roofy

Violations at 266 West Service Road

Staten Island, NY 10314 · BBL 5-02654-0045 · Back to the property

HPD housing violations

No HPD violations on record

DOB building violations

17 DOB violations, newest first.

  • Low pressure boiler boiler required

    Violation issued-failure to file 2018 external low pressure inspection

    Jun 20, 2023

    Dob violation - active
  • Low pressure boiler boiler required

    Violation issued-failure to file 2018 external low pressure inspection

    Jun 20, 2023

    Dob violation - active
  • Low pressure boiler boiler required

    Violation issued-failure to file 2018 external low pressure inspection

    Jun 20, 2023

    Dob violation - active
  • Low pressure boiler boiler required

    Violation issued-failure to file 2018 external low pressure inspection

    Jun 20, 2023

    Dob violation - active
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2017 inspection report

    Nov 8, 2019

    Dob violation - active
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2017 inspection report

    Nov 8, 2019

    Dob violation - active
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2017 inspection report

    Nov 8, 2019

    Dob violation - active
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2017 inspection report

    Nov 8, 2019

    Dob violation - active
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Aug 30, 2017

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Oct 20, 2015

    Dob violation - resolved
  • Construction other optional

    Fail to main. on 11/28/14 a partial coll occured inside the steel fram ed car show rm at the svs area mezz area. a partial coll occured. the bldg has been vacated. cure: the owner is to engage a lic contr & a li c prof. to imd work with the dept to move mezz debris & to stab remain path coll inter struc. all under super of bob & contractors, p.e

    Dec 2, 2014

    Dob violation - dismissed
  • Construction other optional

    Failure to maintain.partial collapse occured inside the steel framed warehouse at the service area mezzanine.the building has been. vacated and is not to be accessed without dob authorization.owner to hire 3rd party contractor to board up exdterior openings, broken windows and provide access to dob and no other access

    Nov 28, 2014

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Nov 28, 2014

    Dob violation - dismissed
  • Elevator annual inspection / test elevatorrequired

    Violation issued to elevator-failure to file category 1 2013 inspection/test

    Oct 31, 2014

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    May 4, 1998

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Aug 29, 1995

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Jun 8, 1994

    Dob violation - dismissed

ECB violations

3 ECB violations, newest first.

  • Class - 1

    Sec. 3303.4.6 storage of combustible material & equipment. storage of combustible material & other material & equipment that may present (future) hazard shall comply w/the new york fire code. note: at the time

    Mar 25, 2013 · Penalty $1,600

    Resolve
  • Class - 2

    Job site fence not constructed pursuant to subsection. note: at the time of my inspection on construction site fence in place,around site w/section missing at exp 2,3 & 4 making site excessible to the public.

    Mar 25, 2013

    Resolve
  • Non-hazardous

    19b/4a/36 - spill switch is disconnected (no wiring). boiler sealed remove boxes surrounding boiler.

    Oct 23, 2000 · Penalty $400

    Resolve