roofy

664 Ralph Avenue

Brooklyn, NY 11212BBL 3-03508-0042Map

Owner of record: NYC Pact Preservation Partners LLC

664 Ralph Avenue is a walk-up apartment building built in 1920 in Brooklyn, 11212. It has 26 residential units across 4 floors. The owner of record is NYC Pact Preservation Partners LLC. HPD has recorded 23 housing violations here, most recently on May 2, 2026. 16 of the 23 most recent violations are still open.

HPD violations
23
DOB violations
12
ECB violations
0
HPD complaints
9

What to know

Concern
3 open Class C

Immediately hazardous issues among recent violations are still open.

Good
Last violation May 2, 2026

Date of the most recent HPD inspection that found a problem.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 23

  • A

    Properly repair the source and abate the evidence of a water leak at ceiling in the 1st room from east located at apt 4c, 4th story, 2nd apartment from south at west

    May 2, 2026 · Apt 4C

    Open — Civ14 mailed
  • A

    Paint with light colored paint to the satisfaction of this department all peeling paint surfaces in the foyer , the private hallway , the kitchen , the 3rd room from east at north, the 1st room from east located at apt 4c, 4th story, 2nd apartment from south at west

    May 2, 2026 · Apt 4C

    Open — Civ14 mailed
  • C

    Abate the infestation consisting of mice in the entire apartment located at apt 4c, 4th story, 1st apartment from west at north

    Mar 30, 2026 · Apt 4C

    Closed — Violation dismissed
  • B

    Fire egress defective. remove obstructing bars or unlawful gates from window to fire escape or provide approved type gate at first window from south at east in the kitchen located at apt 4c, 4th story, 1st apartment from west at north

    Mar 30, 2026 · Apt 4C

    Open — Nov sent out
  • C

    Abate the infestation consisting of roaches in the entire apartment located at apt 4c, 4th story, 1st apartment from west at north

    Mar 30, 2026 · Apt 4C

    Closed — Violation dismissed
  • C

    Provide an adequate supply of heat for the apartment in the 5th room from north located at apt 2b, 2nd story, 1st apartment from east at south

    Feb 9, 2026 · Apt 2B

    Closed — Violation closed
  • C

    Provide ready access to buildings heating system door locked at fire passage way at boiler room

    Dec 11, 2025

    Open — Nov sent out
  • C

    Provide hot water at all hot water fixtures in the entire apartment located at apt 4f, 4th story, 2nd apartment from east at south , section at west

    Dec 11, 2025 · Apt 4F

    Closed — Violation closed
  • C

    Abate the infestation consisting of mice in the entire apartment located at apt 4e, 4th story, 1st apartment from south at west

    Jul 27, 2024 · Apt 4E

    Open — Notice of issuance sent to tenant
  • B

    Properly repair or replace the broken or defective garbage chute at west wall at public hall, 4th story

    Jul 27, 2024

    Open — Nov sent out
Show 13 more ↓
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Apr 11, 2024

    Closed — Violation dismissed
  • C

    Post notice, in form approved by the department, stating the name and location of the person designated by the owner to have key to buildings heating system at public hall, 1st story

    Mar 31, 2024

    Open — Nov sent out
  • A

    Post and maintain a proper sign on wall of entrance story showing the registration number assigned by the department and the address of the building. at public hall, 1st story

    Mar 31, 2024

    Open — Nov sent out
  • A

    Post and maintain a proper notice on wall of the entrance story in english and spanish on the availability of the agencys housing information guide. a sample notice can be found at www.nyc.gov/hpd. at public hall, 1st story

    Mar 31, 2024

    Open — Nov sent out
  • A

    § 329, m/d law and dept. rules and regs. provide a completed certificate of inspection visits in a proper frame at or near mailboxes, bottom edge of frame between 48-62 inches above floor missing frame at public hall, 1st story

    Mar 31, 2024

    Open — Nov sent out
  • B

    Provide adequate lighting at or near the outside of the front entranceway of the building and keep same burning from sunset every day to sunrise on the day following ***minimum 100 watts requierd***

    Sep 8, 2009

    Closed — Violation closed
  • B

    Replace with new the broken or defective window glass upper sash northwest room 1 sty north apt 1a , section '' ''

    Aug 19, 1999 · Apt 1A

    Open — Nov sent out
  • B

    Repair the leaky and/or defective faucets kitchen sink 1 sty north apt 1a , section '' ''

    Aug 19, 1999 · Apt 1A

    Open — Nov sent out
  • B

    Replace with new the missing oven door at gas range kitchen 1 sty north apt 1a , section '' ''

    Aug 19, 1999 · Apt 1A

    Open — Nov sent out
  • B

    Repair the flushing apparatus and maintain same so as to flush effectively the water closet ball cock assembly at tank of water closet bathroom 1 sty north apt 1a , section '' ''

    Aug 19, 1999 · Apt 1A

    Open — Nov sent out
  • B

    Replace with new the broken or defective window glass upper sash at center room and rear room 1 sty north apt 1a , section '' ''

    Aug 19, 1999 · Apt 1A

    Open — Nov sent out
  • A

    Refit double cylinder key operated lock installed entrance door vestibule to 1 sty public hall.

    Dec 23, 1989

    Open — Nov sent out
  • C

    Provide hot water at all hot water fixtures 3 sty apt 3c kitchen & bathroom. , section '' ''

    Oct 23, 1989 · Apt 3C

    Closed — Violation closed

DOB building violations · 12

  • Low pressure boiler boiler required

    Violation issued-failure to file 2024 external low pressure inspection

    Nov 14, 2025

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued-failure to file 2024 external low pressure inspection

    Nov 14, 2025

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued-failure to file 2024 external low pressure inspection

    Nov 14, 2025

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued-failure to file 2024 external low pressure inspection

    Nov 14, 2025

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued-failure to file 2024 external low pressure inspection

    Nov 14, 2025

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued-failure to file 2024 external low pressure inspection

    Nov 14, 2025

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2017 inspection report

    Jan 17, 2020

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2017 inspection report

    Jan 17, 2020

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2017 inspection report

    Jan 17, 2020

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2017 inspection report

    Jan 17, 2020

    Dob violation - dismissed
Show 2 more ↓
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2017 inspection report

    Jan 17, 2020

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2017 inspection report

    Jan 17, 2020

    Dob violation - dismissed

ECB violations · 0

No ECB violations on record

Complaints

  • Paint/plaster

    Wall

    Apr 22, 2026 · Apt 4C

    Close
  • Unsanitary condition

    Pests

    Mar 27, 2026 · Apt 4C

    Close
  • Safety

    Window guard broken/missing

    Mar 27, 2026 · Apt 4C

    Close
  • Unsanitary condition

    Pests

    Mar 27, 2026 · Apt 4C

    Close
  • Heat/hot water

    Apartment only

    Feb 3, 2026 · Apt 2B

    Close
  • Heat/hot water

    Entire building

    Dec 9, 2025 · Apt BLDG

    Close
  • Heat/hot water

    Apartment only

    Dec 23, 2024 · Apt 2E

    Close
  • Paint/plaster

    Wall

    Jul 23, 2024 · Apt APARTM

    Close
  • Unsanitary condition

    Sewage

    Mar 24, 2024 · Apt 3C

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Walk-up apartment building (C1)
Year built
1920
Floors
4
Residential units
26
Building area
24,600 ft²
Lot area
13,878 ft²
Zoning
R6
Community board
316
Council district
41
Block / lot
3508 / 42
Assessed value
$1,176,300
Landmark / historic district
No

HPD registration #390929, last renewed Aug 14, 2025.

Questions about 664 Ralph Avenue

Who owns 664 Ralph Avenue?

The owner of record in NYC Department of City Planning PLUTO data is NYC Pact Preservation Partners LLC.

Does 664 Ralph Avenue have violations?

Yes. NYC HPD has recorded 23 housing violations at this property.

Is 664 Ralph Avenue rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 664 Ralph Avenue built?

City records list 1920 as the year it was built.

How many apartments are in 664 Ralph Avenue?

It has 26 residential units.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.