roofy

36-35 College Point Blvd

Queens, NY 11354BBL 4-04970-0001Map

Owner of record: Cpbspe LLC

36-35 College Point Blvd is a vacant lot in Queens, 11354. The owner of record is Cpbspe LLC. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
1
ECB violations
28
HPD complaints
0

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 1

  • Failure to benchmark none

    Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4

    Jun 1, 2022

    Dob violation - active

ECB violations · 28

  • Class - 2

    Atoi due to severe weather advisory observed styrofoam insulation at street level at exp 1 & 2 creating trip & fall conditions to the public as well as hazardous conditions to vehicular traffic in the event of

    Sep 27, 2026 · Penalty $5,000

    Active
  • Class - 2

    3303.4.2 containers. observed at exp 1 by gate near the pedestrian passageway combustible debris not stored in a non combustible container as required in code, creating fire hazards if a cigarette were to be di

    Sep 27, 2026 · Penalty $2,500

    Active
  • Class - 2

    Bc 3301.9.7 other signs prohibited:b atoi observed sidewalk shed parapet at exp 1 & 4 with prohibited signs for leasing opportunities.remove signs

    Sep 27, 2026 · Penalty $2,500

    Active
  • Class - 2

    Work does not conform to approved construction documents and/or approved amendments. as noted at the time of inspection of a proposed 15 story new building actively placing rebar on 13 floor slab level. observe

    Aug 20, 2026 · Penalty $1,250

    Active
  • Class - 2

    Bc 3301.2 safety measures and standards atoi observed construction debris at adjoining property, concrete formwork locking pins as well as styrofoam found through out adjoining property creating unsafe struck b

    Aug 20, 2026 · Penalty $5,000

    Active
  • Class - 1

    At time of inspection of a proposed 15 story building observed crane in operation at exp 2 for rebar delivery on 11th floor when researching the departmental approved site safety plan the crane was not shown. s

    Aug 14, 2026 · Penalty $2,500

    Active
  • Class - 1

    Proposed 15 story new building with foundation poured and footprint of approx. 29,581 sq. ft. site closed and there was no construction activity. upon shouting at perimeter and banging on fence to alert watchpe

    Feb 7, 2026 · Penalty $5,000

    Resolve
  • Class - 1

    New 15 story mix use building : observed 2 heavy machinery excavators parked on the leading edge of the sheer-cut at the bottom of the excavation. no pe-approved drawings. stop all parking of heavy machinery on

    Dec 22, 2025

    Resolve
  • Class - 1

    At time of inspection, observed three welders performing hot work with no fire guard or fire watch present. contrary to bc 3301.1.2, failure to maintain required fire watch created immediate fire hazard.provide

    Dec 19, 2025 · Penalty $5,000

    Resolve
  • Class - 1

    At time of inspection, observed three welders performing hot work under one hot work permit. contrary to bc 3301.1.2 and fc 3501.1, each distinct hot work operation requires its own authorization. condition cre

    Dec 19, 2025 · Penalty $5,000

    Resolve
Show 18 more ↓
  • Class - 1

    At time of inspection, observed three workers performing welding; one produced valid dob welder license, two departed without presenting required license. contrary to ac 28-401.5, unlicensed welding operations

    Dec 19, 2025 · Penalty $5,000

    Resolve
  • Class - 1

    At time of inspection, observed multiple welding operations without required 2-a:20-b:c fire extinguishers within 30 ft of each torch location. contrary to bc 3301.1.2 & fc 3504.2.6, failure to provide dedicate

    Dec 19, 2025 · Penalty $5,000

    Resolve
  • Class - 1

    At time of inspection, observed jersey barriers unfilled and collapsed into roadway. contrary to bc 3301.1.3 & 3301.2, failure to maintain barriers in accordance with manufacturer specifications created unsafe

    Dec 19, 2025 · Penalty $5,000

    Resolve
  • Class - 2

    At time of inspection observed active job site. the job site excavation and foundation level under construction. the job site fence gate/entrance installed not confirm as per plan. upon request for any document

    Dec 13, 2025

    Resolve
  • Class - 2

    At time of inspection of a 15-story new building at soe and foundation phase, during my inspection i observed ramp being using by workers and machine 12-feet ramp provide onsite not maintain as per code (3315.1

    Aug 9, 2025 · Penalty $2,500

    Active
  • Class - 3

    Work does not conform to approved construction documents/amendments. observed at time of insp,erection of interior sheetrock partition wallfor the display shelf approx 40'long 7'high & steel rolling gate appro

    Mar 13, 2009

    Resolve
  • Class - 2

    Failure to comply with the commissioner's order to file a certificate of correction with the department of buildings for ecb #34561635p,issued 1/31/07. remedy: file certificate of correction.

    Jan 7, 2009 · Penalty $800

    Resolve
  • Class - 2

    Failure to comply with the commissioner's order to file a certificate of correction with the department of buildings for ecb #34561410y issued 2/7/07. remedy: file certificate of correction.

    Jan 7, 2009 · Penalty $800

    Resolve
  • Class - 1

    Failure to maintain building interior observed: missing ceiling panels throughout space stained/bulging ceiling grid in 1st flr of premises.hanging/exposed electrical wires in ceiling pounding water on flr of

    Jan 7, 2009 · Penalty $1,000

    Resolve
  • Class - 2

    Failure to comply with the commissioner's order to file a certificate of correction with the department of buildings for ecb #34561406l,issued 2/7/07. remedy: file certificate of correction.

    Jan 7, 2009 · Penalty $800

    Resolve
  • Class - 1

    Failure to maintain building interior observed: missing,bulging,water stained ceiling tile throughout premises,missing & hanging ceiling grid,exposed & hanging electrical wires throughout space placing workers

    Jan 7, 2009 · Penalty $1,000

    Resolve
  • Class - 2

    Work w.o permit. work noted: at time of insp, store is being renovatedpartitions walls are being built w/wood studs & new bx & receptacles. a new drop ceiling grid has been installed, lival ductwork & insulatio

    Dec 10, 2008 · Penalty $800

    Resolve
  • Non-hazardous

    Failure to maintain bldg interior.defects noted:at 1st fl ceiling.missing panels & warping in various locations w/ marks evident.at rear/north east corner-half bathroom in place approx 5' x 4' x 10' high

    Feb 7, 2007 · Penalty $350

    Active
  • Non-hazardous

    Alt bldg occupied w/o a valid c of o. entire bldg occupied. alt 1 # 400758300-09/05/97.remedy:discontinue illegal occupancy and obtain valid c/o

    Feb 7, 2007

    Resolve
  • Non-hazardous

    Work w/o a permit. work noted:at 1st fl partition wall including office erected to separate show room & storage.at rear/ storage-structure built approx 10'h to store materials in boxes.at front of signage was

    Feb 7, 2007

    Resolve
  • Non-hazardous

    Failure to maintain bldg.interior defects noted:at 1st fl show room-ceiling is damaged missing panels,warping w/ marks evident in various locations.at rear/storage -ceiling-missing panels found & at south east

    Feb 7, 2007

    Resolve
  • Non-hazardous

    Work w/o a permit. work noted:at front-2 awning was built approx 3' x 12' & approx 12' above grade each & printed liu way sign inc. at 1st fl rear a suspended structure was installed approx 15' x 50' x 6'h

    Feb 7, 2007 · Penalty $500

    Resolve
  • Non-hazardous

    Altered building occupied without a valid certificate of occupancy foralt 1 - 400758300. all mezzanines are occupied throughout store building. remedy:obtain a valid certificate of occupancy.

    Jan 31, 2007 · Penalty $180

    Active

Complaints

No HPD complaints in our records

Complaint data is still being backfilled from NYC Open Data.

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Vacant lot (V1)
Year built
—
Floors
—
Residential units
—
Building area
—
Lot area
29,828 ft²
Zoning
C4-2
Community board
407
Council district
20
Block / lot
4970 / 1
Assessed value
$963,450
Landmark / historic district
No

Questions about 36-35 College Point Blvd

Who owns 36-35 College Point Blvd?

The owner of record in NYC Department of City Planning PLUTO data is Cpbspe LLC.

Does 36-35 College Point Blvd have violations?

NYC HPD has no housing violations on record for this property.

Is 36-35 College Point Blvd rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.