10 DOB violations, newest first.
- Low pressure boiler boiler required
Violation issued-failure to file 2024 external low pressure inspection
Nov 14, 2025
Dob violation - dismissed - High pressure boiler boiler required
Violation issued-failure to file 2022 internal high pressure inspection
Apr 25, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2013 inspection report
Mar 3, 2015
Dob violation - active - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2012 inspection report
May 15, 2014
Dob violation - active - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2010 inspection report
Dec 13, 2011
Dob violation - active - Construction other optional
C-construction other optional
Nov 18, 2010
Dob violation - active - Construction other optional
C-construction other optional
Mar 3, 2006
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Feb 13, 2004
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Sep 16, 1997
Dob violation - active - Boiler boiler optional
B-boiler boiler optional
Jun 17, 1992
Vp-violation unserved ecb-active
ECB violations
11 ECB violations, newest first.
- Class - 2
Unregisted boiler,open basement need to fire proof or construct fire proof boiler room,boiler to be on solid blocks,cold wtr feed to be on return ,relief valve on wtr htr to be 8" off floor,missing insulation,c
Jun 27, 2022 · Penalty $625
Resolve - Class - 2
Found weil mclain boiler model # cga-6 pidn serial# cp7931903 unregistered obtain the neccesary permit and register the boiler.
Nov 24, 2021 · Penalty $625
Active - Class - 2
6a,15,32a,50a-c. (50a)no storage around boiler (50b)wrong material for flue support (50c)no clean out on chimney base. correct all violating conditions & submit a c of c.
Mar 7, 2018 · Penalty $312
Resolve - Class - 3
Work does not conform to approved construction documents/amendments pro cert job 410154498 dwg 8/22/08. noted: kitchen dropped ceiling is not shown on plan and no detail provided. remedy: conform to approved
Jun 28, 2010 · Penalty $100
Resolve - Class - 1
Failure to maintain bldg in code compliant manner no firestopping as per bc1014.2 noted missing approx 80sq ft of ceiling in cellar exposing wood fl and joist of 1st fl remedy: provide maintain firestopping
Jun 3, 2009 · Penalty $1,000
Active - Class - 1
Failure to maintain bldg in a code compliant manner noted underminning of 2inch concrete (unreinforced) cellar fl 2-3ft beyond sump pump well at a depth of approx 5ft remedy: support concrete slab obtain and su
Jun 3, 2009 · Penalty $1,000
Active - Non-hazardous
50(a)/ 50(b)/ 48(a)(b)/ 21(b)/ columbia vt boiler, 15 hp, nb 135532, oil, 50(a) evidence of flue gas leakage @ combustion chamber seal, top of boiler. re-seal area. 50(b) no drain line on the gauge glass assemb
Feb 5, 2007
Resolve - Non-hazardous
38
Oct 3, 2005 · Penalty $2,000
Resolve - Non-hazardous
38 50a 50b 1995 columbia n.b. 135532 50a holes in ceiling. 50b add a slow opening valve on the bottom blowdown line after the quick opening valve.
Jun 7, 2005
Resolve - Non-hazardous
14b-49 (1)brick chimney to clean-2-flue pipe to seal gastight in the chimney hole.3.low water cutoff-manual reset pin missing in mcdonal miller cover.
Apr 6, 2001
Resolve - Hazardous
36,17a,17b,33a,33b,49, boiler installed and operated without obtainingnecessary permits from this dept of buildings.. re
Jun 17, 1992 · Penalty $500
Active