13 Stanhope Street
Brooklyn, NY 11221BBL 3-03253-0037Map
Owner of record: 13 Stanhope LLC
13 Stanhope Street is a walk-up apartment building built in 1901 in Brooklyn, 11221. It has 5 residential units across 4 floors. The owner of record is 13 Stanhope LLC. HPD has recorded 11 housing violations here, most recently on August 3, 2026. 2 of the 11 most recent violations are still open.
- HPD violations
- 11
- DOB violations
- 8
- ECB violations
- 24
- HPD complaints
- 2
What to know
Immediately hazardous issues among recent violations are still open.
Date of the most recent HPD inspection that found a problem.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 11
- CImmediately hazardous
Replace or repair the self-closing doors that is missing or defective latch in the entrance located at apt 1, 1st story, 1st apartment from south at west
Aug 3, 2026 · Apt 1
Open — Nov sent out - CImmediately hazardous
Remove the illegal double cylinder key operated locking device at door . in the entrance located at apt 1, 1st story, 1st apartment from west at north
Jun 17, 2024 · Apt 1
Open — Not complied with - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Nov 28, 2023
Closed — Violation dismissed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Nov 17, 2022
Closed — Violation dismissed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Jan 10, 2018
Closed — Violation dismissed - BHazardous
Repair by closing so as to be gas tight all openings in the wast line under kitchen sink in the bathroom located at apt 2-r, 2nd story
Jan 31, 2000 · Apt 2-R
Closed — Violation closed - BHazardous
Repair by closing so as to be gas tight all openings in the waste line under kitchen sink in the kitchen located at apt 2-r, 599th story
Jan 31, 2000 · Apt 2-R
Closed — Violation closed - BHazardous
Abate the nuisance consisting of vermin mice and roaches in the kitchen located at apt 2-r, 2nd story
Jan 31, 2000 · Apt 2-R
Closed — Violation closed - BHazardous
Properly repair with similar material the broken or defective ceramic tile floor in the bathroom located at apt 2-r, 2nd story
Jan 31, 2000 · Apt 2-R
Closed — Violation closed - BHazardous
Repair the broken or defective plastered surfaces and paint in a uniform color walls and ceiling in the 1st entire apartment from east located at apt 2-r, 2nd story
Jan 31, 2000 · Apt 2-R
Closed — Violation closed
Show 1 more ↓
- BHazardous
Properly repair the broken or defective upper and lower window sashesthroughout in the 1st entire apartment from east located at apt 2-r, 2nd story
Jan 31, 2000 · Apt 2-R
Closed — Violation closed
DOB building violations · 8
- Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Feb 16, 2022
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Feb 16, 2022
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Sep 2, 2020
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Sep 2, 2020
Dob violation - dismissed - Construction other optional
C-construction other optional
Jun 20, 2019
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
May 16, 2019
Dob violation - dismissed - Construction other optional
C-construction other optional
Aug 8, 2006
Vw*-violation - work w/o permit dismissed - Construction other optional
Work without a permit. work noted: having constructed partition wall subdividing 2nd floor apartment creating 2 apartments remedy: obtain a permit if feasible or restore premises to prior legal condition
Feb 3, 2000
Vw*-violation - work w/o permit dismissed
ECB violations · 24
- Class - 2
Construction sign not provied-sidewalk shed. at the time of my inspection of a closed site,i observed a sidewalk shed installed at exp#1 under permit#b00103609 which was missing project information construction
Feb 17, 2022 · Penalty $3,125
Resolve - Class - 2
Jobsite fence not constructed or maintained pursuant to subsection. atthe time of my inspection of a closed site,i observed a construction fence erected at exp#1 under permit#b00043546 that was covered w/grafit
Feb 17, 2022 · Penalty $2,500
Resolve - Class - 1
Work does not conform with site safety plan.note:at time of inspection of 4 story building construction work in progress observed stell framing and cmu work in progress review of site safety plan and demo seque
Nov 18, 2021
Resolve - Class - 1
Bc3301.2 failure to maintain egress.note:at time of inspection of 4 story building construction work in progress observed means of egress not maintained throughout building from 1st floor to 3rd floor creating
Nov 18, 2021
Resolve - Class - 2
Construction fence not maintained as per code. at time of inspection observed construction fence at exp #4 not maintained not painted green.this condition violates bc 3307.7. all construction fences must be mai
Sep 14, 2021
Resolve - Class - 2
Failure to comply with the commissioners order contained in summons/violation #35334055p issued on 02-19-2019 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01.b110:failure to protec
Dec 7, 2019
Resolve - Class - 2
Failure to comply w/the comm's order contained in summons/vio#35334055p issued on 02-19-19 & to file a c of c pursuant to 28-201.1 & 1rcny 102-01. failure to provide protection at sides of excavation @ cellar
Oct 25, 2019
Resolve - Class - 1
The respondent design applicant failed to meet the requirements of bc1604.4 & have a complete load path.bc1604.4 mandates that structural analysis results in a system that provides a complete load path that is
Oct 23, 2019 · Penalty $2,500
Resolve - Class - 1
Bc1604.2the respondent design applicant failed to meet the requirements of bc1604.2 & submitted a design w/beam sizes that could not supportthe design loads.job #320910332 doc 2 was filed far structural support
Oct 23, 2019
Resolve - Class - 2
Failure to comply w/the comm's order contained in summons/vio#35334055p issued on 02-19-19 & to file a c of c pursuant to 28-201.1 & 1rcny 102-01. bc3304.4 & 27-1032 failure to provide protection at side of exc
Sep 10, 2019
Resolve
Show 14 more ↓
- Class - 2
Sec. 107.7.1 the respondent filed drawings w/the dob under job#320910332 that failed to meet the minimum requirement set(forth)in ac 28-101.2 professional eugineer failed to show the levels of footings of adjac
Feb 19, 2019
Resolve - Class - 1
Failure to protect the sides of excavation;noted:job#320910332.at cellar level,excavation of cellar floor approx 15'wide x 20'long and 6'in depth,adjacent foundations of attached buildings approx 3'from foundat
Feb 19, 2019
Resolve - Class - 1
Work does not conform to approved construction documents & or approvedamendments. note: at the time of my inspection of a 2 sty bldg being alter to 4 sty construction work in progress. i observed that exp#2 par
Dec 19, 2018 · Penalty $2,500
Resolve - Class - 2
Failure to institute & maintain safety equipment measures & temporary construction. note: at the time of my inspection of a 2 sty bldg being alter to 4 sty construction work in progress. i observed that there
Dec 19, 2018 · Penalty $5,000
Resolve - Class - 2
Sec. 3301.13.13 log. note: at the time of my inspection of a 2 sty being alter to 4 sty construction work in progress. upon request for construction superindent logs as require to verty preset at site & complia
Dec 19, 2018 · Penalty $625
Resolve - Class - 1
Construction superintendent failed to perform duties per code. the following hazardous conditions were observed & partial stop work order was issued to this construction site on this date. 1)not present at site
Dec 19, 2018 · Penalty $10,000
Resolve - Class - 1
Sec. 3301.13.12 competent person. note: at the time of my inspection of a 2 sty bldg being alter to 4 sty construction work in progress. upon for construction superintendent none was provided & upon request for
Dec 19, 2018 · Penalty $2,500
Resolve - Class - 1
Sec. 3307.4.7 work & storage zone. note: at the time of my inspection of a 2 sty bldg being alter to 4 sty construction work in progress. i observed a 30 cuboc yard dumpster being stored & use at exp#1 in roadw
Dec 19, 2018 · Penalty $2,500
Resolve - Class - 1
Sec. 3306.5.1 required documents. note: at the time of my inspection of a 2 sty bldg being alter to 4 sty construction work in progress. i observed rear wall at exp#3,1st fl level was completely removed(demo)&
Dec 19, 2018 · Penalty $2,500
Resolve - Non-hazardous
Failure to comply w/ the commissioners order to correct the violating condition & file a cert of correction w/ the nyc dob for notice of vioaltion #34216042m issued on 2/3/00. remedy:correct the vio condition
Aug 8, 2006
Resolve - Non-hazardous
Failure to comply w/ the commissioners order to correct the violating condition & file a cert of correction w/ the nyc dob for notice of violation #34216041k issued on 2/3/00.remedy:correct the vio condition
Aug 8, 2006
Resolve - Non-hazardous
Failure to maintain building defect is : 1- kitchen ceiling broken loose buldging down ,window balance broken locks missing window loose andinoperative. 2- defective kitchen cabinet and waste line under sink al
Feb 3, 2000 · Penalty $180
Resolve - Non-hazardous
Residence altered for occupancy as a dwelling for more than the legally approved # of families.bldg. dept. records which indicate residence legally approved for 2 families residence now altered for occupancy by
Feb 3, 2000 · Penalty $3,050
Resolve - Non-hazardous
Work without a permit . work noted: having constructed partition walls subdividing 2nd floor apartment creating 2 apartments. remedy: obtain a permit if feasible or restore premises to prior legal condition
Feb 3, 2000 · Penalty $500
Resolve
Complaints
- Unsanitary condition
Mold
Jun 11, 2024 · Apt 1
Close - Nonconst
Illegal
Jun 13, 2003 · Apt BSMT
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Walk-up apartment building (C2)
- Year built
- 1901
- Floors
- 4
- Residential units
- 5
- Building area
- 4,573 ft²
- Lot area
- 2,000 ft²
- Zoning
- R6
- Community board
- 304
- Council district
- 34
- Block / lot
- 3253 / 37
- Assessed value
- $548,550
- Landmark / historic district
- No
HPD registration #392089, last renewed Jul 24, 2026.
Questions about 13 Stanhope Street
Who owns 13 Stanhope Street?
The owner of record in NYC Department of City Planning PLUTO data is 13 Stanhope LLC.
Does 13 Stanhope Street have violations?
Yes. NYC HPD has recorded 11 housing violations at this property.
Is 13 Stanhope Street rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 13 Stanhope Street built?
City records list 1901 as the year it was built.
How many apartments are in 13 Stanhope Street?
It has 5 residential units.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.