No HPD violations on record
DOB building violations
10 DOB violations, newest first.
- Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Feb 13, 2004
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Feb 13, 2004
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Feb 27, 2001
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Feb 27, 2001
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Feb 7, 2000
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Feb 7, 2000
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
May 4, 1998
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
May 4, 1998
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Sep 16, 1997
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Sep 16, 1997
Dob violation - dismissed
ECB violations
38 ECB violations, newest first.
- Class - 2
Failure to maintain building in code compliant manner.noted:there are several classrooms and some corridors with excessive amounts of combustible materials and electrical wires and lights strung across classroo
Mar 31, 2026 · Penalty $1,250
Active - Class - 2
Reissue#35692450p failure to maintain building in code compliant manner.noted:there is water seepage through foundation wall at time of moderaate to heavy rain,that leaks into the electric meter room.high volta
Mar 31, 2026 · Penalty $3,125
Active - Class - 2
Re-issue #35678825l. failure to maintain building in code-compliant manner. noted: water leaks through foundation wall into the electric meter room. rust and damage to electrical equipment boxes and hole in flo
Mar 26, 2025 · Penalty $3,125
Active - Class - 2
Found laars(model#pwo715in09k)h stamped gas fired hot water boiler not registered and leaking, maintain boiler; correct violating condition submit certificate of correction
Apr 5, 2024 · Penalty $625
Active - Class - 2
Reissue#35665327x failure to maintain building in code compliant manner.noted:water leaks through foundation into electric meter room.rem:repair leak/protect electric meter room.
Mar 15, 2024 · Penalty $1,562
Active - Class - 2
Reissue#35636503n.failure to maintain building in code compliant manner.observed in electric meter room,the ongoing problem with water leaking from the foundation into the area continues.water enter above the s
Jan 24, 2023 · Penalty $1,562
Active - Class - 2
Reissue#35555839m.failure to maintain building in code compliant manner.observed at toi in the electric meter room,there is a leak in the foundation wall behind the electric box at meter area.this leak is ongoi
Feb 7, 2022 · Penalty $1,562
Active - Class - 2
Failure to maintain bldg in codecompliant manner:use of prohibited door &/or hardware per bc1008.1.8;27-371j note following doors have illegal kickstops installed:b10,b11,b16,b22.provide legal hardware.
Apr 19, 2021 · Penalty $625
Resolve - Class - 2
28-301.1 failure to provide natural or mechanical ventilation to occupied space per mc401.2 note@cellar level in boilerrm storage@gas lawn mower.comply w/violation remove gas mower.
Apr 19, 2021 · Penalty $1,250
Resolve - Class - 2
Failure to maintain bldg in codecompliant manner note@lower roof levelroof leaks causing damage to ceiling below in auditorium&gym.repair &/or replace.
Apr 19, 2021 · Penalty $625
Resolve - Class - 2
Reissue35502147m failure to maintain bldg in codecompliant manner note@bsmt level in electricalrmb10 water penetration thru foundation wall behind electrical box.repair &/or replace.
Apr 19, 2021 · Penalty $1,562
Active - Class - 2
Failure to maintain building in code and complaint manner at time of inspection observed at electrical room (b 10 ) water penetration by teh foundation wall behind electrical box repair and or replace
Jul 6, 2020 · Penalty $625
Active - Class - 2
Failure to maintain bldg in code-compliant manner: lack of emergency lighting for exits, exit discharges and public corridors per bc 1006.127-542. noted: at 1st flr, auditorium area, inoperative emergency ligh
Oct 27, 2016
Resolve - Class - 2
Exit door not self-closing. noted: at 1st flr and 2nd flr, exit #5 thedoors have defetive in the hinges and closers. the doors remain open after use. rmdy: comply with code.
Oct 27, 2016
Resolve - Class - 1
Reissue #32071852r work w/o a permit. noted: install laars pw0715n09k boiler 715.000 btu's w/o permit. rmdy: comply with code.
Oct 27, 2016
Active - Class - 2
Reissue #35094395l failure to maintain building wall(s) or appurten ances. noted: water damage to ceiling due to water penetration throughroof at 1st flr in auditorium, gym and kindergarten area.rmdy: comply
Oct 27, 2016
Resolve - Class - 2
Reissue #35094398r failure to maintain building in code-compliant manner. noted: throughout basement, water penetration from foundation walls causing damage to walls at boiler room and electrical room.rmdy:com
Oct 27, 2016
Resolve - Class - 2
Failure to maintain bldg wall(s)or appurtenances.uneven pavement.@ gymexit & where the entrance is for playground,pavement is uneven & riseswhere the entrance gates are.rem:repair pavement.
Mar 18, 2015
Resolve - Class - 2
Foundation wall. throughout basement in various areas, water penetrating from foundation walls & entering basement causing puddling. remedy: provide waterproofing on foundation walls.
May 1, 2014
Resolve - Class - 2
Water penetration from facade. throughout bldg in various rooms, water penetrating through interior walls from facade. remedy: provide waterproofing on facade in various areas.
May 1, 2014
Resolve - Class - 2
Water penetration. throughout bldg, there is water penetrating in various areas of all levels of bldg from roof,facade & foundation walls. remedy: prevent water penetration.
May 1, 2014
Resolve - Class - 2
Roof leaks. throughout 3rd floor in various areas of hallway & classrooms, water penetrating from roof onto ceilings. the roof of auditorium & kindergarten wing, which is 1 level, roof water penetrating onto c
May 1, 2014
Resolve - Class - 2
27-371(b):plexi vission panels installed on doors at various locationsrem:provide required glass panels.
Jun 21, 2012
Resolve - Class - 3
Ceiling in auditorium has water damaged plaster. rem:repair ceiling.
Jun 21, 2012
Resolve - Class - 1
B101. installe laars pw0715n09k boiler 715,000 btu's w/out permit.
May 4, 2012
Active - Class - 2
Exit door has sliding bolts remove but the hasp locks remained located on the 1fl exit doors on elverton ave rem: remove hasp locks on exit doors
Oct 27, 2011
Resolve - Class - 3
(r-032), @ 2nd flr, sw corner, 3 broken windows no window guards installed this room. remedy: repair broken windows.
Aug 4, 2010
Resolve - Class - 2
(r-032) at gas meter room, storage present: key machine, tablesaw, lp vinyl records. speakers...etc. remedy: remove all storage from gas meter room.
Aug 4, 2010
Resolve - Class - 2
(r-032) @ 246 plexiglass installed @ vision panel, eliminating flame spread rating. remedy: install appropriate material @ vision panels maintain flame spread rating.
Aug 4, 2010
Resolve - Non-hazardous
19b/36 bq9 bq9 - teledyne laars model lq750 hot water boiler.
Jan 14, 2005
Active - Non-hazardous
* re - issue * failure to maintain. noted ; door jambs / center posts rotted out at bottom at exit 2 & 3 and exit 1 remedy : repair / replace door jambs
Jan 9, 2002
Resolve - Non-hazardous
Failure to obtain a permit for temporary construction.noted:a sidewalk shed was installed on the south side of school without a permit.remeyd:obtain permit for sidewalk shed
Apr 4, 2001
Resolve - Non-hazardous
Failrue to maintain:defect is:in stairwell #1, between floor levels 2 and 3 the wall tile is cracked.remedy:maintain bldg make all necessary repairs forthwith.
Apr 4, 2001
Resolve - Non-hazardous
Failure to maintain.defect is:at exits #s 1,2/3,4/5,6 and the gymnasium exit, have corroded and rotted doors and door bucks.remedy:maintain bldg,make all necessary repairs forthwith
Apr 4, 2001
Resolve - Non-hazardous
Failure to maintain.defect is:the is cracked brick and cracked and loose mortor joints in the following locations:the facade on the east side of school.at exit # 4/5 at exit #6, on the south west corner,north
Apr 4, 2001
Resolve - Non-hazardous
Failure to maintain.defect is:1-the gates are missing from the perimeter fence on the south side of the playfield 2-a gate is missing at the south east corner of the wrought iron fence.remedy:maintain perimter
Apr 4, 2001
Resolve - Non-hazardous
Failure to maintain.defect is:the asphalt surface of the playground has large cracks.remedy:maintain playground,make all necessary repairs forthwith.
Apr 4, 2001
Resolve - Non-hazardous
Failure to maintain bldg. defect is: mortar joint cracked causing 3 bricks slightly projecting out at rear of school. at parapet wall staircase #1. remedy: repair or replace.
Jun 16, 1999
Resolve