75-42 Grand Central Pkwy
Queens, NY 11375BBL 4-02265-0103Map
Owner of record: Gc 42 LLC
75-42 Grand Central Pkwy is a walk-up apartment building built in 2019 in Queens, 11375. It has 10 residential units across 6 floors. The owner of record is Gc 42 LLC. HPD has no housing violations on record for this property.
- HPD violations
- 0
- DOB violations
- 0
- ECB violations
- 37
- HPD complaints
- 0
What to know
No open immediately-hazardous violations among recent records.
HPD has not cited this building.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 0
No HPD violations on record
DOB building violations · 0
No DOB violations on record
ECB violations · 37
- Class - 2
During my inspection of 6 story nb, observed a supported scaffold approx. 36ft high at exposure #3 which was not in use at time of inspection, scaffold was missing numerous end-rails, toe-boards, levels not ful
Dec 20, 2023
Resolve - Class - 2
I observed 5 workers on site a sidewalk shed installed at exposure 1 and scaffold installed at expos 1&3 (expo 1 on top of shed) upon request to see the following documents to be kept on site none were provided
Aug 30, 2023 · Penalty $625
Resolve - Class - 2
Upon inspection of an active 6 story nb i observed work not contrary to the submitted site safety plan. contrary to ssp no roof protection was provided for 1 story neighboring gar at rear of exposure 2 along wi
Aug 30, 2023 · Penalty $625
Resolve - Class - 2
I observed a side walk shed installed contrary to code. sidewalk shed did not cover full width of sidewalk and shed leg post landed beyond the 18" min from curb line as per code bc3307.6.3 at approx. 62". as we
Aug 30, 2023 · Penalty $2,400
Resolve - Class - 2
I observed pedestrian protection(side walk shed) with pipe scaffold installed on top maintained contrary to code. i observed dirt and debris covered sidewalk shed footings as well as deteriorating/rotted sidewa
Aug 30, 2023 · Penalty $2,400
Resolve - Class - 1
At time of inspection of nb 6 story active jobsite observed worker,cs (han kyu park),on jobsite, upon review dob records it was observed the cs license# 021364, expired on 03/12/23 and job site was active and h
Apr 27, 2023
Resolve - Class - 1
At time of inspection of nb 6 story building active jobsite observed sws installed at exp1, sf installed at exp1,3, platforms at elevator shafts, pulley installed at bulkhead, upon request from cs to see the da
Apr 27, 2023 · Penalty $2,500
Resolve - Class - 1
Violation # 39508574j was issued for unsafe supported scaffold, and it is not in compliance without certificate of correction filled and scaffold not repaired. the ecb violation was re-written.
Mar 24, 2023 · Penalty $1,250
Resolve - Class - 1
Violation # 39508576n under complaint # 4906445 was issued on 11/01/2022 for no design drawings for platform. job site not in compliance, no drawings and no certificate of correction. the ecb violation was re-w
Mar 24, 2023 · Penalty $1,250
Resolve - Class - 1
Violation # 39508590j under complaint # 4906449 for inadequateunsafe vertical netting at 6th fl, missing toe-boards on multiple floors was not corrected or certificate of correction filled. the ecb violation wa
Mar 24, 2023 · Penalty $2,500
Resolve
Show 27 more ↓
- Class - 1
Unsafe job site with pswo in place. inadequate guard rail system, netting and housekeeping.
Mar 24, 2023 · Penalty $2,500
Resolve - Class - 2
At time of inspection for a 6 story new building i observed no compliance from respondent in regard to previously issued violation 39508574j issued on 11-1-22 no certificate of correction was submitted to the d
Jan 13, 2023 · Penalty $1,250
Resolve - Class - 2
At time of inspection for a 6 story new building i observed no compliance from respondent in regard to previously issued violation 39508590j issued on 11-1-22 no certificate of correction was submitted to the d
Jan 13, 2023 · Penalty $1,250
Resolve - Class - 2
At time of inspection for a 6 story new building i observed no compliance from respondent in regard to previously issued violation 39508576n issued on 11-1-22 no certificate of correction was submitted to the
Jan 13, 2023 · Penalty $1,250
Resolve - Class - 2
Observed sidewalk shed (sws) at exp#1 and supported scaffolds at exp#1,3- no approved design drawings for the supp scaff + sws, along with the sws daily inspection log and supp scaff pre-shift log were provided
Nov 1, 2022 · Penalty $3,125
Resolve - Class - 1
Observed 6th flr vertical netting cables at the interior stair opening leading edge and the exp#1,3 leading edges were only approx. 30-35" high, the cables were severely loosened, and at least one post was seve
Nov 1, 2022 · Penalty $12,500
Resolve - Class - 1
Observed temporary platforms in elevator shaft at all floors- built contrary to pe-approved dd- no wood ledger, wood planks/joist not extended 8'-1/4" past shaft opening, some planks/joists placed diagonally. a
Nov 1, 2022 · Penalty $6,250
Resolve - Class - 1
Observed supported scaffold at exp#1,3 with the following conditions: missing guard rails/toe-boards on working platforms; missing pins on outriggers; loose and dislodged planks; loose netting; damaged and bent
Nov 1, 2022 · Penalty $6,250
Resolve - Class - 1
At the time of inspection 6 stories nb i observed 2 workers on 3rd fl removing part of concrete slab deck and welding structural steel post support steel beam above floor as structural members as per approved
Jul 6, 2022 · Penalty $2,500
Resolve - Class - 2
Observed inadequate logs no actual orientations for all workers, superintendent time in/out, pre shift meeting, and tools box. 5 workers on 3rd fl deck working on cmu, veneer blocks on edge without fall arrest
Jul 6, 2022 · Penalty $5,000
Resolve - Class - 1
At the time of inspection 6 stories new building about 7 workers i request site safety orientations to be provided on site the competent person provide piece of paper has signing all workers without any subject
Jul 6, 2022 · Penalty $625
Resolve - Class - 2
At the time of inspection 6 stories new building i observed temporary platform at elevator shift i requested dd from competent person he provide inadequate dd without pe stamp no work at elevator shift provide
Jul 6, 2022 · Penalty $1,280
Resolve - Class - 1
Observed 5 workers on 4th fl deck working on cmu, and veneer brick installation on the edges of the slab without any fall arrest system harness to be tied off to any structural members.2workers on 3rd fl deck r
Jul 6, 2022 · Penalty $2,500
Resolve - Class - 2
At the time of inspection 6 stories new building i observed supported scaffold at exp#1,3 has unsafe platform not tied down and missing guard rails and toe board, missing some location netting no exterior work
Jul 6, 2022 · Penalty $1,280
Resolve - Class - 2
At the time of inspection 6 stories new building i observed construction fence at exp#1,# under permit #q00293427 expired on 01/07/2022, supported scaffold at exp#1,3 unsafe under permit #q00314359 expired on 0
Jul 6, 2022 · Penalty $1,280
Resolve - Class - 2
Temporary equipment onsite(sws)expired permit.observed sidewalk shed still up at exp1.temporary construction equipment requires a permit at all times to remain installed.permit in dob now#q00273633-i1-sh expire
May 5, 2022
Resolve - Class - 2
Pedestrian protection does not meet code specifications. note:at time of my inspection observed sidewalk shed installed on pedestrian walkway and are not maintain as required. the sws under light was not on at
Nov 5, 2020 · Penalty $5,000
Resolve - Class - 2
Housekeeping.at the time of inspection of an active 6 story building construction site i observed of construction materials.debris scatteredall over the site.materials,debris,tools laying on floors blocking egr
Mar 5, 2020 · Penalty $1,250
Resolve - Class - 2
Project information panel/sidewalk shed parapet panel/construction sign not provided or not in compliance w/section. at time of inspection @an active new bldg construction job site,i observed there was no const
Feb 15, 2020
Resolve - Class - 2
Bc3301.7/failure to provide pre approved detail drawings.as noted at time of inspection on a active construction site,floor #4 metal deck placemen work.observed exposure #2,#4 stairwell steel panel staircase an
Jan 30, 2020 · Penalty $1,250
Resolve - Class - 2
Work does not conform to approved construction documents and or approved amendments.as noted:at time of inspection an active construction site observed at floor 4 metal deck placement work @ exposure #1 floor 2
Jan 30, 2020
Resolve - Class - 2
Failure to safeguard all persons or property affected by construction operations.as noted:at time of inspection at an active construction site metal deck work on the floor #4.observe at exposure#2,front and rea
Jan 30, 2020 · Penalty $5,000
Resolve - Class - 1
3307.7.7 condition of fence @the time of inspection @a 4sty nb i observed a poorly maintained const fence. panels from the fence had fallen off into the garden of the adjoining property, there was protecting
Dec 12, 2019 · Penalty $2,500
Resolve - Class - 1
3307.2.1 obstruction of street or sidewalk @the time of inspection @4sty nb i observed materials tied together with caution tape in the street @exp1.these large materials were obstructing the street & could be
Dec 12, 2019 · Penalty $625
Resolve - Class - 2
Bc 3301.7 failure to provide pe approved design drawing as noted @timeof my inspection. active site, foundation lvl i observed temporary structure {bridge} @expo#1 made of wooden platform posts. no pe approved
Oct 2, 2019
Resolve - Class - 2
Work does not conform to approved construction documents and/are amendments, as noted @time of my inspection, active site, foundation phase i observed some solider piles were spaced(7-8) feet center to center
Oct 2, 2019
Resolve - Class - 2
Work does not conform to approved construction documents and/or amendments. as noted at time of my inspection observed excavation been done,w/ soe not conforming to the drawing. missing a section about 10'-0-12
Sep 12, 2019
Resolve
Complaints
No HPD complaints in our records
Sales history
No recorded sales in our data
Building details
- Building type
- Walk-up apartment building (C1)
- Year built
- 2019
- Floors
- 6
- Residential units
- 10
- Building area
- 11,726 ft²
- Lot area
- 3,000 ft²
- Zoning
- R6
- Community board
- 406
- Council district
- 29
- Block / lot
- 2265 / 103
- Assessed value
- $831,600
- Landmark / historic district
- No
Questions about 75-42 Grand Central Pkwy
Who owns 75-42 Grand Central Pkwy?
The owner of record in NYC Department of City Planning PLUTO data is Gc 42 LLC.
Does 75-42 Grand Central Pkwy have violations?
NYC HPD has no housing violations on record for this property.
Is 75-42 Grand Central Pkwy rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 75-42 Grand Central Pkwy built?
City records list 2019 as the year it was built.
How many apartments are in 75-42 Grand Central Pkwy?
It has 10 residential units.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.