150 North 12 Street is an elevator apartment building built in 2017 in Brooklyn, 11249. It has 51 residential units across 7 floors. The owner of record is Elrob Realty LLC. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
7
ECB violations
25
HPD complaints
1

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 7

  • Failure to submit eer none

    Failure to submit an eer per ad. code sec. 28-308.4 in 2020

    Jun 20, 2021

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jan 22, 2020

    Dob violation - resolved
  • Failure to benchmark none

    Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4

    Feb 16, 2019

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Mar 8, 2017

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Dec 6, 2016

    Vp*-violation unserved ecb- dismissed
  • Construction other optional

    C-construction other optional

    Jan 28, 2009

    Dob violation - dismissed
  • Construction other optional

    Failure to provide approved plans at time of inspection 302256412 oper ations of shoring ongoing at exp 2x4 w/out shoring plan remedy: stop work provide plans to this dept

    Jun 18, 2008

    Dob violation - dismissed

ECB violations · 25

  • Class - 1

    Failure to maintain exterior building facade and appurtenances. at thetime of my inspection observed crack/losse bricl at exp #4 north elevation on 3rd floor. remedy: maintain exterior facade take safety measur

    Oct 28, 2025 · Penalty $5,000

    Resolve
  • Class - 2

    Top landing is an illegal vestibule. conform to 2.11.6.5.

    Feb 18, 2025 · Penalty $312

    Resolve
  • Class - 1

    Failure to submit the required parking structure initial observation report for an existing parking structure or a periodic inspection of a parking structure(pips) report documenting the conditions of psid#b000

    Oct 1, 2024 · Penalty $625

    Resolve
  • Class - 2

    Work does not conform to approved construction documents and/or approved amendments.premises under alt2 job #320950217.loc folder.at time ofinspection found plan shows powder room at cellar.found no powder room

    Oct 10, 2018 · Penalty $1,250

    Resolve
  • Class - 1

    Fall protection. failure to safeguard. at 6th fl observed worker on balcony w/no fall protection worker was not wearing harness(lanyard)retractable or tied of to any secure point stop all work w/i 10'-0: of bal

    Jun 20, 2017 · Penalty $10,000

    Resolve
  • Class - 1

    Sec. 3301.7 design drawing. at time of inspection observed motorized hoisting system attached to scaffold at 7th fl being used to bring stone up to roof level when i asked for design drawing for this equipment

    Jun 20, 2017 · Penalty $1,600

    Resolve
  • Class - 1

    Guardrails. at new bldg under construction & up to 7th fl observed at all levels at perimeter of bldg no guardrails at balconettes & at fullheight openings. many balcony doors had no glass & doors w/glass were

    Jun 20, 2017 · Penalty $1,200

    Resolve
  • Class - 1

    Housekeeping. at 5th fl observed debris piled consisting of sheetrock,wood,insulation & garbage bags,at 2nd fl consisting of pallets,insulation,plywood,buckets,rope & brick at 7th fl balcony observed insulation

    Jun 20, 2017 · Penalty $2,400

    Resolve
  • Class - 2

    Fence. at time of inspection of active construction site observed job site fence painted 3 different shades of green & 2 4-0 panels not painted "hunter green" as required. remedy: maintain fence per code.

    Jun 20, 2017 · Penalty $400

    Resolve
  • Class - 1

    Toe boards. at new bldg under construction & upto 7th fl observed at all levels that no toe boards were installed at elevator starts from 1st fl to 7th fl creating a condition where materials,debris or public

    Jun 20, 2017 · Penalty $1,000

    Resolve
Show 15 more ↓
  • Class - 1

    Failure to safeguard all persons & property affected by construction operations. note: at the time of my inspection of a 7 sty bldg at roof level,construction work in progress. i observed that there were no ove

    Dec 6, 2016

    Resolve
  • Class - 1

    Sec. 3309.10 protection of roofs. note: at the time of my inspection of a 7 sty bldg at roof level,construction work in progress. i observed that there were no roof protection provided for adjacent property @

    Dec 6, 2016

    Resolve
  • Class - 1

    Sec. 3314.3.3 drawings. note: at the time of my inspection of a 7 sty bldg at roof level,construciton work in progress. i observed an electrical hoisting equipment installed on supported pipe scaffold at exp#3

    Dec 6, 2016

    Resolve
  • Class - 1

    Construction superintendent fail to perform duties as per rule. the following hazardous conditions were observed & stop work order was issued to this construction site on this date. no overhead protection for

    Dec 6, 2016

    Resolve
  • Class - 1

    Sec. 3314.4.3.3 installation inspection for supported. note: at the time of my inspection of a 7 sty bldg at roof level,construction work inprogress. i observed supported pipe scaffold erected & being use at

    Dec 6, 2016

    Resolve
  • Class - 2

    Sec. 3307.6.3 sidewalk shed does not meet code specifications. noted: at the time of my inspection of a 7 sty bldg at roof level,construction work in progress. i observed that sidewalk shed at exp#4 was not

    Dec 6, 2016

    Resolve
  • Class - 1

    Failure to institute/maintain safety equipment measures or temporary construction-no guardrails. note: at the time of my inspection of a 7 sty bldg at roof level,construction work in progress. i observed multip

    Dec 6, 2016

    Resolve
  • Class - 2

    Bc28-116.2.3 failure to provide an adequate inspection program tr1 special inspection tr3 design mix tr2 concrete testing lab.as noted @ time of inspection @ an active construction site no tr1 tr2 tr3 filed w/

    May 13, 2015

    Resolve
  • Class - 1

    3307.2.1 temp.walkways.note:@ time of my insp.of a 7 strory new bldg @ cellar level,i observed temp.walkway @ exp.one made of plastic jersey barriers were not adequately maintain they where shifting towards bot

    Apr 18, 2015 · Penalty $400

    Resolve
  • Class - 2

    Failure to project project information panel sidewalk shed panel/construction sign. noted under permit renewal nb/fn#30256412 dated 7-30-13,no project information sign has been posted.noting work in progress an

    Sep 25, 2013

    Resolve
  • Class - 2

    Jobsite fence not constructed pursuant to subsection noted part of construction fence open outwardly appx 10" blocking walk way for pedestrians and making construction site accesible no construction in progress

    Aug 9, 2012

    Resolve
  • Class - 1

    (misc)bc3304.8open foundation not afequately drained of water &/or surfaces water,note:there is excessive stagnet standing water approx 50'x50'and two ft deep @ bottom of open excavation which is potential dang

    Mar 7, 2011

    Resolve
  • Class - 2

    Work w/o permit. expired permit. permit for construction fence at openfoundation site expired on 2/4/09. note: permit #302256412fn. remedy: renew permit for fence.

    Jun 9, 2009 · Penalty $800

    Resolve
  • Class - 2

    Job site fence not constructed pursuant to subsection. noted jobsite fence erected under app 302256412-01-eq-fn exp 2/4/09 found with the missing required 8' high sections a various locations, missing proper

    Jan 28, 2009

    Resolve
  • Class - 1

    Failure to provide protection at side of excavation noted work on going under permit #30256412 excavation parallel to n 12st approx 30ft into jobsite is approx 13ft deep w/ an angle of repose steeper than 30 de

    Oct 9, 2008 · Penalty $2,400

    Resolve

Complaints

  • Heat/hot water

    Apartment only

    Jan 25, 2026 · Apt 2D

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Elevator apartment building (D3)
Year built
2017
Floors
7
Residential units
51
Building area
53,612 ft²
Lot area
12,860 ft²
Zoning
M1-2/R6A
Community board
301
Council district
33
Block / lot
2290 / 5
Assessed value
$10,899,450
Landmark / historic district
No

HPD registration #389201, last renewed Jul 14, 2026.

Questions about 150 North 12 Street

Who owns 150 North 12 Street?

The owner of record in NYC Department of City Planning PLUTO data is Elrob Realty LLC.

Does 150 North 12 Street have violations?

NYC HPD has no housing violations on record for this property.

Is 150 North 12 Street rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 150 North 12 Street built?

City records list 2017 as the year it was built.

How many apartments are in 150 North 12 Street?

It has 51 residential units.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.