roofy

482 Thomas S Boyland

Brooklyn, NY 11212BBL 3-03518-0046Map

Owner of record: Thomboy Facilities LLC

482 Thomas S Boyland is a vacant lot in Brooklyn, 11212. The owner of record is Thomboy Facilities LLC. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
0
ECB violations
13
HPD complaints
0

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 0

No DOB violations on record

ECB violations · 13

  • Class - 1

    Bc 3303.3 watch person. 6-story nb structure stage 12065 sq. ft. approx. site closed and there was no construction activity. upon shouting at perimeter and banging on fence to alert watchperson and to verify co

    Mar 14, 2026 · Penalty $5,000

    Resolve
  • Class - 2

    Bc 3307.2.1 at time of inspection observed: construction equipment in place using sidewalk and roadway. upon reviewing department record it appears; dot permit has not yet been issued, for occupancy of sidewalk

    Mar 14, 2026 · Penalty $2,500

    Resolve
  • Class - 1

    At the time of my inspection of a 6 story new building, i observed 2 workers using threading machine one on the 1st and 2nd floor, they were not anchoring to the floor. failure to anchor threading machine accor

    Mar 9, 2026 · Penalty $2,500

    Resolve
  • Class - 1

    Bc 2113.1.6.1 at the time of my inspection of a 6 story new building at roof level, i observed chimney of adjacent building at exposure #4 which was not extended to the height of the taller new building. failur

    Mar 9, 2026

    Resolve
  • Class - 2

    At the time of my inspection observed active site @ 4th floor level enclosed with tarp and multiple diesel fuel portable heaters scattered throughout the floor without any escape hatches installed. the site fai

    Feb 26, 2026 · Penalty $2,500

    Resolve
  • Class - 2

    At the time of my inspection observed active site failed to provide upon request certificate of fitness for use of diesel fuel portable heaters scattered throughout the floor on 4th floor level with enclosed wi

    Feb 26, 2026 · Penalty $2,500

    Resolve
  • Class - 2

    Bc 3303.3 at the time of my inspection of a 6 story new building, site closed, construction fence doors and gates were locked, after shouting at the perimeter and knocking on the construction fence to alert the

    Feb 8, 2026 · Penalty $2,500

    Resolve
  • Class - 1

    At the time of my inspection of a 6 story new building at foundation and excavation phase, i observed demolition at exposure #4 of old foundation walls beside adjacent building. upon request for demolition perm

    Nov 10, 2025

    Resolve
  • Class - 1

    At the time of my inspection of a 6 story new building at foundation and excavation phase, i observed concrete foundation for cellar with rakers supporting the walls. upon review of the approved foundation and

    Nov 10, 2025 · Penalty $625

    Resolve
  • Class - 1

    At the time of my inspection of a 6 story new building at foundation/excavation phase, i observed yodak barriers on street with 2 lanes dividing the street for traffic, upon review of the dot permit 5 feet pede

    Nov 10, 2025 · Penalty $1,250

    Resolve
Show 3 more ↓
  • Class - 1

    At the time of my inspection of a 6 story new building at foundation and excavation phase, i observed active jobsite, upon request for the construction superintendent 62 hours site safety card none was provided

    Nov 10, 2025 · Penalty $2,500

    Resolve
  • Class - 1

    At the time of my inspection of a 6 story new building, i observed demolition at exposure #4 of old foundation walls beside adjacent building. upon review of the approved foundation/excavation plan it was not r

    Nov 10, 2025 · Penalty $625

    Resolve
  • Class - 2

    Observed jersey barriers at exp#1 not as per manufactures specification. jersey barriers not fill with water/sand and not continuous interlocked which poses a potential hazard by allowing unintended movement

    Sep 13, 2025 · Penalty $1,250

    Resolve

Complaints

No HPD complaints in our records

Complaint data is still being backfilled from NYC Open Data.

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Vacant lot (V0)
Year built
—
Floors
—
Residential units
—
Building area
—
Lot area
19,673 ft²
Zoning
R6
Community board
316
Council district
41
Block / lot
3518 / 46
Assessed value
$96,900
Landmark / historic district
No

Questions about 482 Thomas S Boyland

Who owns 482 Thomas S Boyland?

The owner of record in NYC Department of City Planning PLUTO data is Thomboy Facilities LLC.

Does 482 Thomas S Boyland have violations?

NYC HPD has no housing violations on record for this property.

Is 482 Thomas S Boyland rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.