2160 Walton Avenue
Bronx, NY 10453BBL 2-03180-0009Map
Owner of record: Mbd West Apartments Housing Development Fund Co.
2160 Walton Avenue is a walk-up apartment building built in 1922 in Bronx, 10453. It has 48 residential units across 5 floors. The owner of record is Mbd West Apartments Housing Development Fund Co.. HPD has recorded 1,752 housing violations here, most recently on April 30, 2026. 48 of the 50 most recent violations are still open. City tax records listed 48 rent-stabilized apartments here in 2024.
- HPD violations
- 1,752
- DOB violations
- 14
- ECB violations
- 37
- HPD complaints
- 1,047
What to know
Immediately hazardous issues among recent violations are still open.
Date of the most recent HPD inspection that found a problem.
No balance due on recent ECB violations.
Rent stabilization
Counts come from owners' rent-stabilization filings shown on NYC Department of Finance tax bills, as extracted by JustFix. They tell you a building has stabilized apartments, not which ones.
Think your apartment is stabilized? Request its rent history from HCR (free), then check your renewal with the renewal calculator.
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 1,752
- ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
Apr 30, 2026
Open — Nov sent out - CImmediately hazardous
Provide temporary seal up throughout entire building to all openings
Jan 3, 2025
Closed — Violation closed - ANon-hazardous
Paint with light colored paint to the satisfaction of this department at ceiling at 1st public hall bulkhead from east at north
Nov 20, 2024
Open — Nov sent out - BHazardous
Properly repair with similar material the broken or defective fire retardant material at ceiling at 1st public hall bulkhead from east at north
Nov 20, 2024
Open — Nov sent out - BHazardous
Properly repair and abate unsafe electric wiring condition consisting of exposed wiring at ceiling in the private hallway located at apt 52b, 5th story, 2nd apartment from south at west
Nov 20, 2024 · Apt 52B
Open — Nov sent out - BHazardous
Properly repair or replace the broken or defective lower window sash balance in the kitchen located at apt 52b, 5th story, 2nd apartment from south at west
Nov 20, 2024 · Apt 52B
Open — Nov sent out - BHazardous
Properly repair or replace the broken or defective upper and lower window sash balance in the 5th room from east located at apt 52b, 5th story, 2nd apartment from south at west
Nov 20, 2024 · Apt 52B
Open — Nov sent out - BHazardous
Properly repair or replace the broken or defective upper window sash balance in the bathroom located at apt 52b, 5th story, 2nd apartment from south at west
Nov 20, 2024 · Apt 52B
Open — Nov sent out - CImmediately hazardous
Trace and repair the source and abate the visible mold condition... greater than 30 square ft at all walls and the ceiling in the bathroom located at apt 32b, 4th story, 2nd apartment from south at west
Nov 7, 2024 · Apt 32B
Open — Notice of issuance sent to tenant - CImmediately hazardous
Replace or repair the self-closing doors that is missing or defective hinges in the entrance located at apt 32b, 4th story, 2nd apartment from south at west
Nov 7, 2024 · Apt 32B
Open — Nov sent out
Show 40 more ↓
- CImmediately hazardous
Properly secure the loose 7th marble tread from bottom to up at public hall stairs, 5th story, section at north
Nov 7, 2024
Open — Nov sent out - CImmediately hazardous
Properly secure the loose 7th marble tread from intermediate landing to up at public hall stairs, 4th story, section at south
Nov 7, 2024
Open — Nov sent out - CImmediately hazardous
Correct the lead-based paint hazard - paint that tested positive for lead content and that is peeling or on a deteriorated subsurface - using work practices set forth in 28 rcny §11-06(b)(2) north wall, east wall in the kitchen located at apt 32b, 4th story, 2nd apartment from south at west
Nov 7, 2024 · Apt 32B
Open — Nov sent out - BHazardous
Properly repair with similar material the broken or defective ceramic floor tiles in the bathroom located at apt 32b, 4th story, 2nd apartment from south at west
Nov 7, 2024 · Apt 32B
Open — Nov sent out - BHazardous
Properly repair with similar material the broken or defective wood floor in the private hallway located at apt 32b, 4th story, 2nd apartment from south at west
Nov 7, 2024 · Apt 32B
Open — Nov sent out - BHazardous
Properly repair with similar material the broken or defective ceramic floor tiles in the kitchen located at apt 32b, 4th story, 2nd apartment from south at west
Nov 7, 2024 · Apt 32B
Open — Nov sent out - BHazardous
Properly repair or replace the broken or defective electrical outlets at west and east walls in the kitchen located at apt 32b, 4th story, 2nd apartment from south at west
Nov 7, 2024 · Apt 32B
Open — Nov sent out - BHazardous
Repair the leaky and/or defective faucets at the bathtub in the bathroom located at apt 32b, 4th story, 2nd apartment from south at west
Nov 7, 2024 · Apt 32B
Open — Nov sent out - CImmediately hazardous
Abate the infestation consisting of roaches in the entire apartment located at apt 32b, 4th story, 2nd apartment from south at west
Nov 7, 2024 · Apt 32B
Open — Notice of issuance sent to tenant - CImmediately hazardous
Abate the infestation consisting of rodents rats in the entire apartment located at apt 32b, 4th story, 2nd apartment from south at west
Nov 7, 2024 · Apt 32B
Open — Notice of issuance sent to tenant - BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color the ceiling in the 5th room from east at north located at apt 32b, 4th story, 2nd apartment from south at west
Nov 7, 2024 · Apt 32B
Open — Nov sent out - BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color the ceiling in the kitchen located at apt 32b, 4th story, 2nd apartment from south at west
Nov 7, 2024 · Apt 32B
Open — Nov sent out - BHazardous
Properly repair the source and abate the evidence of a water leak at the ceiling in the kitchen located at apt 32b, 4th story, 2nd apartment from south at west
Nov 7, 2024 · Apt 32B
Open — Nov sent out - BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color the west wall, south wall in the kitchen located at apt 32b, 4th story, 2nd apartment from south at west
Nov 7, 2024 · Apt 32B
Open — Nov sent out - CImmediately hazardous
M/d law abate the nuisance consisting of free standing refrigerator with door intact at public hall, 1st story, section ''south''
Oct 25, 2024
Closed — Violation closed - CImmediately hazardous
Replace or repair the self-closing doors that is missing or defective building entrance , 1st story
Aug 29, 2024
Open — Violation will be reinspected - CImmediately hazardous
Abate the infestation consisting of roaches in the entire apartment located at apt 22b, 2nd story, 2nd apartment from east at south , section at north
Aug 21, 2024 · Apt 22B
Open — Notice of issuance sent to tenant - BHazardous
Provide a safe and adequate supply of electric service to the fixtures at the ceiling in the foyer located at apt 22b, 2nd story, 2nd apartment from east at south , section ''north'', 2nd from east at south
Aug 21, 2024 · Apt 22B
Open — Nov sent out - CImmediately hazardous
Abate the infestation consisting of roaches in the entire apartment located at apt 22b, 2nd story, section ''north''
Aug 21, 2024 · Apt 22B
Open — Notice of issuance sent to tenant - BHazardous
Repair or replace the carbon monoxide detecting device(s). missing in the entire apartment located at apt 22b, 2nd story, 2nd apartment from east at south , section ''north''
Aug 21, 2024 · Apt 22B
Open — Nov sent out - BHazardous
Repair or replace the smoke detector misssing in the entire apartment located at apt 22b, 2nd story, 2nd apartment from east at south , section ''north''
Aug 21, 2024 · Apt 22B
Open — Nov sent out - CImmediately hazardous
Properly repair with similar material the broken or defective broken glass at west window and upper sash on north window in the 4th room from east at north located at apt 22b, 2nd story, 2nd apartment from east at south , section at north
Aug 21, 2024 · Apt 22B
Open — Nov sent out - BHazardous
Properly repair with similar material the broken or defective floor vinyl tile in the 4th room from east at north located at apt 22b, 2nd story, 2nd apartment from east at south , section at north
Aug 21, 2024 · Apt 22B
Open — Nov sent out - CImmediately hazardous
Properly repair with similar material the broken or defective wood subfloor in the 4th room from east at north located at apt 22b, 2nd story, 2nd apartment from east at south , section at north
Aug 21, 2024 · Apt 22B
Open — Nov sent out - BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color ceiling in the kitchen located at apt 22b, 2nd story, 2nd apartment from south at west
Aug 8, 2024 · Apt 22B
Open — Nov sent out - CImmediately hazardous
Abate the infestation consisting of mice in the entire apartment located at apt 22b, 2nd story, 2nd apartment from south at west
Aug 8, 2024 · Apt 22B
Open — Notice of issuance sent to tenant - CImmediately hazardous
Abate the infestation consisting of roaches in the entire apartment located at apt 22b, 2nd story, 2nd apartment from south at west
Aug 8, 2024 · Apt 22B
Open — Notice of issuance sent to tenant - BHazardous
Properly repair or replace the broken or defective electrical outlet at west wall in the foyer located at apt 22b, 2nd story, 2nd apartment from south at west
Aug 8, 2024 · Apt 22B
Open — Nov sent out - BHazardous
Properly repair or replace the broken or defective electrical outlet at north wall in the 3rd room from east located at apt 22b, 2nd story, 2nd apartment from south at west
Aug 8, 2024 · Apt 22B
Open — Nov sent out - BHazardous
Properly repair or replace the broken or defective light fixture at ceiling in the foyer located at apt 22b, 2nd story, 2nd apartment from south at west
Aug 8, 2024 · Apt 22B
Open — Nov sent out - BHazardous
Properly repair or replace the broken or defective eletrical outlet at south wall in the 5th room from east at south located at apt 22b, 2nd story, 2nd apartment from south at west
Aug 8, 2024 · Apt 22B
Open — Nov sent out - BHazardous
Repair or replace the carbon monoxide detecting device(s). missing in the entire apartment located at apt 22b, 2nd story, 2nd apartment from south at west
Aug 8, 2024 · Apt 22B
Open — Nov sent out - CImmediately hazardous
Properly repair the source and abate the evidence of a water leak ceiling in the kitchen located at apt 22b, 2nd story, 2nd apartment from south at west
Aug 8, 2024 · Apt 22B
Open — Not complied with - CImmediately hazardous
Provide ready access to buildings heating system door locked at boiler room
Jul 31, 2024
Open — Nov sent out - CImmediately hazardous
Replace or repair the self-closing doors that is missing or defective at bulkhead door at public hall, 5th story, section ''north''
Jul 31, 2024
Open — Not complied with - CImmediately hazardous
Properly repair with similar material the broken or defective eroded bricks and mortar joints at building exterior facade at all stories at south yard
Jul 31, 2024
Open — Not complied with - CImmediately hazardous
Properly repair with similar material the broken or defective eroded bricks and mortar joints at building exterior facade at all stories at north yard
Jul 31, 2024
Open — Not complied with - CImmediately hazardous
Repair the roof so that it will not leak at ceiling at apt below
Jul 31, 2024
Open — Not complied with - CImmediately hazardous
Repair the broken or defective plastered surfaces and paint in a uniform color at ceiling in the bathroom located at apt 42a, 4th story, 2nd apartment from south at west
Jul 31, 2024 · Apt 42A
Open — Not complied with - CImmediately hazardous
Properly repair the source and abate the evidence of a water leak at ceiling in the bathroom located at apt 42a, 4th story, 2nd apartment from south at west
Jul 31, 2024 · Apt 42A
Open — Not complied with
DOB building violations · 14
- Low pressure boiler boiler required
Violation issued-failure to file 2024 external low pressure inspection
Nov 14, 2025
Dob violation - active - Failure to benchmark none
Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4
Aug 3, 2024
Dob violation - dismissed - Failure to benchmark none
Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4
May 2, 2024
Dob violation - active - Failure to benchmark none
Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4
Feb 22, 2024
Dob violation - active - Failure to benchmark none
Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4
Nov 2, 2023
Dob violation - active - Failure to benchmark none
Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4
Aug 2, 2023
Dob violation - active - Failure to benchmark none
Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4
May 2, 2023
Dob violation - active - Construction other optional
C-construction other optional
Aug 20, 2009
Vw*-violation - work w/o permit dismissed - Construction other optional
Work w/out permit
Aug 9, 2009
Vw-violation work without permit - active - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Jan 1, 2009
Dob violation - dismissed
Show 4 more ↓
- Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Aug 29, 1995
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Jun 9, 1994
Dob violation - dismissed - Zoning none
Z-zoning none
Nov 25, 1991
Vp-violation unserved ecb-active - Zoning none
Z-zoning none
Mar 13, 1991
Vp-violation unserved ecb-active
ECB violations · 37
- Class - 1
At time of inspection, a worker fell from the roof to the 2nd floor during brick facade work at a 5-story building, sustained injuries, and was transported to the hospital. the scaffold work area at roof level
Oct 15, 2026 · Penalty $10,000
Active - Class - 1
At time of inspection, scaffold logs indicated the scaffold was properly maintained; however, unsafe scaffold conditions were observed at the 5-story building, including broken planking and inadequate maintenan
Oct 15, 2026 · Penalty $10,000
Active - Class - 1
At time of inspection, missing or inadequate toe-boards were observed on scaffolds throughout the 5-story building during brick facade work. the condition created a risk of tools and materials falling and injur
Oct 15, 2026 · Penalty $5,000
Active - Class - 1
At time of inspection, missing and inadequate guardrails were observed at parapet edges and window openings throughout the 5-story building during brick facade work. the conditions exposed workers to fall hazar
Oct 15, 2026 · Penalty $5,000
Active - Class - 1
At time of inspection, missing guardrails were observed on scaffolds throughout the 5-story building during brick facade work. the condition exposed workers to fall hazards.. install and maintain required guard
Oct 15, 2026 · Penalty $5,000
Active - Class - 2
At time of inspection, the site pre-shift safety meeting records lacked details about the work being performed and the hazards present at the 5-story building during brick facade work. . conduct and document pr
Oct 15, 2026 · Penalty $2,500
Active - Class - 2
6 story alt2 active site. observed temporary construction equipment in place/debris chute above roof to courtyard approximately 55 ft in height attached to supported scaffold exp#1. upon request to contractor f
Jul 2, 2026 · Penalty $1,280
Active - Class - 1
6 story building alt2 active site.temporary platform with shoring underneath/crash deck on bsmt/1 floor installed contrary to approved plans permit#x01393202.missing multiple connections from u bolt to i beams
Jul 2, 2026 · Penalty $2,500
Active - Class - 2
6 story alt2 active site. observed shoring on 5 fl attached to ceiling & multiple locations onsite with makeshift timber shoring holding up load bearing masonry walls & window openings. upon request to contract
Jul 2, 2026 · Penalty $1,250
Active - Class - 1
6 story alteration active jobsite. observed no/missing inadequate guardrails on roof/missing netting & toe boards 3308.7.2/3307.8.1/missing roof parapet walls/unsafe conditions/hazard to worker's onsite. materi
Jul 2, 2026 · Penalty $5,000
Resolve
Show 27 more ↓
- Class - 2
6 story alt full renovation active jobsite. observed multiple unsafe conditions onsite as per ecb#39556133k/34m/35y/36x. inadequate guardrails on roof, debris chute without a permit/plans.crash deck on 1 st fl
Jul 2, 2026 · Penalty $5,000
Active - Class - 2
6 story alt full renovation, observed sidewalk shed in place at exp#1,4 installed contrary to plans/code. permit#x01250462 missing sections of 8 ft cross bracing, shed leaning/not plumb. missing 4 ft horizontal
Jul 2, 2026
Resolve - Class - 2
Observed c-joist installed throughout jobsite. manufacture specs states blocking to be installed 10 ft from each other with straps attached top and bottom. multiple locations is missing blocking and sections we
May 12, 2026 · Penalty $1,280
Resolve - Class - 2
Observed multiple fire extinguishers on active jobsite. all fire extinguishers are in adequate missing pins, no fdny inspection tags and discharged. this creates a fire hazard due to structure of jobsite consi
May 12, 2026 · Penalty $1,562
Resolve - Class - 2
Observed supported scaffolding installed at all exposures of jobsite.base of scaffolding has use of 2ft & 4 ft frames. upon review of approved plans does not show the use of these frames only use of standard o
May 12, 2026
Resolve - Class - 2
Observed inadequate housekeeping throughout multiple locations of active jobsite. the housekeeping consist of construction debris/materials such as large of amounts of combustible wood from all wooden joist and
May 12, 2026
Resolve - Class - 2
28-110.2 phased site safety plans- observed active jobsite with large amount of street occupancy. there are material trucks, 20 yard debris container and material storage. review of provided site safety does no
May 12, 2026
Resolve - Class - 1
At time of inspection, observed construction superintendent listed failed to be onsite and there is no notification to the department for an alternate as required. failure to maintain and provide designated con
Feb 13, 2026 · Penalty $5,000
Resolve - Class - 2
At the time of my inspection i observed a 30 yard debris container full to the rim stationed on roadway adjacent to sidewalk shed. i also observed that there is no netting (4 ft and wire mesh) provided as requi
Feb 13, 2026 · Penalty $2,500
Resolve - Class - 1
At time of inspection of a 5 story demo,observed general contractor crew engaging in demolition operations without required demolition endorsement or authorization to perform such work. contrary to 28-401.4, pe
Feb 13, 2026 · Penalty $5,030
Resolve - Class - 1
At time of inspection of a 5 story alteration gut renovation, required site safety plan approved by the department of buildings was not onsite. contrary to bc 3301.7, failure to keep mandated plans prevents ver
Feb 13, 2026 · Penalty $2,500
Resolve - Class - 1
Unlawful acts failure to comply with an order of the commissioner in june 28,2019 a electrical violation was issue to the respondent the respondnet failed to comply with (nyc) electrical code #250.(4) (ecb) 335
Aug 14, 2019 · Penalty $625
Resolve - Class - 2
Unapproved/unsafe/unsuitable electrical equipment,apparatus materials devices appliances or wiring in use.observed in basement electrical room a 100 amp disconnect supplying power to commercial store with the l
Jun 28, 2019 · Penalty $800
Resolve - Class - 2
Failure to provide effective electrical continuity for metal raceways,enclosers,cable armor.observed on 3rd,4th and 5th floors of both sidesof building the installation of emt conduit to provide power for emerg
Jun 28, 2019 · Penalty $1,200
Resolve - Class - 1
Ec250.18/ground clamp not accessible.observed access to water ground clamp is prohibited by wall in apt#1 access to ground clamp shall be sowithout the removal of any part of the building structure or finish.re
Jun 28, 2019 · Penalty $400
Resolve - Class - 1
Electrical work w/o a permit. observed emt conduits,lights,outdoor a.cunit,service disconnect switch panel,riser bx cables,outdoor lights. remedy: obtain permit/comply w/code.
May 12, 2017 · Penalty $800
Resolve - Class - 2
Sec. 225.31 no service disconnect for 2nd bldg. observed meter service14 seperate bldg w/no service disconnect primary disconnect controls 1st bldg w/service tap to 2nd service w/o a means of disconnect.
May 12, 2017
Resolve - Class - 1
Sec. 250.68 ground clamp not accessible. observed that access to water(grand) was prohibited by a walled off area in basement. remedy: comply w/code provide access.
May 12, 2017 · Penalty $800
Resolve - Class - 2
Failure to maintain bldg. noted: door of bulkhead'b'not self closing. wires run across entrance to roof top fire escape landing. remedy: comply w/notice of violation.
May 18, 2016 · Penalty $500
Resolve - Class - 1
Work w/o a permit noted cellar renovated plumbing work electrical partition work done four sro units illegally constructed all work done w/o first obtaining permits rem: obtain permit or restore premises to pri
Aug 9, 2009
Resolve - Class - 1
Residence altered for occupancy as a dwelling for more than the legally approved number of families.note:4 sro units created & occupied in the cellar.total of 8 occupants illegally occupying cellar as residenc
Aug 9, 2009
Resolve - Class - 1
Failure to maintain building in code-compliant manner no 2nd means of egress for 4 sro units located in cellar of above bldg rem: repair and/or replace egress to cellar
Aug 9, 2009
Resolve - Non-hazardous
Failure to maintain.note:ceiling in apt. 31b.living room a 5 ft by 5 ft section is missing exposing woodlath.at location on 3rd floor front.remedy:make all necessary repairs in a safe and lawfull manner.
Jul 13, 2004
Resolve - Hazardous
Work without permits. defect: (1) cut through 2 fire walls from apt 41a between 42a & 43a. creating 2 apts out of 3 apts. created partition walls 2x4 sheetrock to create the 2 apts. remedy: obtain permits is
Oct 30, 2002 · Penalty $500
Resolve - Non-hazardous
Occupancy contrary to that allowed by department records. from legal use :living room ti illegla use : living room and bedroom.location apartment 31 line "a" remedy: discontinue illegal use
Apr 6, 2000 · Penalty $2,500
Resolve - Non-hazardous
Illegal use in a residential district. operating a grocery store in a r-8 zoning district which is contrary to the zoning resolution. remedydiscontinue illegal use
Nov 25, 1991 · Penalty $500
Active - Non-hazardous
Illegal use in a residential district. northeast ground fl apt now occupied as "los amigos entertainment" with 3 pool tables bldg is loc-cated in a r-8 zoning district. remedy: discontinue illegal use forth
Mar 13, 1991 · Penalty $500
Resolve
Complaints
- Door/window
Window frame
Nov 14, 2024 · Apt 52B
Close - Heat/hot water
Entire building
Nov 14, 2024 · Apt 52B
Close - Door/window
Window pane
Nov 14, 2024 · Apt 52B
Close - Electric
No lighting
Nov 14, 2024 · Apt BLDG
Close - Electric
Outlet/switch
Nov 5, 2024 · Apt 32B
Close - General
Cooking gas
Nov 5, 2024 · Apt 32B
Close - Plumbing
Bathtub/shower
Nov 5, 2024 · Apt 32B
Close - Unsanitary condition
Pests
Nov 5, 2024 · Apt 32B
Close - Electric
Lighting
Oct 30, 2024 · Apt 52B
Close - Safety
Smoke detector
Oct 30, 2024 · Apt 52B
Close
Show 40 more ↓
- Flooring/stairs
Floor
Oct 30, 2024 · Apt 52B
Close - Paint/plaster
Wall
Oct 30, 2024 · Apt 52B
Close - Electric
Wiring
Oct 30, 2024 · Apt 52B
Close - General
Cooking gas
Oct 30, 2024 · Apt 52B
Close - Heat/hot water
Apartment only
Oct 24, 2024 · Apt 41A
Close - Electric
No lighting
Oct 24, 2024 · Apt 41A
Close - Unsanitary condition
Pests
Aug 6, 2024 · Apt 22B
Close - Unsanitary condition
Pests
Aug 6, 2024 · Apt 22B
Close - Water leak
Slow leak
Aug 6, 2024 · Apt 22B
Close - Paint/plaster
Ceiling
Aug 6, 2024 · Apt 22B
Close - Water leak
Heavy flow
Jul 17, 2024 · Apt 42A
Close - Appliance
Refrigerator
Jul 17, 2024 · Apt 42A
Close - General
Cooking gas
Jul 1, 2024 · Apt 54B
Close - General
Cooking gas
Apr 24, 2024 · Apt BLDG
Close - Heat/hot water
Entire building
Apr 24, 2024 · Apt BLDG
Close - Safety
Fire escape
Apr 24, 2024 · Apt BLDG
Close - Plumbing
Steam pipe/riser
Apr 4, 2024 · Apt 1B
Close - General
Cooking gas
Apr 4, 2024 · Apt 1B
Close - Unsanitary condition
Pests
Apr 4, 2024 · Apt 1B
Close - Water leak
Heavy flow
Apr 4, 2024 · Apt 1B
Close - Unsanitary condition
Pests
Feb 17, 2024 · Apt 32A
Close - Heat/hot water
Entire building
Feb 17, 2024 · Apt 32A
Close - Unsanitary condition
Pests
Feb 17, 2024 · Apt 32A
Close - Appliance
Electric/gas range
Jan 10, 2024 · Apt 4B
Close - Water leak
Heavy flow
Jan 1, 2024 · Apt 1A
Close - Plumbing
Basin/sink
Jan 1, 2024 · Apt 1A
Close - Plumbing
Bathtub/shower
Jan 1, 2024 · Apt 1A
Close - General
Cooking gas
Dec 5, 2023 · Apt BLDG
Close - Heat/hot water
Entire building
Dec 5, 2023 · Apt BLDG
Close - Door/window
Door
Nov 21, 2023 · Apt 42A
Close - Paint/plaster
Ceiling
Nov 21, 2023 · Apt 42A
Close - Unsanitary condition
Mold
Nov 21, 2023 · Apt 42A
Close - Flooring/stairs
Floor
Nov 8, 2023 · Apt 23B
Close - Electric
Outlet/switch
Nov 7, 2023 · Apt 32A
Close - Unsanitary condition
Mold
Nov 7, 2023 · Apt 32A
Close - Water leak
Slow leak
Nov 7, 2023 · Apt 32A
Close - Paint/plaster
Ceiling
Nov 7, 2023 · Apt 32A
Close - Paint/plaster
Ceiling
Nov 7, 2023 · Apt 32A
Close - Flooring/stairs
Floor
Oct 9, 2023 · Apt 32A
Close - Water leak
Heavy flow
Oct 9, 2023 · Apt 32A
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Walk-up apartment building (C7)
- Year built
- 1922
- Floors
- 5
- Residential units
- 48
- Building area
- 40,075 ft²
- Lot area
- 10,000 ft²
- Zoning
- R8
- Community board
- 205
- Council district
- 14
- Block / lot
- 3180 / 9
- Assessed value
- $1,377,450
- Landmark / historic district
- No
HPD registration #208528, last renewed Nov 6, 2025.
Questions about 2160 Walton Avenue
Who owns 2160 Walton Avenue?
The owner of record in NYC Department of City Planning PLUTO data is Mbd West Apartments Housing Development Fund Co..
Does 2160 Walton Avenue have violations?
Yes. NYC HPD has recorded 1,752 housing violations at this property.
Is 2160 Walton Avenue rent stabilized?
NYC Department of Finance tax bills listed 48 rent-stabilized units here in 2024 (about 100% of its 48 apartments). To confirm a specific apartment, request its rent history from NYS Homes and Community Renewal.
When was 2160 Walton Avenue built?
City records list 1922 as the year it was built.
How many apartments are in 2160 Walton Avenue?
It has 48 residential units and 49 units in total.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.