61 Clarkson Avenue
Brooklyn, NY 11226BBL 3-05055-0081Map
Owner of record: Clarkson Parnasa LLC
61 Clarkson Avenue is an elevator apartment building built in 2021 in Brooklyn, 11226. It has 11 residential units across 6 floors. The owner of record is Clarkson Parnasa LLC. HPD has recorded 7 housing violations here, most recently on October 4, 2026. 6 of the 7 most recent violations are still open. City tax records listed 11 rent-stabilized apartments here in 2024.
- HPD violations
- 7
- DOB violations
- 13
- ECB violations
- 35
- HPD complaints
- 4
What to know
No open immediately-hazardous violations among recent records.
Date of the most recent HPD inspection that found a problem.
No balance due on recent ECB violations.
Rent stabilization
Counts come from owners' rent-stabilization filings shown on NYC Department of Finance tax bills, as extracted by JustFix. They tell you a building has stabilized apartments, not which ones.
Think your apartment is stabilized? Request its rent history from HCR (free), then check your renewal with the renewal calculator.
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 7
- BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color the ceiling in the bathroom located at apt 3b, 3rd story, 1st apartment from west at north
Oct 4, 2026 · Apt 3B
Open — Nov sent out - BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color the north and east wall in the 1st room from north located at apt 3b, 3rd story, 1st apartment from west at north
Oct 4, 2026 · Apt 3B
Open — Nov sent out - BHazardous
Properly repair with similar material the broken or defective wood floor in the 1st room from north located at apt 3b, 3rd story, 1st apartment from west at north
Oct 4, 2026 · Apt 3B
Open — Nov sent out - ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
May 11, 2026
Open — Nov sent out - ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
Jun 16, 2025
Open — Nov sent out - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Nov 29, 2024
Closed — Violation dismissed - ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
Apr 18, 2024
Open — Nov sent out
DOB building violations · 13
- Construction other optional
Emergency work order-per dob records on 09/26/2026 exterior wall efis panel detached from east wall & collapsed onto adj property &s/w.loose efis panel & parapet couping were observed.immed remove all loose efis mterial & remove/secure the parapet couping under direct & continous supervision
Oct 7, 2026
Dob violation - active - Immediate emergency anythingoptional
Remedy: erect approximately 45 linear feet of sidewalk shed at exp #1 extending from 61 clarkson to 63 clarkson. also remove remaining sections of loose stucco at exp #4
Sep 28, 2026
Dob violation - dismissed - Construction other optional
Requesting engineering report due to sections of fa ade dislodged. at the time of inspection observed at exposure #4 approximately 45'h x 45'w section of stucco has dislodged falling to public walkway and the roof, driveway and front yard of adjacent property 63 clarkson avenue.
Sep 26, 2026
Dob violation - active - Construction other optional
Structure rendered non compliant due to high winds . . at time of inspection observed premises with a masonry facade that has sustained damage due to high winds. at exposure #4 approximately 45'h x 45'w section of stucco has dislodged falling to public walkway and the roof, driveway and front yard of adjacent property 63 clarkson avenue.
Sep 26, 2026
Dob violation - active - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Oct 4, 2023
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Oct 4, 2023
Dob violation - dismissed - Construction other optional
C-construction other optional
Nov 23, 2021
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Mar 31, 2021
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Mar 31, 2021
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Mar 31, 2021
Dob violation - dismissed
Show 3 more ↓
- Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Mar 31, 2021
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jan 20, 2021
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Nov 11, 2020
Dob violation - dismissed
ECB violations · 35
- Class - 2
At the time of my inspection conducted at approximately 5:00 am in response to a complaint, i observed the underside of the sidewalk shed not illuminated as required by bc 3307.6.4.8. this condition creates a h
Oct 14, 2026 · Penalty $2,400
Active - Class - 2
At the time of inspection, a sidewalk shed at exp#1 1 of a 6 -story building was observed without the required information panel, creating a hazardous condition and potentially delaying emergency response by fd
Oct 14, 2026 · Penalty $1,250
Active - Class - 2
Failure to comply with commissioner's order contained in summons #35509203j issued on 12/31/2020, and failure to file a certificate of correction pursuant to 28.201.1 and 1rcny 102-01(d)(2). an acceptable certi
Mar 19, 2024 · Penalty $3,125
Resolve - Class - 2
At time of inspection for class1 vio#39507703m, upon reviewing department records no certificate of correction on file associated with the above mentioned violation. respondent failed to comply with commissione
Mar 23, 2023 · Penalty $3,125
Resolve - Class - 1
At time of inspection for hazardous violation #39507703m, i observed that the respondent failed to correct the hazardous conditions. failure to extend or offset the adjoining property chimney as required by bc
Jan 10, 2023 · Penalty $2,500
Resolve - Class - 2
Noted: at time of inspection of an active jobsite. upon reviewing bis/dob now observed permit # b00366807 expired on 9/16/2022.
Oct 17, 2022
Resolve - Class - 1
Noted: at time of inspection of an active jobsite upon request to see the 6 periodic inspection for sws none was provided. the last inspection was done on 2/11/2021.
Oct 17, 2022
Resolve - Class - 1
Noted: at time of inspection of an active jobsite observed at exp # 4 the chimney of the adjoining property not extended pass new/taller building as per code.extended chimney as per code
Oct 17, 2022
Resolve - Class - 1
Upon my request for the orientation records of the workers that were currently onsite, there was none provided. out of the 15 workers that were there, the competent person could not produce 1 orientation for an
Aug 31, 2022
Resolve - Class - 1
An active jobsite with workers onsite, there was large construction debris inside and out of the site. inadequate housekeeping creates a hazardous work condition (trips/falls) for all workers and anyone walkin
Aug 31, 2022
Resolve
Show 25 more ↓
- Class - 2
I observed at the 1st floor that the elevator shaft was open, unguarded with no control access zone established to prevent anyone from falling down to the cellar below. this created a dangerous trip and fall ha
Aug 31, 2022 · Penalty $5,000
Resolve - Class - 1
Upon inspection of the site i observed on the street a generator; i requested to see the fdny permit/document that states permission to have it and none was provide. the gas operated generator possess a fire ha
Aug 31, 2022 · Penalty $6,250
Resolve - Class - 1
I observed that the adjacent property at exposure #4 was missing roof protection for the skylight and the windows, despite all the construction material, debris and the 2 suspended scaffolds that were on top of
Aug 31, 2022 · Penalty $2,500
Resolve - Class - 1
At time of inspection i observed that the supported scaffold at exposure #3 had missing mudsills. i could not determine that mudsills were in place due to piles of mud and debris around the footing of the scaff
Aug 31, 2022 · Penalty $2,500
Resolve - Class - 1
Upon review of the pre-shift safety meeting, i observed that a pre-shift was not conducted for the elevator workers, nor was their attendance noted as being onsite or the elevator work that was being conducted
Aug 31, 2022 · Penalty $5,000
Resolve - Class - 2
Upon entering the construction site, i noticed that the over head protection provide to enter the site was inadequate; the planks above were open with missing toe boards, which would allow debris, tools or pers
Aug 31, 2022 · Penalty $5,000
Resolve - Class - 1
Upon review of the site safety plan, i observed that there was no mention of the 2 suspended scaffolds that was being stored on top of the adjacent property roof. no details on how the scaffolds would be tied d
Aug 31, 2022 · Penalty $2,500
Resolve - Class - 2
Work w/o permit.@time of insp of 6stynb currently@6sty level.i observed temporary outrigger catch platform/work platform w/wood guardrail installed@exp4 exterior wall on 5sty level(makeshift platform).upon requ
Mar 16, 2021 · Penalty $1,250
Resolve - Class - 1
Unlawfully contd work while on notice of swo.@time of insp of 6stynb currently@6sty level active jobsite.jobsite issued swo when bldg was@4sty level1/4/21 w/no work allowed above 1sty.on1/21/21 jobsite issued p
Mar 16, 2021 · Penalty $5,000
Resolve - Class - 1
Bc3308.5 vert safety netting systems.@time of insp of 6stynb active jobsite.i observed inadequate/missing vert safety netting in multiple locations.inadequacy observed (1)no taut system.cable not taut&loose.(2)
Mar 16, 2021 · Penalty $625
Resolve - Class - 2
Failure to safeguard all person and property affected by construction operations.jobsite open with chain cut as per approved pd operation issued on 2/19/2021 during sabbat and unable to serve the site.rem:safeg
Feb 20, 2021 · Penalty $5,000
Resolve - Class - 1
3314.8.missing guardrails@supported scaffold note:@time of my inspection of 6story bldg@4story stage,construction work in progress,i observed men performing masonry work on supported scaffold built across stair
Jan 4, 2021 · Penalty $2,500
Resolve - Class - 2
Expired dot permit. note: at time of my inspection of a 6 sty bldg under constructon at 4 sty stage constructon work in progress. research carrier out on dot records reveals that permit to occupy roadway &/or
Jan 4, 2021
Resolve - Class - 1
Sec. 3307.4.7 work or storage zone. note at time of my inspection of a6 sty bldg at 4 sty stage construction work in progress. i observed that their was a storage zone existed at exp#1 adjacent ot the sidewalk
Jan 4, 2021 · Penalty $625
Resolve - Class - 1
3314.5.supported scaffold planking note:@time of my inspection of 6story bldg@4story stage,construction work in progress i observed supporter scaffold built across stairway@4thstory w/ men performing masonry wo
Jan 4, 2021 · Penalty $2,500
Resolve - Class - 1
Means of egress note:@time of my inspection of 6story bldg@4story stage construction work in progress i observed men working on scaffold built across stairway [email protected] ladder obstructing egress to&f
Jan 4, 2021 · Penalty $625
Resolve - Class - 2
Sec. 3308.5 netting. note: at time of inspection of a 6 sty bldg at 3 sty stage. no work in progress,i observed that there were no netting at guardrails along perimeter at 3 sty level at exp#1. this condition
Dec 31, 2020 · Penalty $1,250
Resolve - Class - 1
Failure to maintain/display on site documents required by bc chapter 33. noted: at time of inspection of a new 6 sty bldg at the foundation phase,i observed a worker operating a mini excavator which was on site
Sep 25, 2020 · Penalty $1,250
Resolve - Class - 1
Failure to provide unobstructed exit passageway: noted: at time of my inspection of a new 6 sty bldg at the foundation phase,i observed one the 2 means of egress had a large mound of soil impeding access to the
Sep 25, 2020 · Penalty $1,250
Resolve - Class - 1
Sec. 27-1018 unsafe storage of combustible material & equipment. notedat time of my inspection of a new 6 sty bldg at the foundation phase,upon entering the rear of the site. i observed a makeshift shanty & a
Sep 25, 2020 · Penalty $2,500
Resolve - Class - 1
Sec. 28-110.1 inadequate site safety plans. noted: at time of inspection of an active jobsite. observed jobsite at foundation/excavation stage & upon reviewing site safety plan observed excavation/foundation
Aug 17, 2020 · Penalty $6,250
Resolve - Class - 2
Failure to maintain/display on site documents required by bc chapter 33. noted: at time of inspection of an active jobsite. upon request to see the monitor report none was provide. remedy: maintain/display requ
Aug 17, 2020 · Penalty $3,125
Resolve - Class - 2
At time of inspection,observed ongoing construction activies contrary to mayors emergency executive order 120 & subsequent order incorporating of governors executive order 202.3.4 & subsequent order & guidance
Aug 17, 2020 · Penalty $5,000
Resolve - Class - 2
Work w/o permit. observed a 10' apx curb cut, no permit on records andit's contrary as per code. property frontage is 22'apprx and is located in the 127 district. also observed there is not clearance between cu
Nov 14, 2018
Resolve - Class - 3
Zoning non-conforming locaton of accessory parking pad noted: front yard being used as open off street accessor parking area. a blue honda with new york plate #hxw6822 observed parked at front yard with fronta
Nov 14, 2018 · Penalty $500
Resolve
Complaints
- Paint/plaster
Ceiling
Oct 2, 2026 · Apt 3B
Close - Paint/plaster
Wall
Oct 2, 2026 · Apt 3B
Close - Heat/hot water
Apartment only
Jul 23, 2024 · Apt 5B
Close - Heat/hot water
Apartment only
Jul 21, 2024 · Apt 5B
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Elevator apartment building (D3)
- Year built
- 2021
- Floors
- 6
- Residential units
- 11
- Building area
- 7,970 ft²
- Lot area
- 2,200 ft²
- Zoning
- R7-1
- Community board
- 309
- Council district
- 40
- Block / lot
- 5055 / 81
- Assessed value
- $743,400
- Landmark / historic district
- No
HPD registration #391081, last renewed Jul 30, 2025.
Questions about 61 Clarkson Avenue
Who owns 61 Clarkson Avenue?
The owner of record in NYC Department of City Planning PLUTO data is Clarkson Parnasa LLC.
Does 61 Clarkson Avenue have violations?
Yes. NYC HPD has recorded 7 housing violations at this property.
Is 61 Clarkson Avenue rent stabilized?
NYC Department of Finance tax bills listed 11 rent-stabilized units here in 2024 (about 100% of its 11 apartments). To confirm a specific apartment, request its rent history from NYS Homes and Community Renewal.
When was 61 Clarkson Avenue built?
City records list 2021 as the year it was built.
How many apartments are in 61 Clarkson Avenue?
It has 11 residential units.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.