90-12 Whitney Avenue is an elevator apartment building built in 2020 in Queens, 11373. It has 10 residential units across 6 floors. The owner of record is 9012 Whitney INC.. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
3
ECB violations
29
HPD complaints
0

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 3

  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Apr 28, 2021

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Apr 28, 2021

    Dob violation - dismissed
  • Unsafe buildings none

    Ub-unsafe buildings none

    Mar 25, 1997

    Dob violation - dismissed

ECB violations · 29

  • Class - 2

    A six-story new building, observed part of the construction fence at exp#1 &4, reviewing the dob now and bis it is noticed that the construction fence permit q00284556 expired on 10/18/2022

    Jan 4, 2023

    Resolve
  • Class - 2

    At the time of inspection observed a part of the construction fence at the corner of exp#1 & exp#4 adjacent to the sidewalk, creating a hazard for the people. as only part of the fence is remained at the site,

    Jan 4, 2023

    Resolve
  • Class - 1

    At the time of inspection i observed, there was no handrails was provided on permanent staircase from 1st floor up to roof level, which was creating a hazardous condition on jobsite.

    Aug 6, 2022 · Penalty $2,500

    Resolve
  • Class - 1

    Unlawfully continued work while on notice of a stop work order.as noted at time of inspection on an active construction site,observed at exp1,2,3,4 floor 1 to bulkhead cmu block masonry exterior wall with facad

    Apr 7, 2022 · Penalty $5,000

    Resolve
  • Class - 2

    Work without a permit(new building permit expired)as noted at time of inspection on an active construction site,observed new building permithas expired on 4/2/2022.permit#421609361-01-nb.observed the gate door

    Apr 7, 2022 · Penalty $3,125

    Resolve
  • Class - 2

    3314.8.2 failure to maintain debris netting as per code.at the time ofinspection,this was a 6 story residential building.construction site was closeed.as per perimeter inspection,i observed debris netting was n

    Oct 19, 2021

    Resolve
  • Class - 2

    Work does not conform to approved construction documents and/or approved amendments. as noted: at time of inspection on an active construction, 6 story concrete cast-in-place building masonry cmu block placemen

    Sep 24, 2021 · Penalty $1,250

    Resolve
  • Class - 2

    3303.7.2 inadequate fire extinguishers.noted at time of inspection at an active jobsite,observed fire extinguishers on 1st and 4th floor missing yearly inspection tags and placed on the floor.and at 2nd floor f

    Aug 24, 2021 · Penalty $620

    Resolve
  • Class - 2

    Failure to maintain embeded safety straps installation inspection log book on site.as noted:at time of inspection on active construction site of a 6 story concrete cast-in-place building,i observed concrete imb

    Apr 30, 2021 · Penalty $1,250

    Resolve
  • Class - 2

    Expired construction fence permit at the time of inspection i observeda construction fence in place at expo#1.upon further inspection of dobnow and bis i saw that the construction fence permit expired on 12-21-

    Mar 30, 2021

    Resolve
Show 19 more ↓
  • Class - 2

    Jobsite fence not constructed or maintained pursuant to subsection.at the time of inspection i observed a construction fence onsite.all construction fences are to be maintained in proper condition which include

    Mar 30, 2021

    Resolve
  • Class - 1

    Bc 3307.4.7 work on storage zone. note-at the time of my inspection ofa 6 story new building. i observed dumpster container on the street adjacent to sidewalk shed and not enclosed w/ a fence,a solid barrier ex

    Mar 19, 2021 · Penalty $625

    Resolve
  • Class - 2

    Temporary construction equipment on site expired permit at the tim eof my inspection i observed upon researching bis and dob now that the construction fence on site had a permit that expired on 12-21-2020

    Feb 18, 2021 · Penalty $620

    Resolve
  • Class - 1

    3309.10 failure to protect adjoining properties during const or demo operation @time of insp on active 6stynb constsite notice@exp4 of constsite contractor failed to maintain/institute protection for property r

    Jan 29, 2021 · Penalty $1,250

    Resolve
  • Class - 1

    3303.11 failure to maintain adequate means of egress during const @time of insp on active 6stynb constsite notice@5fl stairs in or out were being obstructed by rebar >4'h,contractor failed to maintain adequate

    Jan 29, 2021 · Penalty $2,500

    Resolve
  • Class - 1

    No site specific formwork design drawings present per3301.7 @time of insp on active 6stynb const in framing of superstructure,when request was made for drawings for formwork&opening for temp stairs competent pe

    Jan 29, 2021 · Penalty $2,500

    Resolve
  • Class - 1

    Work doesn't conform to approved const docs &/or approved amendments.@time of insp on active 6stynb const site.notice that plans/drawings for sidewalk shed wasn't as per what contractor erected on site.plans ca

    Jan 29, 2021 · Penalty $2,500

    Resolve
  • Class - 1

    Failure to institute/maintain adequate guardrails onsite @time of inspon active 6stynb constsite notice@5flexp1&interior core on 5fl@stairs missing/inadequate guardrails.this is dangerous in that workers were f

    Jan 29, 2021 · Penalty $2,500

    Resolve
  • Class - 2

    Failure to obtain temporary construction equipment permit at time of inspection on a proposed 6 story new building currently at 2nd floor level observed a sidewalk shed in place a exposure#1.upon further resear

    Nov 25, 2020 · Penalty $1,280

    Resolve
  • Class - 2

    3309.14 window protection at time of inspection on a proposed 6 story nb currently pouring at 2nd leve observed at exp #2 & 4 missing windowprotection for occupied bldg at 1st & 2nd fl,currently the site pourin

    Nov 18, 2020

    Resolve
  • Class - 2

    Construction superintendent failed to do duties as per code at the time of a proposed 6 story nb inspection currently pouring 2nd fl observed the following violating conditions in which the site was issued a fu

    Nov 18, 2020 · Penalty $2,500

    Resolve
  • Class - 1

    Work doesnot conform to approved/accepted documents ssp at time on a proposed 6 story nb currently pouring 2nd fl level observed from work for 2nd fl extending over lat.line fence at exp.#4 above adjacent bld

    Nov 18, 2020 · Penalty $2,500

    Resolve
  • Class - 1

    Failure to provide pedestrian protection for sidewalks & walkway.at the time of inspection of a proposed 6 story nb i observed concrete pouring operation in progress,2nd floor deck was being powered observed

    Nov 18, 2020 · Penalty $10,000

    Resolve
  • Class - 1

    Bc3301.13.1 inadequate site safety plan at the time of inspection of a6 story nb currently pouring operation in progress.at exp #1 observed a concrete truck concrete pump & washout box in roadway w/the pump out

    Nov 18, 2020 · Penalty $2,500

    Resolve
  • Class - 1

    Bc3307.4 warnig signs barriers & signals at times of inspection on a proposed 6 story nb currently pouring 2nd fl level,observed concrete pouring operation in progress.at exp#1 observed a concrete truck concr

    Nov 18, 2020 · Penalty $2,500

    Resolve
  • Class - 1

    Bc1704.1.2 responsibility of the special inspection agency- independence at time of inspection on a proposed 6 story nb currently pouring 2nd fl level observed concrete pouring operations in progress & various

    Nov 18, 2020 · Penalty $2,500

    Resolve
  • Class - 1

    Permit holder failed to ensure that workers received site safety orientation.at the time of inspection of a 6 stroy nb currently pouring 2ndfl level.i observed more than 7 workers in the site performing pouring

    Nov 18, 2020 · Penalty $2,530

    Resolve
  • Class - 2

    Fence.note:at the time of my inspection of a demolition job site,i observed missing portions of construction fence at exposure 2(near)and exposure 3,creating a hazardous condition for non construction persons a

    Feb 11, 2020

    Resolve
  • Class - 2

    Failure to maintain building wall or appurtenanas. noted: vacant bldg & missing leader at front & 2 leader at rear terminated open onto yard & not connected to storm snub & maintain ex\system.

    Jul 30, 2014

    Resolve

Complaints

No HPD complaints in our records

Complaint data is still being backfilled from NYC Open Data.

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Elevator apartment building (D1)
Year built
2020
Floors
6
Residential units
10
Building area
16,192 ft²
Lot area
5,000 ft²
Zoning
R7B
Community board
404
Council district
25
Block / lot
1567 / 6
Assessed value
$1,161,450
Landmark / historic district
No

Questions about 90-12 Whitney Avenue

Who owns 90-12 Whitney Avenue?

The owner of record in NYC Department of City Planning PLUTO data is 9012 Whitney INC..

Does 90-12 Whitney Avenue have violations?

NYC HPD has no housing violations on record for this property.

Is 90-12 Whitney Avenue rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 90-12 Whitney Avenue built?

City records list 2020 as the year it was built.

How many apartments are in 90-12 Whitney Avenue?

It has 10 residential units.