roofy

434 Blake Avenue

Brooklyn, NY 11212BBL 3-03780-0021Map

Owner of record: 434 Blake LLC

434 Blake Avenue is an elevator apartment building built in 2025 in Brooklyn, 11212. It has 9 residential units across 5 floors. The owner of record is 434 Blake LLC. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
0
ECB violations
29
HPD complaints
0

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 0

No DOB violations on record

ECB violations · 29

  • Class - 2

    Inadequate site safety plan as per 28-105.12.8 all work shall adhere to ssp/scope of work-site safety plan doesn't show/specify means and methods for protection of adj property as required-stop all work 10 fee

    Mar 2, 2026

    Resolve
  • Class - 2

    At the time of my inspection of active 5 story new building i observed only 2 fire extinguishers on site with one dial showed empty and 2nd one tag showed service in 2024 (as per tag fire ext. is expired after

    Mar 2, 2026 · Penalty $625

    Resolve
  • Class - 2

    At the time of my inspection i observed supported scaffold installed at exp #2 (for masonry work/stucco) above adj property roof and front yard -no protection for roof/front yard/building entrance provided for

    Mar 2, 2026 · Penalty $5,000

    Resolve
  • Class - 2

    At the time of my inspection i observed supported scaffold installed at exp#1/2 and in elevator pit - sidewalk shed at exp#1/4-uppon asking competent person for supported scaffold drawings, installation letter

    Mar 2, 2026 · Penalty $1,250

    Resolve
  • Class - 2

    At the time of my inspection observed sidewalk shed installed at exp#1/4 -big amount of garbage/material/equipment , mortar/dirt all over shed roof , braces from post to post installed 7' high(shall be 8'),loos

    Mar 2, 2026 · Penalty $2,400

    Active
  • Class - 2

    At the time of my inspection of 5 story new building i observed big amounts of garbage/material/equipment scattered all over the floors on all floors and on the exterior of building(crating tripping/fire hazard

    Mar 2, 2026 · Penalty $1,250

    Active
  • Class - 1

    At the time of my inspection of active 5 story new building i observed no handrails provided on all floors from 1st to roofin stairway(1st floor handrail provided in 1 of stairway)

    Mar 2, 2026 · Penalty $2,500

    Resolve
  • Class - 2

    At the time of my inspection observed construction fence installed at exp#1/4 not maintained-multiple location added plywood over old plywood not painted hunter green, multiple broken plywood's ,holes in fence

    Mar 2, 2026 · Penalty $1,000

    Active
  • Class - 2

    Respondent fail to comply with the commissioner order, violating condition was not corrected. no certificate of correction was file with department. comply with the commissioner order, file certification of cor

    Oct 8, 2025 · Penalty $1,250

    Resolve
  • Class - 2

    Respondent fail to comply with the commissioner order, violating condition was not corrected. no certificate of correction was file with department. comply with the commissioner order, file certification of cor

    Oct 8, 2025 · Penalty $1,250

    Resolve
Show 19 more ↓
  • Class - 2

    Respondent fail to comply with the commissioner order, violating condition was not corrected. no certificate of correction was file with department. comply with the commissioner order, file certification of cor

    Oct 8, 2025

    Resolve
  • Class - 1

    At the time of my inspection of a 5 story new building, i observed active jobsite steel framing up to the 4 floor, upon request for 2 workers site safety orientation and refresher none was provided or at jobsit

    Aug 8, 2025

    Resolve
  • Class - 1

    At the time of my inspection of a 5 story new building, i observed active jobsite steel framing up to the 4 floor, upon request for the approved steel framing plans none was provided or at jobsite, failure to p

    Aug 8, 2025 · Penalty $2,500

    Resolve
  • Class - 1

    At the time of my inspection, i observed telehandler on street at exposure #1 with no 4 feet solid plywood barrier from ground level, no 18 gauge wire mesh on top and no barrier around. failure to provide adequ

    Aug 8, 2025 · Penalty $5,000

    Resolve
  • Class - 1

    At the time of my inspection of a 5 story new building, i observed active steel framing up to the 4 floor, supported pipe scaffold approximately 44 feet in height, upon review of the department records it revea

    Aug 8, 2025 · Penalty $1,250

    Resolve
  • Class - 1

    Bc 3307.6.5.4 at the time of my inspection of a 5 story new building, i observed sidewalk shed at exposure #1 and 4 with lots of building materials and parts of pipe scaffold stored at various places, this cre

    Aug 8, 2025 · Penalty $5,000

    Resolve
  • Class - 2

    At the time of my inspection of a sidewalk shed provided to protect members of the public i observed there were no underside lighting provided to protect the safety of members of the public and pedestrians usin

    Aug 1, 2025 · Penalty $2,400

    Resolve
  • Class - 2

    At time of my inspection observed: sidewalk she installed at expo# 1 vertical components placed on green infrastructure, contrary to bc 3307.6.4.10, bc 3307.9, bc 3307.10, ac28-103.8, 15 rcny 19-01creating a n

    Jul 8, 2025 · Penalty $10,000

    Active
  • Class - 2

    At time of inspection observed: proposed 5 story new building cmu work at 3rd fl. level steel column erected at 50 feet height. missing netting between fence and sidewalk shed at expo# 1-4 contrary to bc 3307.2

    Jul 8, 2025 · Penalty $2,400

    Active
  • Class - 2

    At time of inspection observed: proposed 5 story new building cmu work at 3rd fl. level steel column erected at 50 feet height. inadequate housekeeping at throughout job site. creating unsafe condition for publ

    Jul 8, 2025 · Penalty $1,250

    Active
  • Class - 2

    Bc 3303.4.8 machinery. mechanical equipment at storage zone does not barricade, shielded to prevent contact by public. at time of inspection observed: unattended telehandler at exposure# 1 missing enclosure, cr

    Jul 8, 2025 · Penalty $2,500

    Active
  • Class - 2

    At time of inspection observed: proposed 5 story new building cmu work at 3rd fl. level steel column erected at 50 feet height. supported scaffold unsafe at 3rd floor level missing safety components guardrails,

    Jul 8, 2025 · Penalty $2,500

    Active
  • Class - 2

    At time of inspection observed: proposed 5 story new building cmu work at 3rd fl. level steel column erected at 50 feet height. missing over head protection at expo# 1 at main entrance between sidewalk shed and

    Jul 8, 2025 · Penalty $2,500

    Resolve
  • Class - 2

    Atoi observed foundation work in process 70% poured requested approved plans arch/en not provided., maintain/display required documents; maintain approved plans on site.https://www1.nyc.gov/site/buildings/codes

    Dec 17, 2024 · Penalty $1,250

    Resolve
  • Class - 2

    Job site fnce nt const/mntnd pursnt to sbsction: atoi, the entire run of const fnce has collapsed into the lot at exp-4. a 8'ft portion has collapsed at exp-1 partially onto the public sidewlk with nails/screws

    Feb 6, 2023 · Penalty $1,000

    Resolve
  • Class - 2

    Temporary construction equipment on site-expired permit: at time of inspection 122' linear ft of poorly maintained construction fence was observed installed at exps-1 & 4 at said place of occurrence. dob fence

    Feb 6, 2023 · Penalty $1,250

    Resolve
  • Class - 2

    Job site fence not constructed or maintained pursuant to subsection.note: fence is not constructed securly some plywood is warped in and some are warped out no 2x4 to support structure ,also no view panel cut

    Jan 11, 2018 · Penalty $400

    Resolve
  • Class - 2

    Job site fence not constructed subsection. at the time of inspection it was observed that the 8 feet plywood/metal fence collapse is the vacant lot leaving the ground lot open to the public. remedy: repair &/or

    Feb 15, 2017 · Penalty $400

    Resolve
  • Hazardous

    Failure to maintain. defect is: 1) interior floor slab collapsed thru-out 1st fl. 2) masonry wall @ interior collapsed out of level approx. 6". remedy: vacate premises, make safe, make all necessary repairs.

    Mar 19, 1999 · Penalty $2,500

    Active

Complaints

No HPD complaints in our records

Complaint data is still being backfilled from NYC Open Data.

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Elevator apartment building (D1)
Year built
2025
Floors
5
Residential units
9
Building area
11,625 ft²
Lot area
3,000 ft²
Zoning
R6
Community board
316
Council district
42
Block / lot
3780 / 21
Assessed value
$93,600
Landmark / historic district
No

Questions about 434 Blake Avenue

Who owns 434 Blake Avenue?

The owner of record in NYC Department of City Planning PLUTO data is 434 Blake LLC.

Does 434 Blake Avenue have violations?

NYC HPD has no housing violations on record for this property.

Is 434 Blake Avenue rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 434 Blake Avenue built?

City records list 2025 as the year it was built.

How many apartments are in 434 Blake Avenue?

It has 9 residential units.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.