roofy

88 Guyon Avenue

Staten Island, NY 10306BBL 5-04655-0045Map

Owner of record: 80-90 Guyon Avenue Assoc Ltd.

88 Guyon Avenue is a store building built in 1968 in Staten Island, 10306. The owner of record is 80-90 Guyon Avenue Assoc Ltd.. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
28
ECB violations
4
HPD complaints
0

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 28

  • High pressure boiler boiler required

    Violation issued-failure to file 2020 external hgh pressure inspection

    Jun 30, 2023

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued-failure to file 2020 external hgh pressure inspection

    Jun 30, 2023

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued-failure to file 2020 internal hgh pressure inspection

    Jun 30, 2023

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued-failure to file 2020 internal hgh pressure inspection

    Jun 30, 2023

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued-failure to file 2021 external hgh pressure inspection

    Jun 30, 2023

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued-failure to file 2021 external hgh pressure inspection

    Jun 30, 2023

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued-failure to file 2021 internal hgh pressure inspection

    Jun 30, 2023

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued-failure to file 2021 internal hgh pressure inspection

    Jun 30, 2023

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued-failure to file 2018 external hgh pressure inspection

    Jun 20, 2023

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued-failure to file 2018 external hgh pressure inspection

    Jun 20, 2023

    Dob violation - dismissed
Show 18 more ↓
  • High pressure boiler boiler required

    Violation issued-failure to file 2018 internal hgh pressure inspection

    Jun 20, 2023

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued-failure to file 2018 internal hgh pressure inspection

    Jun 20, 2023

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued-failure to file 2019 external hgh pressure inspection

    Jun 20, 2023

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued-failure to file 2019 external hgh pressure inspection

    Jun 20, 2023

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued-failure to file 2019 internal hgh pressure inspection

    Jun 20, 2023

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued-failure to file 2019 internal hgh pressure inspection

    Jun 20, 2023

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued-failure to file 2022 internal high pressure inspection

    Apr 25, 2023

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued-failure to file 2022 internal high pressure inspection

    Apr 25, 2023

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued-failure to file 2022 external high pressure inspection

    Apr 25, 2023

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued-failure to file 2022 external high pressure inspection

    Apr 25, 2023

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued - failure to file 2017 external high pressure boiler inspection

    Mar 16, 2020

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued - failure to file 2017 external high pressure boiler inspection

    Mar 16, 2020

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued - failure to file 2017 internal high pressure boiler inspection

    Mar 16, 2020

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued - failure to file 2017 internal high pressure boiler inspection

    Mar 16, 2020

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued for failure to file 2016 annual high pressure boiler inspection

    Jun 22, 2018

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued for failure to file 2016 annual high pressure boiler inspection

    Jun 22, 2018

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued for failure to file 2015 annual high pressure boiler inspection

    Jun 23, 2017

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued for failure to file 2015 annual high pressure boiler inspection

    Jun 23, 2017

    Dob violation - dismissed

ECB violations · 4

  • Non-hazardous

    B4a,50a,50b.50a-reverse boiler blow down valve,slow opening terminate last.50b-flue pipe defective.

    Jun 26, 2007 · Penalty $180

    Resolve
  • Hazardous

    Cease use.b4b,3a,24b,48b,50a,51.50a-need support on flue pipe from theceiling.

    Jun 26, 2007 · Penalty $400

    Resolve
  • Non-hazardous

    36 49 49)bq9-27-147 fulton fb010-a high pressure boiler nb#84543 1999 year installed without permit from dob boiler division.27-793 fulton boiler operating without an equipment from dob.must submit 900a as pr

    Feb 23, 2001 · Penalty $850

    Resolve
  • Non-hazardous

    8a,8b,8c,9a,9b-pertains to bottom handholes welding.

    Jun 29, 1999 · Penalty $350

    Resolve

Complaints

No HPD complaints in our records

Complaint data is still being backfilled from NYC Open Data.

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Store building (K1)
Year built
1968
Floors
1
Residential units
—
Building area
7,000 ft²
Lot area
20,380 ft²
Zoning
R3-2
Community board
503
Council district
50
Block / lot
4655 / 45
Assessed value
$1,012,500
Landmark / historic district
No

Questions about 88 Guyon Avenue

Who owns 88 Guyon Avenue?

The owner of record in NYC Department of City Planning PLUTO data is 80-90 Guyon Avenue Assoc Ltd..

Does 88 Guyon Avenue have violations?

NYC HPD has no housing violations on record for this property.

Is 88 Guyon Avenue rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 88 Guyon Avenue built?

City records list 1968 as the year it was built.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.