in a form approved by the commissioner, at or near the mail box missing at public hall
Aug 7, 2022
Closed — Violation dismissed - ANon-hazardous
§ 329, m/d law and dept. rules and regs. provide a completed certificate of inspection visits in a proper frame at or near mailboxes, bottom edge of frame between 48-62 inches above floor missing at public hall
Aug 7, 2022
Closed — Violation dismissed - CImmediately hazardous
Post notice, in form approved by the department, stating the name and location of the person designated by the owner to have key to buildings heating system missing at public hall
Aug 7, 2022
Open — Nov certified late - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Dec 6, 2017
Closed — Violation closed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Nov 23, 2016
Closed — Violation closed - CImmediately hazardous
Repair the broken or defective connection wasteline leaking at sink in the kitchen located at apt 3, 1st story, 1st apartment from south at west
Dec 9, 2015 · Apt 3
Closed — Violation closed
Show 18 more ↓
- BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color the walls and ceiling in the kitchen located at apt 3, 1st story, 1st apartment from south at west
Dec 9, 2015 · Apt 3
Closed — Violation closed - BHazardous
Properly repair the broken or defective light fixture at the west wall in the kitchen located at apt 3, 1st story, 1st apartment from south at west
Dec 9, 2015 · Apt 3
Closed — Violation closed - BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color the walls and ceiling in the bathroom located at apt 3, 1st story, 1st apartment from south at west
Dec 9, 2015 · Apt 3
Closed — Violation closed - CImmediately hazardous
Properly repair the source and abate the evidence of a water leak at the east wall and ceiling in the bathroom located at apt 3, 1st story, 1st apartment from south at west
Dec 9, 2015 · Apt 3
Closed — Violation closed - CImmediately hazardous
Trace and repair the source and abate the nuisance consisting of mold ... at the walls and ceiling ( east wall = approximately 8 square feet, ceiling = 16 square feet, north wall = 6 square feet) in the bathroom located at apt 3, 1st story, 1st apartment from south at west
Dec 9, 2015 · Apt 3
Closed — Violation closed - BHazardous
Replace with new the missing flushometer at the toilet in the bathroom located at apt 3, 1st story, 1st apartment from south at west
Dec 9, 2015 · Apt 3
Closed — Violation closed - CImmediately hazardous
Properly repair the broken or defective lock and assembly at entrance door to building. , 1st story
Dec 9, 2015
Closed — Violation closed - BHazardous
Provide adequate lighting at or near the outside of the front entranceway of the building and keep same burning from sunset every day to sunrise on the day following 100 watts at south entrance to building
Dec 9, 2015
Closed — Violation closed - BHazardous
Provide adequate lighting at the vestibule area , 1st story
Dec 9, 2015
Closed — Violation closed - BHazardous
Repair or replace the carbon monoxide detecting device(s). inoperable located at apt 3, 1st story, 1st apartment from south at west
Dec 9, 2015 · Apt 3
Closed — Violation closed - BHazardous
Repair or replace the smoke detector inoperable located at apt 3, 1st story, 1st apartment from south at west
Dec 9, 2015 · Apt 3
Closed — Violation closed - BHazardous
Properly repair with similar material the broken or defective all walls and ceiling at the vestibule area , 1st story
Dec 9, 2015
Closed — Violation closed - CImmediately hazardous
Properly repair the source and abate the evidence of a water leak ceiling at the vestibule area , 1st story
Dec 9, 2015
Closed — Violation closed - ANon-hazardous
Paint with light colored paint to the satisfaction of this department the vestibule walls and ceiling , 1st story
Dec 9, 2015
Closed — Violation closed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Oct 16, 2015
Closed — Violation dismissed - BHazardous
Properly repair the broken or defective lock set at entrance door from vetibule at public hall, 1st story
May 15, 2015
Closed — Violation closed - ANon-hazardous
Post and maintain a proper notice on wall of the entrance story in english and spanish on the availability of the agencys housing information guide. a sample notice can be found at www.nyc.gov/hpd. at public hall, 1st story
May 15, 2015
Closed — Violation closed - BHazardous
Fire egress defective. remove obstructing bars or unlawful gates from at least 1 window or provide approved type gate .. in the entire apartment located at apt 3, 1st story, 1st apartment from west at north
Jan 5, 2010 · Apt 3
Closed — Violation closed
DOB building violations · 2
- Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2016 inspection report
Apr 6, 2018
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2015 inspection report
Feb 24, 2017
Dob violation - dismissed
ECB violations · 47
- Class - 1
Failure to maintain/display on site documents(docs to be kept on site)at time of inspection competent person could not provide orientation logs,pre-shift meetings log and tool box talks when requested.all docum
May 29, 2020 · Penalty $625
Resolve - Class - 2
Failure to comply with dot regulations,dot permit.at time of inspection on an active 8 story new building observed debris container parks atexposure#2 of job site.after reviewing dot observe no yo-docks placed
May 29, 2020 · Penalty $1,250
Resolve - Class - 2
Slipping and tripping hazards-should be minimized unit summons 3303.4.1.1 and 3383.4.12 at time of inspection on nb 8 sty: i observed workeron second floor doing tiling in hallway cables and debris can be seen
May 20, 2020 · Penalty $625
Resolve - Class - 1
Bc 3303.7.2 fire extinguishers-fire extinguishers shall be provided in accordance with the new york city fire code.at time of inspection of nb 8 sty.i observed fire extinguishers(2) on main roof not properly se
May 20, 2020 · Penalty $312
Resolve - Class - 1
Permit holder failed to produce for inspection the daily log that is required by bc 3321.2, item 4. remedy: comply with code
Mar 4, 2020 · Penalty $2,500
Resolve - Class - 2
Bc3307.6.5.10=daily inspection sidewalk shed log.at the time of inspection on an active jobcitse currently at roof level i observed sidwalk shed installed at exposure 1 and 2 upon my request for daily log for
Jan 27, 2020
Resolve - Class - 2
No storage on shed at the time of inspection on an active jobsite currently at roof level i observed material parts and wood of exposure 1 and 4.removed storage from on top of sidewalk shed
Jan 27, 2020 · Penalty $2,400
Resolve - Class - 1
Failure to instistute guardrails at time of my inspection of a an 8 story building i observed that all of the the elevator shafts(8) did not have guardrails in place there was also missing guardrails at the top
Oct 28, 2019 · Penalty $12,500
Resolve - Class - 1
3314.1.failure to provide supp scaffold as per code.at the time of inspection 8sty nb active site,observed supp scaffold approx 70ft high atexposures1,2,3,where 5fully planked platforms was in place.also some p
Oct 18, 2019 · Penalty $6,250
Resolve - Class - 1
Failure to provide const super when required by code.at the time of inspection,8story building nb active site approx 15 workders perform their job.after reviewed jobsite log observed,const super last time came
Oct 18, 2019 · Penalty $12,500
Resolve
Show 37 more ↓
- Class - 2
3314.4.3.2.1.installation inspection reports.at the time of inspection 8story nb active site observed approx 70ft hight supp scaffold in placed where 5 fully planked decks was in placed without dd mentioned tha
Oct 18, 2019
Resolve - Class - 2
28-103.8 matters not provided for embedded fall arrest system logs. asnoted: @time of inspection on an active const site, observed (wes) device fall arest system installed w slabs (2 sty c.i.p structure)-failed
Aug 16, 2019
Resolve - Class - 1
Inadequate egress from working floor.at time of inspection of an 8 story nb under construction,i observed that there was a single ladder leading into/out of the working floor/8th fl.i observed no other means of
Jul 23, 2019 · Penalty $10,000
Resolve - Class - 1
Work doesn't conform to approved const.docs.and/or amendments-form work.@time of inspection of an 8 story nb under construction,i observed const,form work on the 8th fl.& roof.upon review of the provided form w
Jul 23, 2019 · Penalty $2,500
Resolve - Class - 1
Bc 3314.1 supported scaffold not built/installed in code-compliant manner.at time of inspection of an 8 story nb under construction,i observed a supported scaffold @exps#'s 1.2.3&4 with the following conditions
Jul 23, 2019 · Penalty $2,500
Resolve - Class - 1
Failure to designate/have competent person on site when required.at time of inspection of an 8 story nb under construction,i asked several workers on site about the competent person.a worker who identified hims
Jul 23, 2019 · Penalty $10,000
Resolve - Class - 1
Bc 3301.2failure to institute safety measures at construction site-ho les/penetrations.at time of inspection of an 8 story nb under construction,i observed multiple holes/penetrations in the concrete slabs that
Jul 23, 2019 · Penalty $625
Resolve - Class - 1
Work w/o a permit-needle beam platform.at time of inspection of an 8 story nb.under construction,i observed a needle beam platform @exp#4 with a supported scaffold installed on top of it.upon review of dept.rec
Jul 23, 2019 · Penalty $1,250
Resolve - Class - 1
Work doesn't conform to approved const.docs.and/or amendments.needle beam platform.@time of inspection of an 8 storey nb under construction i observed a needle beam platform @exp#4 with a scaffold installed on
Jul 23, 2019 · Penalty $625
Resolve - Class - 2
Bc 3301.13.13 inadequate jobsite log book.at time of inspection of an 8 story nb under construction,i reviewed the construction super's jobsite logs.upon review,i observed that one entry was missing a signature
Jul 23, 2019 · Penalty $625
Resolve - Class - 1
Work doesn't conform to approved const.docs.and/or amendments.temporary platforms.@time of inspection of an 8 story nb under construction,i observed temporary platforms in elevator shafts,at all fls.upon review
Jul 23, 2019 · Penalty $2,500
Resolve - Class - 1
Failure to maintain safety equipment measures or temporary construction-guardrails.at the time of inspection of a new 8 story bld.under construction,i observed guardrails thru-out site with the foll:conditions-
Jul 23, 2019 · Penalty $2,500
Resolve - Class - 2
Pedestrian protection does not meet code specification.at time of inspection of an 8 story nb under construction,i observed that the sidewalk shed @exp2 was not extended as required.sws footing inadequate.no hi
Jul 23, 2019 · Penalty $5,000
Resolve - Class - 1
Failure to maintain/display on site docs.required by chapter 33.at time of inspection of an 8 story nb under construction,i observed roof protection on the adjacent bld.@exp#4,as well as overhead protection in
Jul 23, 2019 · Penalty $1,250
Resolve - Class - 2
Work does not conform to approved cont documents and/or approved amendments @the time of inspection @ 8 sty new building. work in progress currently @ 5 floor. i observed roof protection @exp#4 does not conform
May 29, 2019
Resolve - Class - 2
Job fence not constructed or maintained pursuant to subsection.@the time of inspection i observed active const site, work in progress. constfence in place, missing flexiglass in (vertical panel), not in
May 29, 2019
Resolve - Class - 2
Permit holder/employer failed to ensure each construction worker successfully completed the require training under bc3321.1. noted: observednoberto manzano at a bldg site for which a construction superintendent
Mar 13, 2019 · Penalty $1,250
Resolve - Class - 1
Failure to provide sidewalk shed where required. noted: at time of inspection i observed nb bldg in construction progress proposed stores is8 sty current stories is 3rd fl slab or elev 18'-9" the contractor fai
Mar 13, 2019 · Penalty $2,500
Resolve - Class - 1
Sec. 3301.7 failure to provide drawings for work platform. noted: at time of inspection i observed nb bldg in construction progress w/no design drawings for work platform in place or exp#4. pswo issued stop all
Mar 13, 2019 · Penalty $2,500
Resolve - Class - 1
Permit holder/employer failed to ensure each construction worler successfully completed the require training under bc 3321.1. noted: observed juan hernandez at a bldg site for which a construction superintenden
Mar 13, 2019 · Penalty $1,250
Resolve - Class - 2
Permit holder/employer failed to ensure each construction worker successfully completed the required training under bc 3321.1. noted: observed alan jerry calk guell at a bldg site for which a construction super
Mar 13, 2019 · Penalty $1,250
Resolve - Class - 2
Permit holder/employer failed to ensure each construction worker successfully completed the require training under bc3321.1. noted: observed dony chao he at a bldg site for which a construction. remedy: comply
Mar 13, 2019 · Penalty $1,250
Resolve - Class - 1
Failure to maintain adequate housekeeping per section requirements. note: at time of inspection i observed active site w/poor housekeeping. throughout the site creating a unsanitary slipping & tripping hazard
Mar 13, 2019 · Penalty $625
Resolve - Class - 2
Permit holder/employer failed to ensure each construction worker successfully completed the require training under bc3321.1. noted: observed natividad vazquez at a bldg site for which a construction superintend
Mar 13, 2019 · Penalty $1,250
Resolve - Class - 2
Permit holder/employer failed to ensure each construction worker successfully completed the require training under bc3321.1. noted: at time of inspection i observed lin chong jian at a bldg site for which a con
Mar 13, 2019 · Penalty $1,250
Resolve - Class - 1
Sec. 3309.1 failure to protect adequately protect adjoining properties during construction. noted: at time of inspection i observed nb bldg in construction progress w/o adequate protection in place to protect
Mar 13, 2019 · Penalty $625
Resolve - Class - 1
Permit holder/employer failed to ensure each construction worker successfully completed the require training under bc 3321.1. noted: observed alon jerry calk guell at a bkdg site for which a construction superi
Mar 13, 2019 · Penalty $1,250
Resolve - Class - 1
Permit holder/employer failed to ensure each construction worker successfully completed the require training under bc3321.1. noted: observednorberto manzano at a bldg site for which a construction superintenden
Mar 13, 2019 · Penalty $1,250
Resolve - Class - 1
Permit holder/employer failed to ensure each construction worker successfully completed the require training under bc3321.1. noted: observed natividad vazquez at a bldg site for which a construction superintend
Mar 13, 2019 · Penalty $1,250
Resolve - Class - 1
Permit holder/employer failed to ensure each construction worker successfully completed the required training under bc 3321.1. noted: observed dony chao he at a bldg site for which a construction superintendent
Mar 13, 2019 · Penalty $1,250
Resolve - Class - 1
Permit holder/employer failed to ensure each construction worker successfully completed the required training under bc 3321.1. noted: at time of inspection i observed lin cheng jian at a bldg site for which a
Mar 13, 2019 · Penalty $1,250
Resolve - Class - 2
Permit holder/employer failed to ensure each construction worker succedssfully completed the required training under bc-3321.1. noted: observed borerge saul pacheco at a bldg site for which a construction super
Mar 13, 2019 · Penalty $1,250
Resolve - Class - 2
Permit holder/employer failed to ensure each construction worker successfully completed the require training under bc3321.1. noted: at time of inspection i observed juan hernandez at a bldg site for which a con
Mar 13, 2019 · Penalty $1,250
Resolve - Class - 1
Sec. 3301.1 failure to comply w/osha standards. noted: at time of inspection i observed nb bldg in constuction progress w/the live electrical line for the adjacent property running less than 10 feet from the nb
Mar 13, 2019 · Penalty $2,500
Resolve - Class - 1
Permit holder/employer failed to ensure each construction worker successfully completed the require training under bc3321.1. noted: observedbonerge saul pacheco at a bldg site for which a construction superinte
Mar 13, 2019 · Penalty $1,250
Resolve - Class - 1
Failure to safeguard all persons or property affected by construction operations. as noted:at time of inspection at an active construction site. rebar placement at floor#2 to floor#3,observed at exposure #4,fai
Feb 25, 2019 · Penalty $10,000
Resolve - Non-hazardous
Use of storage dwelling w/storage cellar changed to use of cellar as living quaters. remedy: discontinue use of cellar as living quarters
Jun 6, 1988
Resolve
Complaints
- General
Bell/buzzer/intercom
Jul 21, 2026 · Apt 7B
Close - Heat/hot water
Apartment only
Feb 3, 2026 · Apt 4A
Close - Door/window
Window frame
Feb 3, 2026 · Apt 4A
Close - Water leak
Heavy flow
Jan 10, 2024 · Apt 7B
Close - Door/window
Door frame
May 31, 2022 · Apt 4A
Close - Flooring/stairs
Floor
May 31, 2022 · Apt 4A
Close - Heat/hot water
Entire building
Mar 3, 2022 · Apt BLDG
Close - Door/window
Window frame
Jan 22, 2022 · Apt 4A
Close - Heat/hot water
Apartment only
Jan 22, 2022 · Apt 4A
Close - Electric
No lighting
Dec 8, 2015 · Apt 3
Close
Show 25 more ↓
- Heat/hot water
Apartment only
Dec 8, 2015 · Apt 3
Close - Plumbing
Basin/sink
Dec 8, 2015 · Apt 3
Close - Door/window
Door
Dec 8, 2015 · Apt 3
Close - Door/window
Door
Jan 9, 2015 · Apt BLDG
Close - Door/window
Door
Dec 19, 2014 · Apt 9
Close - Heat/hot water
Apartment only
Jun 12, 2014 · Apt 7
Close - Heating
Heat related
Mar 7, 2014 · Apt 4
Close - Heating
Heat related
Dec 30, 2010 · Apt 3
Close - Heating
Heat related
Dec 19, 2009 · Apt 3
Close - Nonconst
Carbon monoxide
Jun 22, 2007 · Apt 3
Close - Nonconst
Smoke detector
Jun 22, 2007 · Apt 3
Close - General
Windows
Jun 22, 2007 · Apt 3
Close - Electric
Wiring
Jun 22, 2007 · Apt 3
Close - General
Locks
Jun 22, 2007 · Apt 3
Close - Heating
Heat related
Jun 22, 2007 · Apt 3
Close - Nonconst
Vermin
Jun 22, 2007 · Apt 3
Close - Nonconst
Vermin
Jun 22, 2007 · Apt 3
Close - Plumbing
Toilet
Jun 22, 2007 · Apt 3
Close - General
Mold
Jun 22, 2007 · Apt 3
Close - Plumbing
Bathtub/shower
Jun 22, 2007 · Apt 3
Close - Paint/plaster
Ceiling
Jun 22, 2007 · Apt 3
Close - Heating
Heat related
Feb 19, 2005 · Apt 4
Close - Heating
Heat related
Nov 13, 2004 · Apt 4
Close - Appliance
Sprinker cert
Jul 26, 2004
Close - Heating
Heat related
Apr 3, 2004 · Apt 4
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Elevator apartment building (D1)
- Year built
- 2018
- Floors
- 8
- Residential units
- 20
- Building area
- 18,361 ft²
- Lot area
- 5,000 ft²
- Zoning
- R7B
- Community board
- 404
- Council district
- 21
- Block / lot
- 1552 / 43
- Assessed value
- $2,019,150
- Landmark / historic district
- No
HPD registration #433763, last renewed Jul 21, 2026.
Questions about 91-03 Whitney Avenue
Who owns 91-03 Whitney Avenue?
The owner of record in NYC Department of City Planning PLUTO data is 91 Whitney Avenue Construction LLC.
Does 91-03 Whitney Avenue have violations?
Yes. NYC HPD has recorded 28 housing violations at this property.
Is 91-03 Whitney Avenue rent stabilized?
NYC Department of Finance tax bills listed 10 rent-stabilized units here in 2024 (about 50% of its 20 apartments). To confirm a specific apartment, request its rent history from NYS Homes and Community Renewal.
When was 91-03 Whitney Avenue built?
City records list 2018 as the year it was built.
How many apartments are in 91-03 Whitney Avenue?
It has 20 residential units.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.