1515 Surf Avenue is an elevator apartment building built in 2022 in Brooklyn, 11224. It has 324 residential units across 26 floors. The owner of record is Sirena Realty Corp.. HPD has no housing violations on record for this property. City tax records listed 463 rent-stabilized apartments here in 2024.

HPD violations
0
DOB violations
11
ECB violations
49
HPD complaints
13

Available now in this building

Show 2 more ↓

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

Rent-stabilized units in 2024
463
About 100% of the building's 324 apartments

Counts come from owners' rent-stabilization filings shown on NYC Department of Finance tax bills, as extracted by JustFix. They tell you a building has stabilized apartments, not which ones.

Stabilized units by tax-bill year

Think your apartment is stabilized? Request its rent history from HCR (free), then check your renewal with the renewal calculator.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 11

  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 11, 2024

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 11, 2024

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 11, 2024

    Dob violation - dismissed
  • Construction other optional

    Fail2perform standrd curing specmn:obsrvd 1/23/24@fenagh llc inspctn, temps of final curing tanks were 51-53degrees f,well outside limit of 73.5 +- 3.5f&temp recordrs disconctd from tanks&dry to touch. remedy: comply w codes&req astm stndrds.eor revw non-conformnce,submt s/s w alternate test results by 5/31/24

    Mar 8, 2024

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 4, 2023

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 4, 2023

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 4, 2023

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 4, 2023

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 4, 2023

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 4, 2023

    Dob violation - dismissed
Show 1 more ↓
  • Failure to benchmark none

    Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4

    May 2, 2023

    Dob violation - dismissed

ECB violations · 49

  • Class - 1

    Cease use item: inoperative zone lock restrictors class 2 item: unreadable main line fuses.

    Feb 24, 2026 · Penalty $1,250

    Resolve
  • Class - 1

    Observed active site with two workers performing work inside storage zone using mini loader, upon request from them for ssm designated on site, they all stated he is not here. no ssm was on site after waiting o

    Aug 18, 2024 · Penalty $12,500

    Resolve
  • Class - 1

    Bc3303.4.7 storage near sidewalks. observed unsafe storage zone at exp#1&2. manlift stored adjacent to a sidewalk exp#2 and materials stored adjacent to the sidewalk, blocking pedestrian sidewalk exp#1 higher t

    Aug 18, 2024 · Penalty $5,000

    Resolve
  • Class - 1

    Failure to obey vacate order from commissioner as per 28-207.4.note:at time of inspection observed aread that was ordered to vacate on vio #01052024sr1307ns was occupied with parked vehicles.remedy:comply with

    Jun 4, 2024

    Resolve
  • Class - 1

    Observed at 7 floor set back exp# 1& 2 no guardrail and handrail provided also the 8 floor set back inadequate guardrail missing netting. creates a potential hazard for fallsstop all exterior work at 7 floor se

    Mar 29, 2024 · Penalty $5,000

    Resolve
  • Class - 1

    Bc 3314.1 observed pipe scaffold installed at 22 thru 24 floor exp# 2 & 3 balconies and first floor exterior exp #1 no guardrail system in place and planks not secured(tie off)stop at work on pipe scaffold

    Mar 29, 2024 · Penalty $5,000

    Resolve
  • Class - 1

    Response to incident where a worker(jacqueline bareiroleiva) cut her hand while using spackle knife for tapping, upon request from ssm and site construction super for injured worker site safety orientation, the

    Mar 27, 2024 · Penalty $2,500

    Resolve
  • Class - 1

    3301.6.2 design requirements multiple active unsafe platform upon request for d.d non was provided, one consisting of scaffold frame with alum platform resting on 2nd fl stair wall covered with unsecured plywoo

    Mar 27, 2024 · Penalty $5,000

    Resolve
  • Class - 1

    Response to incident were worker cut her hand by spackle knife while tapping on 3/26/2024 around 2:00 pm. inspection revel that site safety manger who signed the daily logs on the day of the incident failed to

    Mar 27, 2024

    Resolve
  • Class - 1

    At the time of inspection on an active job site currently at roof level. i observed at 9th floor exposure 3 set back that no guard rail system was in place creating a potential fall hazardous condition on site

    Mar 13, 2024 · Penalty $5,000

    Resolve
Show 39 more ↓
  • Class - 1

    At time of inspection of an active job site, building currently is 16 story partially enclosed and topped off at roof level. while responding to an incident where a worker fell off a ladder injuring himself in

    Nov 16, 2023 · Penalty $2,530

    Resolve
  • Class - 1

    At the time of my inspection of an active new building 26 stories 266 feet high structure, i observed a worker on the leading edge of a terrace on the 17 th floor at exposure 1 without any fall protection syste

    Sep 20, 2023 · Penalty $2,530

    Resolve
  • Class - 1

    In responding to an incident reporting by site safety manager, investigation revile that two workers were caring sheet rock upstairs when they slip and the sheetrock fell on the one at the back, failure to saf

    Jul 10, 2023 · Penalty $12,500

    Resolve
  • Class - 1

    At the time of my inspection of a 26 story new building construction work in progress, i observed suspended scaffold on site at exposure # 1, upon request for rigging foreman to supervise suspended scaffold ope

    May 5, 2023 · Penalty $5,030

    Resolve
  • Class - 1

    At the time of my inspection of a 26 story new building construction work in progress, i observed suspended scaffold on site at exposure # 1, upon request for rigging foreman to supervise suspended scaffold ope

    May 5, 2023 · Penalty $2,530

    Resolve
  • Class - 1

    At time of inspection, tower crane cd 5582 cn 3022 was on site with an expired cd fee date. the cd fee date was 03/16/2023 at time of inspection. this fee is required to maintain validity of the certificate of

    Apr 26, 2023 · Penalty $5,000

    Resolve
  • Class - 1

    Contractor sheds and offices. observed contractor sheds built within a building being constructed not as per code. observed 4 contractor sheds/shanties not 30 feet apart as required by code. this condition crea

    Apr 19, 2023 · Penalty $2,530

    Resolve
  • Class - 1

    During inspection, i observe the guardrail system on multiple floors had unsafe conditions, including loose posts, nettings, cables, uncapped rebar on the walkways, and uncovered holes throughout the floors. to

    Apr 15, 2023 · Penalty $2,530

    Resolve
  • Class - 2

    Equipment on the worksite must follow manufacturer specifications and the code. violations include cantilever and standalone formwork not installed per the manufacturer's drawings, missing or improperly install

    Apr 15, 2023 · Penalty $3,125

    Resolve
  • Class - 1

    The purposed 26-story mixed-use building violated code section 3305.3.4 by failing to perform necessary formwork observation. additionally, there were no inspection logs available as per section 3305.3.3.1, and

    Apr 15, 2023 · Penalty $12,500

    Resolve
  • Class - 2

    Observed plastic barriers with chain link fence at exp#4 and barriers only at exp#2 not as per manufacture specifications, observed barriers not locked in place, not filled out with water as required. make it e

    Mar 25, 2023 · Penalty $1,280

    Resolve
  • Class - 1

    In responding to an incident reported by the site safety manager that worker was water proofing window sill and jams at the 11 floor on a bakers scaffold when he lost his balance and fell approximately 3 feet,

    Mar 17, 2023 · Penalty $5,030

    Resolve
  • Class - 1

    At the time of my inspection of a 26 story new building construction work in progress. upon request for the fire safety manager and waited for about 1 hour no fire safety manager was at job site. this creates

    Mar 17, 2023 · Penalty $2,530

    Resolve
  • Class - 1

    Failed to notify the dept of an incident that resulted in a fatality or injury. note:a window panel was placed on a worker foot the worker walked to urgent care. as per check of the dept records the permit hold

    Mar 13, 2023 · Penalty $5,030

    Resolve
  • Class - 1

    While operating the tower crane the operator caused the hookblock to hit the boom/jib because he did not have enough height to work with overiding the anti 2 block limits causing damages to lacings/chord which

    Mar 8, 2023

    Resolve
  • Class - 1

    Inspection of an 26 story building with work in progress, observed worker on 10th floor cutting metal stud with a saw (hilti ) and using a trash contrainer as a work station. upon review manufacturer spec worke

    Mar 3, 2023 · Penalty $2,530

    Resolve
  • Class - 1

    Inspection of an 26 story building with work in progress, obseverd at 21 floor to 22 floor escape hatch when heating floor. upon review escape hatch were made outof plywood and plastic tarp not metal as per

    Mar 3, 2023 · Penalty $2,530

    Resolve
  • Class - 2

    I observed a non-active jobsite with unsafe storage of materials, exp 1, in the street, contrary to dot req. unlinked/missing chain link fence/yodocks, const materials, dumpster open to public.; 3307.2, comply

    Feb 7, 2023 · Penalty $1,280

    Resolve
  • Class - 1

    Observed horizontal netting system installed not as per design drawings provided. horizontal netting was secured to vertical netting system instead of a concrete slab as shown on drawings. also observed horizon

    Feb 6, 2023 · Penalty $2,530

    Resolve
  • Class - 2

    In response to incident where a work was injured. inspection reveal that worker was climbing a 10 feet ladder with a bale of cables in one hand. worker failed to maintain 3 point of contact while climbing, and

    Dec 16, 2022 · Penalty $5,030

    Resolve
  • Class - 1

    Failure to provide escape hatch. observed temporary heating equipment in use on a 11th story level, to provide temporary heating for concrete placement. no escape hatch provided for operation as required by cod

    Dec 16, 2022 · Penalty $2,530

    Resolve
  • Class - 1

    Horizontal safety netting. observed no horizontal safety netting provided on a 6th story level at exp#3, 2 floors below stripping floor. horizontal safety netting was not jumped to 6th story level as required b

    Dec 16, 2022 · Penalty $2,530

    Resolve
  • Class - 1

    Failed to notify the dept of an incident that resulted in a fatality or injury. note:a worker tripped on stored lumber. the worker suffered a back injury. worker was taken to hospital. as per check of the dept

    Oct 20, 2022 · Penalty $5,030

    Resolve
  • Class - 1

    Inspection of an 26 story building with work in progress respondent to a complaint where and individual were walking with a 4 inch pipe have land on his feet. i observed worker have to travel over shoring, and

    Sep 15, 2022 · Penalty $6,250

    Resolve
  • Class - 1

    At the time of my inspection of an 26 story building at 4 floor with work in progress, i observed site safety concrete manager on site with expire license on september 09,2022 with no extension . upon review de

    Sep 15, 2022

    Resolve
  • Class - 1

    At the time of my inspection of a proposed 26 story new building observed inadequate housekeeping which create an unsafe conditions for workers and personnel accessing site

    Sep 1, 2022 · Penalty $6,250

    Resolve
  • Class - 1

    At the time of my inspection responding to incident with worker ramirez herrera silvestre after review site safety manager log book and department records reveal that ssm herbert miller failed to immediately no

    Sep 1, 2022 · Penalty $2,500

    Resolve
  • Class - 1

    At the time of my inspection observed excavation approximately 20 ft depth with inadequate guardrail system which create an unsafe conditions.provide adequate guardrail system

    Sep 1, 2022 · Penalty $6,250

    Resolve
  • Class - 2

    Jobsite fence not const or maintained pursuant to subsec as noted:atoi@active jobsite in excavation phase of proposed26styb observed overalldepth of excavation aprx15'd.observed@exp4 neighboring property comple

    Aug 23, 2022

    Resolve
  • Class - 1

    Failure to institute/maintain safety equipment measures or temp const-guardrail system during excavation.as noted:atoi@active jobsite in excavation phase of proposed26styb,observed overall depth of excavation a

    Aug 23, 2022 · Penalty $5,030

    Resolve
  • Class - 1

    Failure to provide protection@sides of excavation as noted:atoi@activejobsite in excavation phase of proposed 26styb,i observed large excavated area@exp1,which was aprx6'd w/workers in hole.i also observed that

    Aug 23, 2022 · Penalty $5,030

    Resolve
  • Class - 1

    No site specific formwork design drawings present per 3301.7.as noted at time of inspection at an active construction site,observed concretefloors supported by concrete shear walls and columns up to 8th floor.

    Aug 12, 2022 · Penalty $6,250

    Resolve
  • Class - 1

    No site specific formwork design drawings present per 3301.7.as noted at time of inspection at an active construction site observed concreteplacement of 3rd floor slab partial.3rd floor concrete slab is support

    Aug 12, 2022 · Penalty $6,250

    Resolve
  • Class - 1

    2104.6 failure to provide masonry cmu wall construction bracing accordance with tms 602/aci 5301.1/asce 6 section 3.3.e.as noted at time of inspection at an active construction site on 8th floor level,observed

    Aug 12, 2022 · Penalty $6,250

    Resolve
  • Class - 2

    Observed large dewatering tank on site at exp#1. upon review of department records it was observed that no permit has been issued for temporary construction equipment, for use of dewatering tank on site.

    Jun 24, 2022

    Resolve
  • Class - 1

    Work not conforming to site safety plan. temporary construction equipment on site that is not reflected on site safety plan. large dewatering tank located on site at exp#1 and no indication of tank on site safe

    Jun 24, 2022 · Penalty $6,250

    Resolve
  • Class - 1

    Failure to provide safe means of egress and ingress from/to excavation. observed excavation covering a large portion of the jobsite without means of egress/ingress for workers. observed workers climbing soil an

    Jun 24, 2022 · Penalty $6,250

    Resolve
  • Class - 2

    Job site fence not constructed/maintained to code & pursuant to subsection exp.#3 & #4.at time of inspection at a 26 story nb,i observed an active job site construction fence in place but not maintained to code

    Mar 17, 2022

    Resolve
  • Class - 2

    Work does not conform to approved construction documents &/or amendments-site safety plan excavation phase & foundation phase.at time of inspection at a 26 story nb,i observed on an active job site while in exc

    Mar 17, 2022

    Resolve

Complaints

  • Unsanitary condition

    Garbage/recycling storage

    Aug 24, 2026 · Apt BLDG

    Close
  • Flooring/stairs

    Floor

    May 2, 2026 · Apt 1107

    Close
  • Flooring/stairs

    Floor

    Apr 21, 2026 · Apt 1107

    Close
  • Heat/hot water

    Apartment only

    Feb 24, 2026 · Apt 601

    Close
  • Electric

    Power outage

    Feb 24, 2026 · Apt 601

    Close
  • Paint/plaster

    Ceiling

    Jan 15, 2026 · Apt 722

    Close
  • Water leak

    Heavy flow

    Dec 22, 2025 · Apt 1507RE

    Close
  • Water leak

    Heavy flow

    Oct 31, 2025 · Apt 605

    Close
  • Water leak

    Damp spot

    Oct 31, 2025 · Apt 605

    Close
  • Electric

    Lighting

    Oct 31, 2025 · Apt 605

    Close
Show 3 more ↓
  • Unsanitary condition

    Garbage/recycling storage

    Sep 2, 2025 · Apt BLDG

    Close
  • Safety

    Fire escape

    Sep 2, 2025 · Apt BLDG

    Close
  • Unsanitary condition

    Garbage/recycling storage

    Sep 2, 2025 · Apt BLDG

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Elevator apartment building (D7)
Year built
2022
Floors
26
Residential units
324
Building area
276,483 ft²
Lot area
66,256 ft²
Zoning
R7X
Community board
313
Council district
47
Block / lot
7063 / 12
Assessed value
$25,092,000
Landmark / historic district
No

HPD registration #391219, last renewed Aug 23, 2025.

Questions about 1515 Surf Avenue

Who owns 1515 Surf Avenue?

The owner of record in NYC Department of City Planning PLUTO data is Sirena Realty Corp..

Does 1515 Surf Avenue have violations?

NYC HPD has no housing violations on record for this property.

Is 1515 Surf Avenue rent stabilized?

NYC Department of Finance tax bills listed 463 rent-stabilized units here in 2024 (about 100% of its 324 apartments). To confirm a specific apartment, request its rent history from NYS Homes and Community Renewal.

When was 1515 Surf Avenue built?

City records list 2022 as the year it was built.

How many apartments are in 1515 Surf Avenue?

It has 324 residential units and 327 units in total.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.