2025 Kings Highway
Brooklyn, NY 11229BBL 3-06767-0047Map
Owner of record: 2025 Kh LLC
2025 Kings Highway is an office building built in 2009 in Brooklyn, 11229. The owner of record is 2025 Kh LLC. HPD has no housing violations on record for this property.
- HPD violations
- 0
- DOB violations
- 6
- ECB violations
- 11
- HPD complaints
- 0
What to know
No open immediately-hazardous violations among recent records.
HPD has not cited this building.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 0
No HPD violations on record
DOB building violations · 6
- Low pressure boiler boiler required
Violation issued-failure to file 2018 external low pressure inspection
Jun 20, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued-failure to file 2019 external low pressure inspection
Jun 20, 2023
Dob violation - active - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2017 inspection report
Jan 17, 2020
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2013 inspection report
Mar 3, 2015
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Dec 28, 2011
Dob violation - resolved - Construction other optional
Stop all work failure to provide approved plans on site at time of ins pection noted: at time of insp an active site pouring concrete foundat ion walls with a sheer cut approx 14 to 15 feet and no soe plans job # 310207175 remedy: stop all work provide plans call excavation unit for appointme
Mar 27, 2009
Dob violation - dismissed
ECB violations · 11
- Class - 2
Failure to safeguard all persons and property affected by constructionoperations "no smoking" signs w/i construction site not observed in violation of nyc fire code 1404 & fc 310. remedy: safeguard public &
Mar 27, 2009 · Penalty $6,000
Resolve - Class - 1
Sec. bc 3304.4;27-1032b. stop all work failure to provide 3'6" guard rail or solid enclosure around open and accessible sides of excavation.noted: at time of inspection, an active site w/a sheer cut approx 14'
Mar 27, 2009 · Penalty $8,000
Resolve - Class - 1
Sec. bc 3304.7;26-229(a). stop all work. failure to provide adequate means of exit from excavation. noted: at time of inspection an active site w/o a sheer cut approx 14' deep along exp 1,2 & 4 and new adequate
Mar 27, 2009 · Penalty $8,000
Resolve - Class - 1
Stop all work. failure to provide protection at side of excavation. noted: at time of inspection an active site, foundation walls (partial) along exp 1 & 2 w/a sheer cut approx. 14' deep along exp 1,2 & 4 & no
Mar 27, 2009 · Penalty $12,000
Resolve - Class - 1
Sec. bc 3309.2;27-1031. stop all work. failure to adequately support adjoining grounds affected by excavation. noted: at time of inspection an active site w/a sheer cut approx. 14' deep along exp 1 undermining
Mar 27, 2009 · Penalty $8,000
Resolve - Class - 1
Sec. bc 3307.7;27-1021. failure tto provide an adequate construction fence. inadequacies. noted: at time of inspection an active site foundation walls along exp 1 & 2 and a sheer cut approx. 14' deep and
Mar 27, 2009 · Penalty $8,000
Resolve - Class - 1
Sec. 33307.5.2. no flag person. noted: at time of inspection an activesite sidewalk closed w/concrete truck along exp 1 & 4 & no flagperson to take care of public & traffic. job #310207175. remedy: provide
Mar 27, 2009 · Penalty $8,000
Resolve - Class - 1
Failure to safeguard public and property effected by demo operations. noted:(bldg)is roof at above locations(portably)demolished. no work in progress. no overhead protection provided for adj. property(driveway)
Oct 21, 2008 · Penalty $2,400
Resolve - Class - 1
Failure to safeguard all person and property affected by construction operations observed 2 workers smoking w/in construction site near flammable and combustible material(s) in violation of nyc fire code 1404.1
Oct 8, 2008 · Penalty $2,400
Resolve - Class - 1
Sec bc3306.9.3 27-1039f dust producing operations shall be wetted down to the extent necessary to control the dust upon insp at the above address 2 stories demolition is in progress huge amount of combustible d
Oct 8, 2008 · Penalty $1,600
Resolve
Show 1 more ↓
- Class - 1
Failure to safeguard all person and property affected by demo operation. upon insp at the above address 2 stories bldg demo is in progress, huge amount of combustible debris is on site from roof and interior
Oct 8, 2008 · Penalty $2,400
Resolve
Complaints
No HPD complaints in our records
Sales history
No recorded sales in our data
Building details
- Building type
- Office building (O7)
- Year built
- 2009
- Floors
- 2
- Residential units
- —
- Building area
- 7,029 ft²
- Lot area
- 3,080 ft²
- Zoning
- R7A
- Community board
- 314
- Council district
- 48
- Block / lot
- 6767 / 47
- Assessed value
- $598,950
- Landmark / historic district
- No
Questions about 2025 Kings Highway
Who owns 2025 Kings Highway?
The owner of record in NYC Department of City Planning PLUTO data is 2025 Kh LLC.
Does 2025 Kings Highway have violations?
NYC HPD has no housing violations on record for this property.
Is 2025 Kings Highway rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 2025 Kings Highway built?
City records list 2009 as the year it was built.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.