23-09 Broadway is an elevator apartment building built in 2021 in Queens, 11106. It has 10 residential units across 7 floors. The owner of record is Everest 2309 Broadway LLC. HPD has recorded 2 housing violations here, most recently on May 11, 2026. 2 of the 2 most recent violations are still open. City tax records listed 3 rent-stabilized apartments here in 2024.
- HPD violations
- 2
- DOB violations
- 1
- ECB violations
- 22
- HPD complaints
- 1
What to know
No open immediately-hazardous violations among recent records.
Date of the most recent HPD inspection that found a problem.
No balance due on recent ECB violations.
Rent stabilization
Counts come from owners' rent-stabilization filings shown on NYC Department of Finance tax bills, as extracted by JustFix. They tell you a building has stabilized apartments, not which ones.
Think your apartment is stabilized? Request its rent history from HCR (free), then check your renewal with the renewal calculator.
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 2
- ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
May 11, 2026
Open — Nov sent out - ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
Jun 16, 2025
Open — Nov sent out
DOB building violations · 1
- Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Mar 2, 2022
Dob violation - dismissed
ECB violations · 22
- Class - 2
Failure to safeguard all persons and property affected by construction operations. at time of inspection observed adjoining property at 23-11 broadway roof (exit) has been compromised due to construction materi
May 24, 2022 · Penalty $625
Resolve - Class - 1
Unsafe storage of combustible material&equipment.noted:ato my insp of n7styb const in progress,bldg topped off,aprx3workers onsite,i observed upon entering cellar in rm were 4portable 125000btu heaters,stacked
Apr 6, 2022
Resolve - Class - 2
Sec. 28-105.12.8 site conditions contrary to site safety plan-staging area. noted: at time of my inspection of a new 7 sty bldg constructionin progress,bldg topped off,i observed the staging area at exp#1 was
Dec 2, 2021 · Penalty $1,250
Resolve - Class - 1
Unsafe storage of combustible material. noted: at time of my inspection of a new 7 sty bldg,construction in progress,bldg topped off,approx 10 workers on site,i observed a plastic 5 gallon container of gasoline
Dec 2, 2021
Resolve - Class - 2
Work platforms-no design drawings. noted: at time of my inspection of a new 7 story building construction in progress, building topped off, approx 6 workers on site. i observed 2 platforms on the 6/7 floors app
Sep 28, 2021
Resolve - Class - 2
Inadequate site safety plan. noted: at time of my inspection of a new 7 story building, construction in progress, building topped off, i asked to review the site safety plan. the current site conditions had a s
Sep 28, 2021
Resolve - Class - 1
Failure to institute/maintain safety equipment measures or tem. construction-no/inadequate guardrails. noted: at time of my inspection of a new 7 story building construction in progress, building topped off, i
Sep 28, 2021 · Penalty $2,500
Resolve - Class - 2
Failure to maintain/display on site documents required by chapter-33. noted: at time of my inspection of a new 7 storty building, construction in progress building topped off, i observed a supported scaffold of
Sep 28, 2021
Resolve - Class - 2
Observed on 9/22/21 at 1010 am electrical work in progress for the installation of bx wiring on the 5th floor. worker kevin jones was observed installing bx wiring in the ceiling . temporary lighting was also o
Sep 22, 2021
Resolve - Class - 2
Bc3301.13.13 log book. note:at time of inspection of proposed 7 story new building upon request for super log book to verify compliance with code and presence of superintendent on site none was provided.remedy:
Jun 15, 2021
Resolve
Show 12 more ↓
- Class - 2
Bc3309.10 protection of roofs.note:at the time of my inspection proposed 7 story new bldg observed that roof protection or adjacent propertyat exp.#4 inadequate(chimney vent pipes & parapet not protected).failu
Jun 15, 2021
Resolve - Class - 1
Work does not conform to approved construction documents.at the time of my inspection of a proposed 7 story new bldg observed needle beams not connected to the slab w/l4 x 4 x 3/8 angle which is contrary to ap
Jun 15, 2021
Resolve - Class - 1
3301.2 failure to provide safety equipment or inform workers of dangeraffected by construction operations.note:at the time of my inspection of a proposed 7 story new bdlg i observed no guardrails on roof level
Jun 15, 2021 · Penalty $2,500
Resolve - Class - 2
3307.2.1 obstruction of sts or sidewalks(failure to comply w/dot regs)@time of my insp of closed&permitted jobsite,i observed@exp1 st level debris dumpster along w/yodock temp barrier system&partially installed
Mar 8, 2021
Resolve - Class - 2
Jobsite fence constructed or maintained pursuant to subsec @time of myinsp on closed&permitted jobsite,i observed that permit holder failed to maintain jobsite fence@exp1 which was installed to rear of adjacent
Mar 8, 2021
Resolve - Class - 1
Documents to be kept onsite at time of my inspection on an active nb-jobsite observed that the competent person did not have all required documents as stipulated on this section.specifically the competent perso
Feb 25, 2021 · Penalty $1,250
Resolve - Class - 1
Protection of adjacent property(roof protection)at time of my inspection on an active nb-jobsite at fifth floor level.observed that the contractor failed to installed roof protection for adjacent property at ex
Feb 25, 2021 · Penalty $2,500
Resolve - Class - 2
Failure to obtain a temporary construction permit prior to installation/use of temporary construction equipment(fence).at time of my inspection on an active nb-jobsite at fifth floor level.observed that there w
Feb 25, 2021 · Penalty $625
Resolve - Class - 2
Work after hours contrary to variance permit.note:at the time of my inspection of an active jobsite where worker were performing superstructure operation.review of department records shows that the permit for t
Jan 30, 2021 · Penalty $625
Resolve - Class - 1
Permit holder failed to ensure all workers receive site safety orientation.note:at the time of my inspection of an active jobsite i observedapproximately 15 workers performing construction activity onsite.upon
Jan 30, 2021 · Penalty $625
Resolve - Class - 1
Permit holder employer failed to ensure that each construction or demolition worker working/engaged at the site successfully completed training under bc 3321.1. i observed muhammad qureshi working at the site w
Jan 26, 2021 · Penalty $1,250
Resolve - Class - 1
Owner failed to ensure that each construction or demolition worker working/engaged at the site successfully completed the required training under bc 3321.1. i observed muhammad qureshi working at the site w/o a
Jan 26, 2021 · Penalty $1,250
Resolve
Complaints
- Unsanitary condition
Garbage/recycling storage
Oct 15, 2026 · Apt BLDG
Open
Sales history
No recorded sales in our data
Building details
- Building type
- Elevator apartment building (D7)
- Year built
- 2021
- Floors
- 7
- Residential units
- 10
- Building area
- 14,301 ft²
- Lot area
- 3,979 ft²
- Zoning
- R6A
- Community board
- 401
- Council district
- 22
- Block / lot
- 567 / 21
- Assessed value
- $1,122,300
- Landmark / historic district
- No
HPD registration #434455, last renewed Jul 7, 2025.
Questions about 23-09 Broadway
Who owns 23-09 Broadway?
The owner of record in NYC Department of City Planning PLUTO data is Everest 2309 Broadway LLC.
Does 23-09 Broadway have violations?
Yes. NYC HPD has recorded 2 housing violations at this property.
Is 23-09 Broadway rent stabilized?
NYC Department of Finance tax bills listed 3 rent-stabilized units here in 2024 (about 30% of its 10 apartments). To confirm a specific apartment, request its rent history from NYS Homes and Community Renewal.
When was 23-09 Broadway built?
City records list 2021 as the year it was built.
How many apartments are in 23-09 Broadway?
It has 10 residential units and 11 units in total.