Violations at 2616 Cropsey Avenue
Brooklyn, NY 11214 · BBL 3-06933-0051 · Back to the property
HPD housing violations
6 HPD violations, newest first.
- BHazardous
Properly repair with similar material the broken or defective acoustic tiles at ceiling at public hall, 2nd story
Aug 29, 2006
Open — Nov sent out - CImmediately hazardous
Remove the illegal fastening double cylinder key operated lock at building door in the entrance located at apt 2fl, 2nd story, 1st apartment from east at south
Aug 29, 2006 · Apt 2FL
Open — Nov sent out - BHazardous
Properly repair with similar material the broken or defective ceiling in the 2nd room from north located at apt 2fl, 2nd story, 1st apartment from east at south
Aug 29, 2006 · Apt 2FL
Open — Nov sent out - BHazardous
Abate the nuisance consisting of water leak at ceiling in the 2nd room from north located at apt 2fl, 2nd story, 1st apartment from east at south
Aug 29, 2006 · Apt 2FL
Open — Nov sent out - BHazardous
Repair the broken or defective plastered surfaces and paint in uniform color the south wall in the 1st room from north located at apt 2fl, 2nd story
Apr 28, 2006 · Apt 2FL
Open — Nov sent out - BHazardous
Repair the broken or defective plastered surfaces and paint in uniform color the ceiling and walls in the entire apartment located at apt 2fl, 2nd story
Apr 28, 2006 · Apt 2FL
Open — Nov sent out
DOB building violations
No DOB violations on record
ECB violations
18 ECB violations, newest first.
- Class - 2
Failure to safeguard the public and property affected by construction operations. at time of inspection observed at exposure 4(right) 3rd floor roof water runoff to adjacent property (2606 cropsey avenue) at ap
Sep 22, 2026 · Penalty $5,000
Active - Class - 2
Failure to maintain adequate housekeeping per section requirements. at time of inspection observed at exposure 4(right) 3rd floor roof puddling of water no drainage in place creating flooding hazardous conditio
Sep 22, 2026 · Penalty $1,250
Active - Class - 2
Observed construction work exceeding 75ft with erected steel, finished stair and elevator bulkheads at 93ft and 98ft without access to elevator/hoist contrary to code 3303.12.2.1, creating safety hazards for fi
May 13, 2026 · Penalty $2,500
Active - Class - 1
At time of inspection, observed inadequate guardrail system throughout working floor deck, creating fall hazard.
Nov 24, 2025
Resolve - Class - 1
At time of inspection observed strucural steel placement in progress contrary to approved ahv permit#b7506775.stop all after hors work conform and rsolve civil penalty associated with violationstop all ahv work
Sep 20, 2025 · Penalty $2,500
Resolve - Class - 1
At time of inspection and requested to review site safety plan for conformance and it should be noted that required hoisting equipment on site of spyder crane that was in use for structural steel placement and
Sep 20, 2025 · Penalty $2,500
Resolve - Class - 1
Atoi observed spyder cranes on site and in use. after review of all department's records there was no application on file for use of 2 spyder cranes being used for structural steel placement . stop all use of
Sep 20, 2025 · Penalty $2,500
Resolve - Class - 2
At time of inspection, i observed three trees without tree protection at exposure #1. contractor failed to protect trees as per bc 3309.11.
Feb 5, 2025 · Penalty $2,500
Resolve - Class - 2
At time of inspection, i observed the project information panel not posted to the sidewalk shed at exposure #1 & #2.
Feb 5, 2025 · Penalty $1,250
Resolve - Class - 2
At the time of inpsection of active job site. construction superintendent on site. upon request for site safety plan none was provided. pswo for failure to maintain/display site safey plan. stop all demo work a
Dec 28, 2023
Resolve - Class - 2
Ati i observed the construction fence under job b00920115-fn which expires 01-31-2024 is 8ft high & 280ft long installed around the perimeter of the property address listed above but has no viewing panels cut i
Nov 6, 2023 · Penalty $1,000
Resolve - Class - 3
Work does not conform to aprpoved construction documents or amendmentsjob #320696797/a2/dwg dated 12/24/12 noted: 1-1st floor rear existing window closed w/masonry (plan shown window operable);2-front exterior
Feb 26, 2013 · Penalty $100
Resolve - Non-hazardous
Work w/o a permit. work noted: erected sheetrock partitions @ one side of loft area forming approx. 7 rooms including a laundry room in the rear of dwelling. one of the rooms consists of water closet and sink,a
Apr 19, 2005 · Penalty $500
Resolve - Hazardous
Occupancy contrary to that allowed by certificate of occupancy. cerificate of occupancy issued on 6/9/64 #188274 which states 1st floor to be commercial and 2nd floor to be an office. presently 2nd fl is used a
Apr 19, 2005 · Penalty $800
Resolve - Hazardous
Plumbing work without a permit.in the cellar of grocery store saw gas line running from gas meter down and across ceiling to an open end pipe.pipe then tee off and went up to grocery store to a griddle.all pvc
Apr 19, 2005 · Penalty $800
Resolve - Hazardous
Exit door:total obstruction hazardous:exit door at 1st floor rear is blocked exterior roll down steel gate.remedy:remove obstruction.
Apr 14, 2005 · Penalty $480
Resolve - Hazardous
Failure to maintain building-hazardous.noted:1/2" vertical crack in east concrete foundation wall and cinderblock wall above from cellar to roof line.floor by refrigeration unit in deli sinking/caving in.remedy
Apr 14, 2005 · Penalty $800
Resolve - Non-hazardous
3a 44a 50 1983 fulton natl bd 42759 3a remove the floor with the pipe stuck in it. 50 pipe down the safety valve discharge to a safe point.
Dec 18, 2004 · Penalty $400
Resolve