29 Locust Street is a mixed residential and retail building built in 1910 in Brooklyn, 11206. It has 2 residential units across 3 floors. The owner of record is 29 Locust Street LLC. HPD has recorded 6 housing violations here, most recently on March 27, 2010. 6 of the 6 most recent violations are still open.
- HPD violations
- 6
- DOB violations
- 23
- ECB violations
- 18
- HPD complaints
- 2
What to know
Immediately hazardous issues among recent violations are still open.
Date of the most recent HPD inspection that found a problem.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 6
- BHazardous
Abate the nuisance consisting of bedbugs in the entire apartment located at apt 3, 3rd story
Mar 27, 2010 · Apt 3
Open — Nov sent out - BHazardous
Properly secure the loose balustrade , at public hall, 2nd story
Mar 27, 2010
Open — Nov sent out - CImmediately hazardous
Replace with new the missing balusters 2nd story at public hall stairs
Mar 27, 2010
Open — Nov sent out - BHazardous
Abate the nuisance consisting of bedbugs in the entire apartment located at apt 3, 3rd story, 1st apartment from west at north
Feb 8, 2010 · Apt 3
Open — Nov sent out - BHazardous
Provide an approved and operational carbon monoxide detecting device, installed in accordance with applicable law and rules. in the entire apartment located at apt 3, 3rd story, 1st apartment from west at north
Feb 8, 2010 · Apt 3
Open — Nov sent out - BHazardous
Remove all encumbrances consisting of constuction materials at public hall, 1st story
Feb 8, 2010
Open — Nov sent out
DOB building violations · 23
- Low pressure boiler boiler required
Violation issued-failure to file 2024 external low pressure inspection
Nov 14, 2025
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2023 external low pressure inspection
Sep 23, 2024
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2020 external low pressure inspection
Jun 30, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2021 external low pressure inspection
Jun 30, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2018 external low pressure inspection
Jun 20, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2019 external low pressure inspection
Jun 20, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2022 external low pressure inspection
Apr 25, 2023
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2017 inspection report
Nov 8, 2019
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2016 inspection report
Apr 6, 2018
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2015 inspection report
Feb 24, 2017
Dob violation - dismissed
Show 13 more ↓
- Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2014 inspection report
Oct 1, 2015
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2013 inspection report
Mar 3, 2015
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2012 inspection report
May 15, 2014
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2011 inspection report
Mar 1, 2013
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2010 inspection report
Dec 13, 2011
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jan 13, 2011
Dob violation - dismissed - Low pressure boiler boiler required
Lblvio-low pressure boiler boiler required
Dec 31, 2009
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Jan 1, 2009
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Jan 6, 2006
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Jan 31, 2005
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
May 4, 1998
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Jul 25, 1994
Dob violation - dismissed - Plumbing none
P-plumbing none
Oct 4, 1989
Dob violation - dismissed
ECB violations · 18
- Class - 2
Following objections: i observed wood beam supporting wood joist and not showing in approved drawings page a00300 at 1st floor level.
Jul 28, 2022
Resolve - Class - 2
Access was denied into job siteprovide access into job site to conduct routine inspection
Jul 15, 2022 · Penalty $1,250
Resolve - Class - 3
Contractor did not give dept 72 hour notice.; bc3303.10.2, comply with code; comply with notice of violation
Aug 28, 2019
Resolve - Class - 2
Failure pf permit holder to provide inspection access to &/or expose ongoing construction or work on active & permitted worksite. at time ofinspection,worker at 2nd fl window had dust mask & hard hat on & hand
Jun 27, 2019 · Penalty $1,250
Resolve - Class - 2
As per class 2 (b265) 28-303.7 failure to file a complete boiler in spection report as per dob records. submit a current b09 report.
Apr 24, 2017 · Penalty $500
Resolve - Class - 1
Failure to comply w/ the comm order contained in nov#34087431z issued on 6/9/11 work w/o a work permit rem: comply / the comms order
Jul 30, 2011
Resolve - Class - 1
Failure to comply w/comm's order to correct vio #34087431z for work w/o permit. remedy: comply w/comm's order & obtain permit.
Jun 9, 2011 · Penalty $6,000
Resolve - Class - 1
Failure to comply w/the commissioner's order to obtain a permit per nov #34687491z,issued 8-14-08 for work w/o permit - 1fl offices. remedy:comply w/code.
Apr 6, 2011 · Penalty $12,500
Resolve - Class - 1
Failure to correct condition(s0 cited in nov 3468491z for constructionplumbing work done w/o a permit. remedy: correct condition(s) cited
Feb 10, 2011
Resolve - Class - 1
Failure to comply w/comm's order to correct vio #3468491z for work w/o permit. no record of correction. remedy: comply w/comm's order & obtain permit.
Oct 18, 2010
Resolve
Show 8 more ↓
- Class - 1
Fail to correct conditions cited to correct conditions cited in nov 34687491z for work done w.o a permit. remedy: correct conditions cited in 34687491z.
Jun 3, 2010 · Penalty $24,000
Resolve - Class - 1
Failure to correct ecb#346874912 for illegal work on 1st floor no record of correction with d o b, remedy-obtain permit.
Jan 6, 2010
Resolve - Class - 2
Failure to file a certificate for nov#34804880m pursant 28-204.2 remedy file certificate.
Jan 6, 2010
Resolve - Class - 1
Failure to comply w/ comms order to correct vio#34687491z for work w/o permit a 1st fl illegal toilets plumbing & partitions no record of correction rem: comply w/ comms order & obtain permit
Aug 27, 2009 · Penalty $2,400
Resolve - Class - 2
Failure to comply w/commissioner order to file cert of correction for vio#34687491z rem: file cert of correction
Aug 27, 2009 · Penalty $400
Resolve - Class - 1
Sec. 28-201.1. failure to comply w/comm's order to correct vio #34687491z for work w/o permit @ 1st fl installed partitions for 2 offices toilets w/o permit. no record of correction. remedy: comply w/comm's
Mar 12, 2009
Resolve - Class - 1
Work w/o a permit. work noted: partitions have been constructed in the1st floor creating 2 offices 1 storage & 2 toilets. remedy: obtain permit or restore to prior legal condition.
Aug 14, 2008 · Penalty $1,600
Resolve - Class - 3
Occupancy contrary to that allowed by the c of o legal occupancy in the 1st fl per co 141603 is tailor shop now changed to church remedy: discontinue illegal use or amend c of o
Aug 14, 2008 · Penalty $500
Resolve
Complaints
- Nonconst
Vermin
Mar 21, 2010 · Apt 3
Close - Nonconst
Vermin
Jan 27, 2010 · Apt 3
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Mixed residential and retail building (S2)
- Year built
- 1910
- Floors
- 3
- Residential units
- 2
- Building area
- 5,300 ft²
- Lot area
- 2,500 ft²
- Zoning
- M1-1
- Community board
- 304
- Council district
- 34
- Block / lot
- 3134 / 36
- Assessed value
- $124,980
- Landmark / historic district
- No
Questions about 29 Locust Street
Who owns 29 Locust Street?
The owner of record in NYC Department of City Planning PLUTO data is 29 Locust Street LLC.
Does 29 Locust Street have violations?
Yes. NYC HPD has recorded 6 housing violations at this property.
Is 29 Locust Street rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 29 Locust Street built?
City records list 1910 as the year it was built.
How many apartments are in 29 Locust Street?
It has 2 residential units and 3 units in total.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.