HPD housing violations

No HPD violations on record

DOB building violations

17 DOB violations, newest first.

  • Low pressure boiler boiler required

    Violation issued-failure to file 2024 external low pressure inspection

    Nov 14, 2025

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued-failure to file 2023 external low pressure inspection

    Sep 23, 2024

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued-failure to file 2021 external low pressure inspection

    Jun 30, 2023

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued-failure to file 2020 external low pressure inspection

    Jun 30, 2023

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued-failure to file 2019 external low pressure inspection

    Jun 20, 2023

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued-failure to file 2018 external low pressure inspection

    Jun 20, 2023

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued-failure to file 2022 external low pressure inspection

    Apr 25, 2023

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Oct 5, 2021

    Dob violation - active
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2017 inspection report

    Jan 17, 2020

    Dob violation - dismissed
  • Construction other optional

    The si borough commissioner has issued a stop work order to permit/ job app#520261699 due to the permit holder or record has informed the dept that she/he has withdrawn from the projet. the work being remedy:comply with the commissionerorder. the permit holder of record need to inform the si borough commiss office to resolve this issue

    Oct 23, 2017

    Dob violation - dismissed
  • Construction other optional

    The boro commissioner's office has ordered all work at site and loca- tionstopped as of 7/7/17 for job #520271615. the permit holder of record has withdrawn from the project. approx. 60% of work was comple ted remedy: stop all work at site and location

    Jul 10, 2017

    Vw*-violation - work w/o permit dismissed
  • Construction other optional

    Based on inspect on 12/2/16,observed issues on construction. flr joist connect to steel ibeams@2ndfl questionable.welding tr-1 need aws cert connection of new wood joist to cmv walls questionable.remedy:stop all work.request meeting/audit to resolve all questionable items above contact feu office at 212-393-2433 to setup meeting no later 12/12/16

    Dec 5, 2016

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Apr 6, 2016

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2014 inspection report

    Oct 1, 2015

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2013 inspection report

    Mar 3, 2015

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2013 inspection report

    Mar 3, 2015

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Sep 16, 1997

    Dob violation - dismissed

ECB violations

3 ECB violations, newest first.

  • Class - 2

    Jobsite fence not constructed or maintained pursuant to subsection.note:at time of inspection i observed job site fence on 2nd exposure is leaning over towards sidewalk.temporary construction fence may fall ont

    Sep 14, 2018

    Resolve
  • Class - 2

    Failure to safeguard all person & property afected by construction operations.in that exterior construction ongoing w.o a construction fencemultiple trip hazard throughout .no guard rails @stairwells &elevator

    Dec 2, 2016

    Resolve
  • Class - 1

    Work w/o a permit. noted: in a renovation of bldg at 2nd fl all partition wall is demolished & constructed new partition wall several ceiling beam replaced. some ceiling replaced & all electrical points & wirin

    Jan 4, 2016 · Penalty $1,630

    Resolve