198 19 Street
Brooklyn, NY 11232BBL 3-00637-0019Map
Owner of record: Eshokol Development Corp.
198 19 Street is an elevator apartment building built in 2016 in Brooklyn, 11232. It has 29 residential units across 5 floors. The owner of record is Eshokol Development Corp.. HPD has recorded 17 housing violations here, most recently on September 9, 2026. 11 of the 17 most recent violations are still open. City tax records listed 29 rent-stabilized apartments here in 2024.
- HPD violations
- 17
- DOB violations
- 2
- ECB violations
- 12
- HPD complaints
- 8
What to know
Immediately hazardous issues among recent violations are still open.
Date of the most recent HPD inspection that found a problem.
No balance due on recent ECB violations.
Rent stabilization
Counts come from owners' rent-stabilization filings shown on NYC Department of Finance tax bills, as extracted by JustFix. They tell you a building has stabilized apartments, not which ones.
Think your apartment is stabilized? Request its rent history from HCR (free), then check your renewal with the renewal calculator.
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 17
- ANon-hazardous
Post a proper notice regarding rent stabilization law, in a form approved by the commissioner, in a conspicuous location within the common area at the buildings entrance. for more information about signage requirements, please visit: https://www.nyc.gov/site/hpd/services-and-information/required-signage.page
Sep 9, 2026
Open — Nov sent out - ANon-hazardous
Post and maintain a proper sign on wall of entrance story showing the registration number assigned by the department and the address of the building. at public hall, 1st story
Sep 9, 2026
Open — Nov sent out - CImmediately hazardous
Replace or repair the self-closing doors that is missing or defective hinges at compactor closet at public hall, 1st story
Sep 9, 2026
Open — Nov sent out - CImmediately hazardous
Post notice, in form approved by the department, stating the name and location of the person designated by the owner to have key to buildings heating system missing at public hall, 1st story
Sep 9, 2026
Open — Nov sent out - ANon-hazardous
Properly repair with similar material the broken or defective glass pane at 1st door from south at west at public hall, 1st story
Sep 9, 2026
Open — Nov sent out - ANon-hazardous
Properly repair with similar material the broken or defective glass pane at 2nd door from south at west at public hall, 1st story
Sep 9, 2026
Open — Nov sent out - ANon-hazardous
Properly repair with similar material the broken or defective glass pane at door to ''stair a'' at public hall, 1st story
Sep 9, 2026
Open — Nov sent out - BHazardous
Remove all encumbrances consisting of household items at public hall, 1st story
Sep 9, 2026
Open — Nov sent out - ANon-hazardous
§ 329, m/d law and dept. rules and regs. provide a completed certificate of inspection visits in a proper frame at or near mailboxes, bottom edge of frame between 48-62 inches above floor missing at public hall, 1st story
Sep 9, 2026
Open — Nov sent out - BHazardous
Trace and repair the source and abate the visible mold condition... more than 50 sq ft aggregate observed at ceiling at cellar level at public hall
Sep 9, 2026
Open — Nov sent out
Show 7 more ↓
- ANon-hazardous
Properly repair with similar material the broken or defective glass pane at door to ''stair b'' at cellar level at public hall
Sep 9, 2026
Open — Nov sent out - ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
Jun 13, 2025
Closed — Violation dismissed - ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
Apr 17, 2024
Closed — Violation dismissed - ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
Mar 31, 2023
Closed — Violation dismissed - ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
Mar 10, 2022
Closed — Violation dismissed - ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
Apr 20, 2021
Closed — Violation dismissed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Apr 20, 2021
Closed — Violation dismissed
DOB building violations · 2
- Elevator annual inspection / test elevatorrequired
Violation issued to elevator-failure to file category 1 2016 inspection/test
Sep 15, 2017
Dob violation - dismissed - Facade facade optional
Ll1080-local law 10/80 - facade facade optional
Jul 1, 1997
Dob violation - dismissed
ECB violations · 12
- Class - 2
Inoperative car phone (2.27.1.1.3.). replace worn gibs where needed.(2.11.11.5.7.). missing hoist rope cotter pin (2.20.9.). controller room door unlocked (2.7..3.4.1.(a)). missing in case of fire sign at roof
Sep 10, 2026 · Penalty $625
Active - Class - 1
Failure to safeguard all persons & property affected by constr operation. note: @ time of insp of a 5 story bldg @ 5 flr level, constr work in progress. i observed worker beyond perimeter edge of bldg approx 35
Jun 4, 2016 · Penalty $10,000
Resolve - Class - 1
Sec: bc3314.8. guardrail system. note: @ time of insp of a 5th story bldg up to 5th flr level, constr work in progress. i observed 3 workerson a pipe scaffold performing weather proofing operation approx 12 ft
Jun 4, 2016 · Penalty $1,600
Resolve - Class - 1
Use of supported pipe scaffold w/out user certification. note: @ time of insp of a 5 story bldg @ 5th flr level, constr work in progress. i observed 3 workers (2 men, 1 woman)on supported pipe scaffold performi
Jun 4, 2016
Resolve - Class - 1
Sec: bc3314.5. platform constr. note: @ time of insp of a 5 story bldg @ 5th flr level, constr work in progress. i observed 3 workers on supported pipe scaffold approx 12ft in height above flr level, i also obs
Jun 4, 2016 · Penalty $1,600
Resolve - Class - 1
Sec: bc3309.10. protection of roofs. note: @ time of insp of a 5 storybldg w/ pour flr to 3rd & steel erected to 5th flr level approx 20ft above adjacent property roof @ exp#2 & 10ft above adjacent property @ e
May 16, 2016 · Penalty $1,600
Resolve - Class - 1
Unlawfully continued work while on notice of a stop work order. note: @ time of insp of 5 story bldg on partial stop work order @ exp#1 & 15ft back, site was @ 1st flr w/ steel erected to 3rd (issued on 4/21/16
May 16, 2016 · Penalty $4,800
Resolve - Class - 1
Failure to adequately supervise work @ a construction site, so as to maintain a safe construction site & ensure compliance w/ approved construction docs & chapter33 (safegaurds during construction & demolition)
May 16, 2016 · Penalty $1,600
Resolve - Class - 1
Failure to provide sidewalk shed. at time of inspection observed job site not active. steel beans are erected approx. 25 feet high & are 5 feet away from the job site fence at exposure 1. no sidewalk shed has b
Apr 12, 2016 · Penalty $4,800
Resolve - Class - 2
3307.7.2 failure to have jobsite fence painted hunter green.at time ofinspection observed, jobsite fence is not painted hunter green as required by this section of code.all construction fences are to be painted
Jul 14, 2015
Resolve
Show 2 more ↓
- Class - 2
3307.7.2 failure to have job site fence painted hunter green.at time of inspection observed. jobsite fence is not painted hunter green as required by this section of code. all construction fences are to be
Jul 14, 2015
Resolve - Class - 1
3303.2.4 failure to provide sanitary facilities for workers on site.at time of insp.demo work in progress.i observed no sanitary facilites was provided for workers on site on request for sanitary facilities wor
Jun 10, 2015 · Penalty $400
Resolve
Complaints
- Elevator
Maintenance
Jul 4, 2026 · Apt BLDG
Close - Water leak
Heavy flow
Dec 9, 2019 · Apt 4H
Close - Paint/plaster
Ceiling
Dec 9, 2019 · Apt 4H
Close - Unsanitary condition
Mold
Dec 9, 2019 · Apt 4H
Close - Heat/hot water
Entire building
Nov 28, 2019 · Apt 2E
Close - Water leak
Slow leak
Apr 22, 2019 · Apt 4H
Close - Heat/hot water
Entire building
Mar 10, 2019 · Apt BLDG
Close - Heating
Heat related
Mar 9, 2013 · Apt 3A
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Elevator apartment building (D3)
- Year built
- 2016
- Floors
- 5
- Residential units
- 29
- Building area
- 22,503 ft²
- Lot area
- 10,017 ft²
- Zoning
- R6B
- Community board
- 307
- Council district
- 38
- Block / lot
- 637 / 19
- Assessed value
- $1,842,300
- Landmark / historic district
- No
HPD registration #387160, last renewed Aug 1, 2025.
Questions about 198 19 Street
Who owns 198 19 Street?
The owner of record in NYC Department of City Planning PLUTO data is Eshokol Development Corp..
Does 198 19 Street have violations?
Yes. NYC HPD has recorded 17 housing violations at this property.
Is 198 19 Street rent stabilized?
NYC Department of Finance tax bills listed 29 rent-stabilized units here in 2024 (about 100% of its 29 apartments). To confirm a specific apartment, request its rent history from NYS Homes and Community Renewal.
When was 198 19 Street built?
City records list 2016 as the year it was built.
How many apartments are in 198 19 Street?
It has 29 residential units.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.