Violations at 840 5 Avenue
Brooklyn, NY 11232 · BBL 3-00693-0039 · Back to the property
HPD housing violations
No HPD violations on record
DOB building violations
27 DOB violations, newest first.
- Low pressure boiler boiler required
Violation issued-failure to file 2024 external low pressure inspection
Nov 14, 2025
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2024 external low pressure inspection
Nov 14, 2025
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2023 external low pressure inspection
Sep 23, 2024
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2023 external low pressure inspection
Sep 23, 2024
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2018 external low pressure inspection
Jun 20, 2023
Dob violation - dismissed - Construction other optional
Vehicle impacting sidewalk shed
Jul 8, 2021
Dob violation - active - Construction other optional
C-construction other optional
Mar 8, 2019
Vp*-violation unserved ecb- dismissed - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2016 inspection report
Apr 6, 2018
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2013 inspection report
Mar 3, 2015
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2010 inspection report
Dec 13, 2011
Dob violation - dismissed - Low pressure boiler boiler required
Lblvio-low pressure boiler boiler required
Dec 31, 2009
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Jan 19, 2007
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Jan 31, 2005
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Feb 13, 2004
Dob violation - dismissed - Public assembly none
Pa-public assembly none
Jun 21, 2003
Vw*-violation - work w/o permit dismissed - Construction other optional
C-construction other optional
Jun 21, 2003
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Mar 19, 2003
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Mar 26, 2002
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Feb 27, 2001
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Mar 16, 1999
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
May 4, 1998
Dob violation - dismissed - Construction other optional
C-construction other optional
Apr 2, 1997
Vpw*-violation unserved ecb-work without permit-dismissed - Electric signs none
Es-electric signs none
Apr 2, 1997
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Feb 10, 1997
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Jun 1, 1994
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Aug 16, 1993
Dob violation - active - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Jun 1, 1993
Dob violation - dismissed
ECB violations
22 ECB violations, newest first.
- Class - 1
Failure to notify dept of accident/incident that resulted in fatality or injury.noted:boom of crane hit second stroy damaged adjacent property.as per check of dept records permit holder failed to notify dob wit
Sep 8, 2022
Resolve - Class - 1
Observed workers on supported scaffold at exp 2 with facade completed up to 2nd story height and no sidewalk shed in place to protect pedestrians walking on temporary sidewalk in a roadway that is within half o
Aug 9, 2022
Resolve - Class - 1
Observed 8ft high chainlink fence at exp2 with netting attached and posts rest on ground hold by sandbags creating hazard for public - no adequate measures provided to hold posts in an upright position restrain
Aug 3, 2022 · Penalty $500
Resolve - Class - 2
Observed 8ft high chainlink construction fence along exp 2 sidewalk with netting attached and posts hold by sandbags. upon request for design drawings for the above temporary construction equipment none were pr
Aug 3, 2022
Resolve - Class - 1
Observed crane collapsed at exp 2&3 causing damage. upon review of ccd1 provided in lieu of sidewalk shed all operations on western elevation to be ceased including roof, however, materials lifting operation fr
Aug 3, 2022 · Penalty $2,500
Resolve - Class - 1
In response to incident observed crane at exp3 collapsed onto right side towards exp 2, damaged adjoining property, delivery truck, and public property. observed outriggers not extended on right side as per man
Aug 3, 2022
Resolve - Class - 1
Reliable lifting, owner of knuckle boom, operating without outrigger extended of pick side of crane. causing crane to tip over, boom collapsed into adjacent occupied building with the boom laid across the stree
Aug 3, 2022
Resolve - Class - 1
Reliable lifting, owner of knuckleboom, operating to hoist material to roof of building. outriggers not extended on pick side of crane. as pick was attempted, crane was overloaded, safety shut off was over ridd
Aug 3, 2022 · Penalty $10,000
Resolve - Class - 1
Knuckleboom operating without outrigger extended of pick side of crane. causing crane to tip over, boom collapsed into adjacent occupied building with the boom laid across the street. massive & catastrophic acc
Aug 3, 2022
Resolve - Class - 1
Knuckleboom operating to hoist material to roof of building. outriggers not extended on pick side of crane. as pick was attempted, crane was overloaded, safety shut off was over ridden, and tipped over. boom of
Aug 3, 2022 · Penalty $10,000
Resolve - Class - 1
Operator of knuckleboom, omar fernandez, was operating knuckleboom without outriggers extended on pick side. attempting to pick load approx 2200lbs, overrode crane shutoff, and the crane tipped over. sufficient
Aug 3, 2022 · Penalty $10,000
Active - Class - 2
Failure to provide parapet panel for sidewalk shed as required. at thetime of my inspection of an active jobsite,i observed that the parapetpanel sign on the sidewalk shed was missing. this information to give
Nov 22, 2021
Resolve - Class - 1
Sec. bc3304.4.4 failure to provide 3'6" guardrail system or solid enclosure around open & accessible side or excavation. at the time of my inspection of an active jobsite. at foundation stages,i observed that t
Nov 22, 2021 · Penalty $2,500
Resolve - Class - 2
Work does not conform to approve documents &/or approved amendments. at time of inspection observed a supported scaffold in place @ exp1,3,&4. the supported scaffold had modified pipe frames throughout. upon re
Oct 28, 2021 · Penalty $1,250
Resolve - Class - 1
Sec. bc 3301.1.2 no compliance w/fdny fire code. note: at time of inspection of 4 sty new bldg,active jobsite w/preparations of concrete slab of 4th fl. i observed about 8 fuel canisters stored in a cage(closet
Jun 21, 2021 · Penalty $2,500
Resolve - Class - 1
Failure to communicate required information to workers during pre-shift safety meeting.note at time of inspection of a 4 story new building active jobsite with preperation of concrete slab for 4th floor.upon re
Jun 21, 2021 · Penalty $5,000
Resolve - Class - 2
Job fence not constructed or maintained pursuant to subsection.at the time of my inspection of 2 story dmeo site locked/closed i could not observed the condition of site via job site viewing panels due to openi
May 29, 2019
Resolve - Hazardous
Failure to maintain exterior building wall-hazardous- work noted: at extension premises wall (north) several vertical cracked brickwork at parapet area vertical crack (rear parapet) at first floor vertical erec
Sep 10, 2003 · Penalty $800
Resolve - Hazardous
Occupancy contrary to that allowed by c of o #300614574 a legal eating & drink e stablishment on 1st fl. with a factory & offices on 2nd fl. has now been illegally converted to a cabaret on the 2nd fl.
Jun 21, 2003 · Penalty $2,500
Resolve - Non-hazardous
Failure to comply with occupant load(1)by the actual # of people.at time of inspection p.a.arrange to be occupied by over 300 people with only 1 second means of egress.
Jun 21, 2003 · Penalty $2,500
Resolve - Non-hazardous
Work w/o a permit. note : at 1st story full partition walls erected throughout at various locations creating 2 new bathrooms, offices and 2 wooden stages also erected approx. 40' long x 13' wide x 1' high and 1
Apr 12, 2002 · Penalty $500
Resolve - Non-hazardous
Occupancy contrary to that allowed by the building department records. open space used as storage of cars. remedy: obtain valid certificate of occupancy.
May 18, 1994 · Penalty $800
Resolve