roofy

166 Hillside Terrace

Staten Island, NY 10308BBL 5-05148-0025Map

Owner of record: Theodora Stolz

166 Hillside Terrace is an one-family home built in 1940 in Staten Island, 10308. It has 1 residential unit across 2.5 floors. The owner of record is Theodora Stolz. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
3
ECB violations
16
HPD complaints
0

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 3

  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    May 30, 2012

    Dob violation - active
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    May 30, 2012

    Dob violation - active
  • Construction other optional

    C-construction other optional

    Dec 10, 2009

    Dob violation - active

ECB violations · 16

  • Class - 2

    Failure to comply w/the commissioner's order to file a c/c w/the dob for nov #34935880m issued on 3.6.12 pursuant to 28-204.4 & 1rcny 102-01. remedy: file a c/c.

    Oct 19, 2013

    Resolve
  • Class - 1

    Failure to comply w/commissioner's order contained in nov#34935880m issued on 3/6/12. work w/o permit. at rear exposure 4 erected structure with room. rmdy: comply with commissioner's order.

    Oct 19, 2013 · Penalty $6,000

    Active
  • Class - 1

    Failure to comply w/the commissioner's order contained in nov #34935880m issued on 3.6.12. work w/o permit. noted: at rear erected structurew/room at rear right side of house. remedy:comply w/the commissioner's

    Aug 28, 2013 · Penalty $2,400

    Active
  • Class - 1

    Failure to comply w/the commissioner's order to correct conditions cited in nov #34935880m issued on 3.6.12 for constructing a room at rear right side w/o a permit. remedy: comply w/code.

    Oct 10, 2012 · Penalty $2,400

    Resolve
  • Class - 1

    Failure to comply with the commissioner's order to correct conditions cited in nov 34935880m issued on 3/6/12 for constructing a room at the rear right side without a permit. rem:comply with code.

    Aug 31, 2012 · Penalty $6,000

    Resolve
  • Class - 1

    Failure to comply w/the comm's order contained in nov #34935747n issued on 3/2/12 for work w/o permit-left side block retaining wall. remedy: comply w/code.

    Jul 12, 2012 · Penalty $6,000

    Resolve
  • Class - 1

    Failure to comply w/the comm's order contained in nov #34935880m issued on 3/6/12 for work w/o permit-right side rear room. remedy: comply w/code.

    Jul 12, 2012 · Penalty $6,000

    Resolve
  • Class - 1

    Failure to comply with the commissioner's order contained in nov#34935747n issued on 3/2/12 for work without permit left side block retaining wall. rem:comply with code.

    May 9, 2012 · Penalty $2,400

    Resolve
  • Class - 1

    Failure to comply with the commissioner's order contained in nov #34935880m issued on 3/6/12 for work without permit right side rear room. rem:comply with code.

    May 9, 2012 · Penalty $2,400

    Resolve
  • Class - 1

    Work w/o a permit. work noted: at the time of my inspection i observedat the right side rear of the property there was a new room that was constructed framed, (sheathed), roofed at the interior the walls were

    Mar 6, 2012 · Penalty $1,600

    Active
Show 6 more ↓
  • Class - 1

    Unlawfully continued work while on notice of a stop work order noted.@time of insp i observed work at the (right rear) of the property constructed a new room this arear was (almost)85% complete west const fully

    Mar 6, 2012

    Resolve
  • Class - 1

    Work w/o a permit. noted: at the time of my inspection i observed a block retaining wall being constructed the wall was in the process of being placed at the left side front & the leeft side the area is approx

    Mar 2, 2012 · Penalty $1,600

    Active
  • Hazardous

    Illegal use in residential district noted: there are 2 @ 6'w x 20'l x 8'h steel sea containers @ rear yard in a r1-2 residential district asdead storage. remedy: remove containers/ discontinue illegal use.

    Oct 26, 2007

    Resolve
  • Hazardous

    Work w/o a permit. work noted: the installation of 2 @ 6'w x 20'l x 8'h steel sea containers @ rear yard being used as storage sheds. shed are 160 sq each. remedy: obtain permit or restore premises to prior

    Oct 26, 2007

    Resolve
  • Hazardous

    Failure to maintain adequate housekeeping.noted:upon my inspection i observed debris all over property large pieces of wood.nails sticking out garbage bags all over property.construction material the entire rea

    Aug 17, 2007 · Penalty $500

    Resolve
  • Non-hazardous

    Failure to maintain noted: property is consumed with overgrown weeds,trees, shrubs & ivy so much so that it is encroaching neighboring properties remedy: maintian property

    Sep 3, 2004 · Penalty $180

    Resolve

Complaints

No HPD complaints in our records

Complaint data is still being backfilled from NYC Open Data.

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
One-family home (A1)
Year built
1940
Floors
2.5
Residential units
1
Building area
2,580 ft²
Lot area
14,150 ft²
Zoning
R1-2
Community board
503
Council district
51
Block / lot
5148 / 25
Assessed value
$58,080
Landmark / historic district
No

Questions about 166 Hillside Terrace

Who owns 166 Hillside Terrace?

The owner of record in NYC Department of City Planning PLUTO data is Theodora Stolz.

Does 166 Hillside Terrace have violations?

NYC HPD has no housing violations on record for this property.

Is 166 Hillside Terrace rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 166 Hillside Terrace built?

City records list 1940 as the year it was built.

How many apartments are in 166 Hillside Terrace?

It has 1 residential units.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.