71-13 60 Lane is an elevator apartment building built in 1930 in Queens, 11385. It has 55 residential units across 5 floors. The owner of record is New Ridgewood LLC. HPD has recorded 12 housing violations here, most recently on June 11, 2025.

HPD violations
12
DOB violations
61
ECB violations
52
HPD complaints
28

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
Last violation Jun 11, 2025

Date of the most recent HPD inspection that found a problem.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 12

  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Jun 11, 2025

    Closed — Violation dismissed
  • A

    Post and maintain a proper notice on wall of the entrance story in english and spanish on the availability of the agencys housing information guide. a sample notice can be found at www.nyc.gov/hpd. at public hall, 1st story

    May 29, 2022

    Closed — Violation dismissed
  • A

    Post, in a form approved by the commissioner, and maintain a notice in a common area of the building regarding the procedures that should be followed when a gas leak is suspected at public hall, 1st story

    May 29, 2022

    Closed — Violation dismissed
  • A

    Post a proper notice of smoke detector requirements, in a form approved by the commissioner, at or near the mail box paper sign at public hall, 1st story

    May 29, 2022

    Closed — Violation dismissed
  • A

    Post, in a form approved by the commissioner, and maintain a notice in a common area of the building regarding the procedures that should be followed when a gas leak is suspected at public hall, 1st story

    Jan 27, 2021

    Closed — Violation dismissed
  • A

    Post and maintain a proper notice on wall of the entrance story in english and spanish on the availability of the agencys housing information guide. a sample notice can be found at www.nyc.gov/hpd. at public hall, 1st story

    Jan 27, 2021

    Closed — Violation dismissed
  • A

    Post a proper notice of smoke detector requirements, in a form approved by the commissioner, at or near the mail box .. at public hall, 1st story

    Jan 27, 2021

    Closed — Violation dismissed
  • A

    Post and maintain a proper sign on wall of entrance story showing the registration number assigned by the department and the address of the building. at public hall, 1st story

    Jan 27, 2021

    Closed — Violation dismissed
  • A

    Post a proper notice of carbon monoxide detecting device requirements, in a form approved by the commissioner, in a common area of a class a multiple dwelling near inspection certificate or provide notice to tenants in a private dwelling.

    Jan 27, 2021

    Closed — Violation dismissed
  • A

    § 329, m/d law and dept. rules and regs. provide a completed certificate of inspection visits in a proper frame at or near mailboxes, bottom edge of frame between 48-62 inches above floor .. at public hall, 1st story

    Jan 27, 2021

    Closed — Violation dismissed
Show 2 more ↓
  • A

    Post sign on wall of entrance story bearing name, address including apartment number if any, and telephone number of superintendent, janitor or housekeeper. at public hall, 1st story

    Jan 27, 2021

    Closed — Violation dismissed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 17, 2016

    Closed — Violation dismissed

DOB building violations · 61

  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Nov 1, 2019

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Sep 22, 2018

    Dob violation - resolved
  • Failure to benchmark none

    Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4

    Aug 2, 2017

    Dob violation - dismissed
  • Failure to benchmark none

    Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4

    May 2, 2017

    Dob violation - active
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2015 inspection report

    Feb 24, 2017

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jun 17, 2015

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jun 17, 2015

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jun 11, 2014

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jun 11, 2014

    Dob violation - resolved
  • Failure to benchmark none

    Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4

    May 1, 2014

    Dob violation - active
Show 40 more ↓
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 7, 2013

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 7, 2013

    Dob violation - resolved
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2011 inspection report

    Mar 1, 2013

    Dob violation - dismissed
  • Elevator annual inspection / test elevatorrequired

    Violation issued to elevator-failure to file category 1 2011 inspection/test

    Oct 1, 2012

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    May 30, 2012

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jan 26, 2012

    Vw*-violation - work w/o permit dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jan 26, 2012

    Vw*-violation - work w/o permit dismissed
  • Failure to benchmark none

    Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4

    Jan 1, 2012

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Violation issued for failure to file annual boiler 2010 inspection report

    Dec 13, 2011

    Dob violation - dismissed
  • Elevator annual inspection / test elevatorrequired

    Violation issued to elevator-failure to file category 1 2010 inspection/test

    Dec 13, 2011

    Dob violation - dismissed
  • Elevator annual inspection / test elevatorrequired

    Vcat1-elevator annual inspection / test elevatorrequired

    Oct 8, 2010

    Dob violation - dismissed
  • Low pressure boiler boiler required

    Lblvio-low pressure boiler boiler required

    Dec 31, 2009

    Dob violation - dismissed
  • Elevator elevatoroptional

    Ll1081-local law 10/81 - elevator elevatoroptional

    Feb 27, 2009

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Jan 2, 2009

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Jan 1, 2009

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 19, 2008

    Vw*-violation - work w/o permit dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 19, 2008

    Dob violation - resolved
  • Elevator elevatoroptional

    Ll1081-local law 10/81 - elevator elevatoroptional

    Mar 21, 2008

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Jan 3, 2008

    Dob violation - dismissed
  • Elevator elevatoroptional

    Ll1081-local law 10/81 - elevator elevatoroptional

    Apr 2, 2007

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Jan 19, 2007

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Jan 6, 2006

    Dob violation - dismissed
  • Elevator elevatoroptional

    Ll1081-local law 10/81 - elevator elevatoroptional

    Oct 1, 2005

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Apr 27, 2005

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Apr 27, 2005

    Dob violation - resolved
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Jan 31, 2005

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Sep 9, 2004

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Sep 9, 2004

    Dob violation - resolved
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Feb 13, 2004

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Nov 20, 2003

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Nov 20, 2003

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Nov 20, 2003

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Sep 26, 2002

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Sep 26, 2002

    Dob violation - resolved
  • Elevator elevatorrequired

    4p1542

    Oct 4, 2001

    Dob violation - resolved
  • Elevator elevatorrequired

    4f455

    Oct 4, 2001

    Dob violation - resolved
  • Elevator elevatorrequired

    4p1542

    Oct 19, 2000

    Dob violation - resolved
  • Elevator elevatorrequired

    4p455

    Oct 19, 2000

    Dob violation - resolved
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Sep 16, 1997

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Aug 29, 1995

    Dob violation - dismissed

ECB violations · 52

  • Class - 2

    B254,15,32,50. 15-opening in walls and ceilings; 32-wiring exposed inboiler room; 50-spill switch on flue pipe jumped out.

    Sep 2, 2014 · Penalty $1,250

    Resolve
  • Class - 1

    Failure to safeguard all persons & property affected by construction operations. work under permit #402442031-alt 1. miscellaneous safety violation observed on the ground flr workers doing carpentry work withou

    Mar 7, 2012 · Penalty $2,400

    Resolve
  • Class - 2

    Failure to safeguard all persons & property affected by construction operations. work in progress under permit #402442031-alt 1. noted:no smoking signs within construction site not observed in violation of nyc

    Mar 7, 2012 · Penalty $1,200

    Resolve
  • Class - 2

    Failure to maintain adequate housekeeping. construction material/debris not properly stored or removed from site. work under permit #402442031-alt1. noted:excessive debris throuhout the building. in the cellar

    Mar 7, 2012 · Penalty $400

    Resolve
  • Class - 2

    Failure to safeguard all persons and property affected by constructionoperations.work in progress uner permit #40244031. noted:the job observed-stucco on right facade involves installation of foamed plastic boa

    Dec 16, 2011 · Penalty $1,200

    Resolve
  • Class - 1

    Plumbing work w/o a permit. failure to have new or altered plumbing system tested. sprinkler plumbing work for entire building w/o a permit.remedy: obtain a permit to legalize work performed. perform test compl

    Sep 14, 2009

    Resolve
  • Class - 1

    Performing plumbing unlicensed work w/o a master plumbers license. sprinkler plumbing work for entire building. remedy: comply with code.

    Sep 14, 2009 · Penalty $1,000

    Resolve
  • Class - 2

    Work does not conform to approved plan/construction documents & or approved amendments. noted: at time of inspection scaffold permit #410221380 issued 2/4/09 exp 1/20/10. allows scaffold to be erected from 2nd

    Sep 11, 2009 · Penalty $250

    Resolve
  • Class - 1

    Failure to institute maintain safety equipment measures or temp const no guardrails noted at side of bldg (right) exp 4 1 guardrals present at balcony openings thruout all flr remedy: provide guardrail

    Apr 7, 2009

    Resolve
  • Class - 1

    Sec.bc3314.9 supported scaffold (greater than 40ft) not erected to dob code specifications noted at time of inspection supported scaffold was erected at the left side of the job adjacent properties rear yard

    Apr 7, 2009 · Penalty $1,600

    Resolve
Show 40 more ↓
  • Class - 1

    Failure to maintain adjoining property noted: a 4'x8'x3/4" plywood flew away & went to the roof of 1st flr adjoining property at 60-65 nyrtle ave adjoining property has no visible damage. remedy: maintain/prote

    Feb 13, 2009 · Penalty $400

    Resolve
  • Class - 1

    Failure to safeguard all persons and property affected by constructionoperations. defect noted: oxygen tank stored improperly at flr #2 front tank is secured to 2 x 4 wood stud w/ a nylon strap. also noted: pla

    Jan 5, 2009

    Resolve
  • Class - 2

    Failure to maintain adequate housekeeping. noted: piles of 5'high debris of metal, wood & masonry from demo thru-out site. remedy: maintain adequate housekeeping, remove debris. make site safe.

    Dec 31, 2008 · Penalty $400

    Resolve
  • Class - 2

    Job site fence not constructed pursuant to subsection. noted: missing construction fence along approx 60' at rear. remedy: stop all work repair fence.

    Dec 31, 2008 · Penalty $400

    Resolve
  • Class - 1

    Work does not conform to approved plans. noted: approx 1'6" to 2 ft ofsoil was excavated from cellar floor exposing footings of walls & columns. remedy: stop all excavation make site safe.

    Dec 31, 2008 · Penalty $500

    Resolve
  • Class - 1

    Failure to provide protection at sides of excavation defect noted at time of inspection there is an excavation between the bldg for a footing that was poured a sheer cut was made approx. 10-12ft in depth w/no

    Oct 4, 2008 · Penalty $2,400

    Resolve
  • Class - 1

    Failure to carry out demolition operations as required by section defects noted:at time of inspection demolished construction material is being remoced in a dangerous manner wheel barrels full of bricks are bei

    Oct 4, 2008 · Penalty $2,400

    Resolve
  • Class - 1

    Failure to institute maintain safety equipment measures or temporary construction no guard rails defects noted no guard rails at many window openings at openings in fls at all levels at rooftop level no guard

    Oct 4, 2008

    Resolve
  • Class - 2

    Failure to maintain adequate housekeeping per section requirements defects noted:excessive debris observed on all fls of bldg also debris piles observed outside of bldg at exposure #3 some debris is combustible

    Oct 4, 2008 · Penalty $800

    Resolve
  • Class - 1

    Failure to safeguard all persons & property affected by construction operations no netting or plywood at exposure #2 to catch debris & prevent debris from falling into adjacent properties backyards,glass,brick

    Oct 4, 2008

    Resolve
  • Non-hazardous

    Failure to safeguard public and property affected by construction operations. defects noted: at time of inspection there is demolition occurring on the upper floors of a factory bldg. due to demolition work and

    May 14, 2008

    Resolve
  • Hazardous

    Failure to maintain exterior bldg wall.defects noted:front,north & south near front w/missing & broken glass windows.bulging steel windows frames at front 2,3,4 fl;north side at 4fl & south side at 2 & 3 floors

    Mar 18, 2008 · Penalty $2,000

    Resolve
  • Non-hazardous

    Failure to maintain exterior bldg wall. defect noted: at front facade & east & west wall elevation - windows bulging out lintels corroded, broken glass panels. remedy: repair all defects.

    Mar 10, 2008 · Penalty $880

    Resolve
  • Hazardous

    Failure to maintain exterior bldg wall defects noted front north and south near front with missing and broken glass windows bulging window frames at front 2 3 4 flrs north side at 4th fl and south side at 2 & 3

    Nov 21, 2007 · Penalty $2,000

    Resolve
  • Hazardous

    Failure to maintain exterior bldg walls.defect noted:broken glass windows,missing window glass panel,bulging windows,corroded steel unitl evident in various locations.remedy:make all necessary repairs & maintai

    Jul 21, 2007 · Penalty $800

    Resolve
  • Non-hazardous

    50a/18a 50b/50c cyclotherm f.t.s.m boiler 98hs 1035 hs, 50a) no discharge pipe on the safety valve. 50b) improper arrangement of the blowdown valves. 50c) steam pressure gauge dial range is 0-160 psi. install a

    May 18, 2005 · Penalty $2,500

    Resolve
  • Non-hazardous

    50a/50b 50c/50d 18a/50e cyclotherm ftsm boiler 50a) corrosion and heavy scale on boiler shell repair 50c) corrosion and leakage on the watercolumn drain. 50d) gauge glass broken-out of service. 50e) steam

    May 18, 2005 · Penalty $2,500

    Resolve
  • Non-hazardous

    50a/50b 50c hb smith c.i. has blr ser# 28a, oil/gas, 2000 50a) feed water supply connected directly to the front end cast iron section of the referenced boiler. thermal shock hazard presented by the direct

    May 18, 2005 · Penalty $2,500

    Resolve
  • Non-hazardous

    18ab/48ab 6a/50 fulton v.t. boiler, 15hp, nb 44316, gas, 1984 18ab corroded and leaking lower hanhole. repairs in progress. complete repairs. 48ab dirty, corroded and leaking guage glass. assembly. 6a) safety

    May 18, 2005 · Penalty $180

    Resolve
  • Non-hazardous

    50a/50b fulton v.t. boiler, 10hp, nb66391, gas, 1993 50a) secondary low water cut off manual reset switch disconnected. re-connect switch tocircuit in control panel. 50b) corroded and leaking blowdown valves.

    May 18, 2005

    Resolve
  • Non-hazardous

    Bq9/36 50a/50b columbia v.t. boiler, 6hp, nb138107, oil, 1998 bq9 (27-147) referenced high pressure steam boiler was installed and placed inoperation without a permit. 36) boiler is not registered by the d.o.b.

    May 18, 2005 · Penalty $500

    Resolve
  • Non-hazardous

    50a/50b 50c/50d fulton v.t. boiler, 10hp, nb 13639e, oil, 1966 50a) referenced high pressure steam boiler in operation on an open factory floor without an enclosure. install a fire-rated boiler room for code

    May 18, 2005 · Penalty $180

    Resolve
  • Non-hazardous

    50a/50b fulton v.t. boiler, 10hp nb62212, oil, 199(1) 50a) screw threads in place at the outlet end of the safety valve discharge pipe. remove the threads. 50b) improper arrangement of the blowdown valves.

    May 18, 2005

    Resolve
  • Hazardous

    05i11/34q03/12x10/85bb05/84m07/15b07/51tbb/53tbb/16m7 (84) facia plates. (15) post certificate in car as per rule 27-1004 (51) reshackle (53) reshackle cease use until 16.m.7 is complied with.

    Sep 13, 2004 · Penalty $2,500

    Resolve
  • Non-hazardous

    50a,50b,50c. 50a)caseing around bottom hand hole corroded on basement 50b)underated valves on water colume must be rated 200 wsp not 125 wsp50c)underated valves on bottom blow down lines

    Mar 18, 2003

    Resolve
  • Non-hazardous

    49-no key to boiler room on premises.

    Feb 4, 2000 · Penalty $2,500

    Resolve
  • Hazardous

    57o02, 01l11, 09m07, 31q06, 73o02, 20l11, 31d6. 01-l emer stop sw not working, 31q cover elect. boxes in shaft 20l 3rd fl hall call not working 31d electric wiring top of car secure.

    Oct 15, 1999

    Resolve
  • Non-hazardous

    15q,15i,10q,6m,18m,57o,35p,14m,10x,75b. hatch door not closing. gates switches tied up, covers missing, wiring to car gate sw missing. unsafe motor room entrance,

    Sep 13, 1999 · Penalty $500

    Resolve
  • Non-hazardous

    73x, resstore to service so that a full inspection can be made by thisdepartment. call 212-312-8740 for an reinspection.

    Sep 13, 1999

    Resolve
  • Non-hazardous

    Operation of place of assembly without permit. note gym at 4 floor. it has number of machines other equipment to be used by more than 75 persons. obtain pa permit.

    Mar 5, 1999 · Penalty $2,500

    Resolve
  • Non-hazardous

    50y,08v,15b,05j,31d,74o,22d,06r,18m, 15-shaft doors have no handle's 05-car panch not aligned 31-electrical box in shaft basement not covered property 74o-top of elev. dirty 22-emergency exit grill not secured

    Jun 12, 1998 · Penalty $2,500

    Resolve
  • Hazardous

    05m06n31q40o74#73o 31-q-03 provide covers on boxes in shaft. 74-#-#-using equipment without equipment without equipment us permit cease use still in effect.

    Apr 30, 1998 · Penalty $2,500

    Resolve
  • Non-hazardous

    15x57o75r 15-cell d.o.b. when fix for full inspection

    Feb 18, 1998 · Penalty $500

    Resolve
  • Non-hazardous

    57o75r

    Feb 18, 1998

    Resolve
  • Non-hazardous

    36,

    Aug 21, 1997 · Penalty $400

    Resolve
  • Non-hazardous

    Boilers

    Mar 31, 1997 · Penalty $400

    Resolve
  • Non-hazardous

    06m 06m 15j 11i 06m replace gate rollers 2 06m gate wires cover

    Mar 10, 1994 · Penalty $100

    Resolve
  • Non-hazardous

    Local law

    Aug 11, 1992 · Penalty $600

    Resolve
  • Non-hazardous

    73 # 5, 18 m 12, 6 d 11. 5 year test file elv3. replace missing door lock covers. properly wire gate switch.

    Mar 6, 1991 · Penalty $150

    Resolve
  • Non-hazardous

    73#, 15b, 73) 5 year test file elv3. 15) 4th flr hoistway door gibbs.

    Mar 6, 1991 · Penalty $150

    Resolve

Complaints

  • Heat/hot water

    Entire building

    Oct 19, 2026 · Apt BLDG

    Close
  • Heat/hot water

    Entire building

    Oct 19, 2026 · Apt BLDG

    Close
  • Heat/hot water

    Entire building

    Oct 19, 2026 · Apt BLDG

    Close
  • Heat/hot water

    Entire building

    Oct 19, 2026 · Apt BLDG

    Close
  • Heat/hot water

    Entire building

    Oct 18, 2026 · Apt BLDG

    Close
  • Heat/hot water

    Entire building

    Oct 18, 2026 · Apt BLDG

    Close
  • Plumbing

    Bathtub/shower

    Nov 7, 2024 · Apt 306

    Close
  • General

    Signage missing

    Feb 15, 2022 · Apt BLDG

    Close
  • Heat/hot water

    Apartment only

    Jan 24, 2021 · Apt 407

    Close
  • Unsanitary condition

    Mold

    Oct 22, 2015 · Apt 409

    Close
Show 18 more ↓
  • Paint/plaster

    Ceiling

    Oct 22, 2015 · Apt 409

    Close
  • Heat/hot water

    Entire building

    Apr 27, 2014 · Apt 305

    Close
  • General

    Cooking gas

    Jan 30, 2014 · Apt 101

    Close
  • Heating

    Heat related

    Jan 4, 2014 · Apt 501

    Close
  • Heating

    Heat related

    Dec 18, 2013 · Apt 109

    Close
  • Heating

    Heat related

    Dec 8, 2013 · Apt 1

    Close
  • Heating

    Heat related

    Dec 6, 2013 · Apt BLDG

    Close
  • Heating

    Heat related

    Nov 26, 2013 · Apt 102

    Close
  • Heating

    Heat related

    Nov 26, 2013 · Apt NA

    Close
  • General

    Window guards

    Apr 27, 2013 · Apt 205

    Close
  • General

    Window guards

    Apr 27, 2013 · Apt 205

    Close
  • Heating

    Heat related

    Mar 11, 2013 · Apt 103

    Close
  • General

    Cooking gas

    Mar 4, 2013 · Apt 205

    Close
  • Heating

    Heat related

    Nov 14, 2012 · Apt 502

    Close
  • Heating

    Heat related

    Oct 12, 2012 · Apt NA

    Close
  • Plumbing

    Water supply

    Oct 5, 2012 · Apt 201

    Close
  • Construction

    Roof

    Oct 8, 2004 · Apt 4

    Close
  • Heating

    Heat related

    Jan 23, 2004 · Apt BLDG

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Elevator apartment building (D3)
Year built
1930
Floors
5
Residential units
55
Building area
53,884 ft²
Lot area
28,500 ft²
Zoning
R6B
Community board
405
Council district
30
Block / lot
3538 / 67
Assessed value
$4,154,850
Landmark / historic district
No

HPD registration #430572, last renewed Jul 14, 2026.

Questions about 71-13 60 Lane

Who owns 71-13 60 Lane?

The owner of record in NYC Department of City Planning PLUTO data is New Ridgewood LLC.

Does 71-13 60 Lane have violations?

Yes. NYC HPD has recorded 12 housing violations at this property.

Is 71-13 60 Lane rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 71-13 60 Lane built?

City records list 1930 as the year it was built.

How many apartments are in 71-13 60 Lane?

It has 55 residential units.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.