537 Gates Avenue is a condominium built in 2006 in Brooklyn, 11216. It has 18 residential units across 3 floors. The owner of record is Unavailable Owner. HPD has recorded 15 housing violations here, most recently on March 9, 2022. 2 of the 15 most recent violations are still open.

HPD violations
15
DOB violations
1
ECB violations
37
HPD complaints
7

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
Last violation Mar 9, 2022

Date of the most recent HPD inspection that found a problem.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 15

  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Mar 9, 2022

    Closed — Violation dismissed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Mar 9, 2022

    Closed — Violation dismissed
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Mar 9, 2022

    Closed — Violation dismissed
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Mar 9, 2022

    Closed — Violation dismissed
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Mar 9, 2022

    Closed — Violation dismissed
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Mar 9, 2022

    Closed — Violation dismissed
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Apr 19, 2021

    Closed — Violation dismissed
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Apr 19, 2021

    Closed — Violation dismissed
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Apr 19, 2021

    Closed — Violation dismissed
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Apr 19, 2021

    Closed — Violation dismissed
Show 5 more ↓
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Apr 19, 2021

    Closed — Violation dismissed
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Apr 19, 2021

    Closed — Violation dismissed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Mar 4, 2015

    Closed — Violation dismissed
  • B

    Trace and repair the source and abate the nuisance consisting of mold ... at all walls ,aprx .40 square feet at basement

    Oct 2, 2013

    Open — Nov sent out
  • A

    Trace and repair the source and abate the nuisance consisting of mold ... at storage closet provided for apt # 2 (approx 4 sq.ft.) at basement

    Jul 28, 2013

    Open — Nov sent out

DOB building violations · 1

  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Aug 10, 2011

    Dob violation - active

ECB violations · 37

  • Class - 1

    Work w/o permit.work noted:i observed in bsmnt area from 3 flr gas meter 3/4 gas line ran 10 to 12 ft terminated using 3/4 gas valve which is 12' from location of existing electric dryers.rem:obtain permit or r

    May 17, 2011 · Penalty $1,600

    Active
  • Hazardous

    Openings holes not covered. note at front 1st fl, grade level opening approx 4'x 6'x 8' not covered. remedy: cover all holes & openings.

    Feb 28, 2007 · Penalty $1,250

    Resolve
  • Hazardous

    Openings/ holes not covered. note: at 1st fl level at rear openings & holes (at grade) level) still not covered. remedy: cover all openings & holes.

    Feb 28, 2007 · Penalty $1,250

    Resolve
  • Hazardous

    Openings/ holes not covered at ground fl front opening approx 4'x 6'x 8 not covered. remedy: cover all openings & holes.

    Feb 28, 2007 · Penalty $5,000

    Resolve
  • Hazardous

    Openings/ holes not covered. noted: openings at ground level fl rear, not covered. creating hazardous conditions. remedy: cover all holes & openings.

    Feb 28, 2007 · Penalty $5,000

    Resolve
  • Hazardous

    Openings holes not covered- at rear at ground fl level openings & holes not covered. remedy: cover all holes & openings.

    Feb 28, 2007 · Penalty $1,250

    Resolve
  • Hazardous

    Openings/ holes not covered. at front of bldg @ 1st fl opening to cellar approx 4'x 6'x 8' not covered. photo. remedy: cover openings.

    Feb 28, 2007 · Penalty $5,000

    Resolve
  • Hazardous

    Openings/ holes not covered. note: at rear of bldg hole approx 5x 5x 4in center of yd not covered. remedy: cover all holes & openings.

    Feb 28, 2007 · Penalty $1,250

    Resolve
  • Hazardous

    Openings/ holes not covered. note: 4x 6'x 8' opening at front to cellar has no protection. photo. remedy: cover all holes & openings.

    Feb 28, 2007 · Penalty $500

    Resolve
  • Hazardous

    Openings holes not covered. at rear of bldg. at 1st fl (grade) level uncovered holes/ openings are hazardous. remedy: cover all holes & openings.

    Feb 28, 2007 · Penalty $1,250

    Resolve
Show 27 more ↓
  • Hazardous

    Openings/ holes not covered: at front 1st fl level an opening approx 4'x 6'x 8 is not covered. remedy: cover all openings.

    Feb 28, 2007 · Penalty $1,250

    Resolve
  • Hazardous

    Failure to maintain adequate housekeeping-note:more than 30 cu yds of construction debris dumped all over rear of property no containers.remedy:maintain adequate housekeeping.

    Feb 28, 2007 · Penalty $500

    Resolve
  • Hazardous

    No guard rails:hazardous.noted:no guard rails installed @ front side of 2nd & 3rd flr level during construc.activities are in progress.remedy:stop all works & provide guard rails where required & make site safe

    Oct 17, 2006 · Penalty $500

    Resolve
  • Hazardous

    Opening/holes not covered.hazardous.noted:open holes @ rear of bldg a pproximately 25'foot long by 4'foot wide by 10'foot deep leading to cellar.remedy: stop all work!!

    Oct 17, 2006 · Penalty $500

    Resolve
  • Hazardous

    Opening/holes not covered.hazardous.noted:open holes @ rear of bldg approximately 25'foot long by 4'foot wide by 10'foot deep leading to cellar area.remedy:stop all work!except to cover hole & make site safe.

    Oct 17, 2006 · Penalty $500

    Resolve
  • Hazardous

    Opening/holes not covered.hazardous.noted:open holes @ rear of bldg approximately 25'ft long x 4'ft wide x 10'ft deep leading to cellar area.remedy:stop all work except to cover holes&make site safe.contact dob

    Oct 17, 2006 · Penalty $5,000

    Resolve
  • Hazardous

    Opening/holes not covered.hazardous.noted:open holes @ rear of bldg approximately 25'long x 4'ft wide x 10'ft deep leading to cellar area.remedy:stop all work!except to cover holes & make site safe.contact dob

    Oct 17, 2006 · Penalty $5,000

    Resolve
  • Hazardous

    Opening/holes not covered.hazardous.noted:open holes @ rear of bldg.approximately 25'foot long by 4'foot wide by 10'foot deep @ leading to cellar area.remedy:stop all work!except to cover holes & make site safe

    Oct 17, 2006 · Penalty $500

    Resolve
  • Hazardous

    No guard rails:hazardous.noted:no guard rails installed @ front side of 2nd & 3rd flr level during construction activities are in progress. remedy:stop all work except to provide guard rails wehre required.

    Oct 17, 2006 · Penalty $5,000

    Resolve
  • Hazardous

    No guard rails:hazardous.noted:no guard rails installed @ front side of 2nd & 3rd flr level during construction activities are in progress.remedy:stop all works except to provide guard rails where required.

    Oct 17, 2006 · Penalty $5,000

    Resolve
  • Hazardous

    No guard rails:hazardous.noted:no guard rails installed @ front side of 2nd & 3rd flr level during construction activities are in progress.remedy:stop all works except to provide guard rails where required.

    Oct 17, 2006 · Penalty $5,000

    Resolve
  • Hazardous

    No guard rails:hazardous.noted:no guard rails installed @ front side of 2nd & 3rd flr level during construction activities are in progress. remedy:stop all work except to provide guard rails where required.

    Oct 17, 2006 · Penalty $500

    Resolve
  • Hazardous

    No guard rails:hazardous.noted:no guard rails installed @ front side of 2nd & 3rd flr level during construction activities are in progress.remedy:stop all works except to provide guard rails where required.

    Oct 17, 2006 · Penalty $500

    Resolve
  • Hazardous

    Failure to provide 8ft high fence where required during excavation operations.noted:no 8'ft high fence erect@west side of construc.site @rear to protect&prevent access from adjacent property.remedy:stop all wrk

    Oct 17, 2006 · Penalty $480

    Resolve
  • Hazardous

    Opening/holes not covered.hazardous.noted:open holes @ rear of bldg approximately 25'ft long x 4'ft wide x 10'ft deep leading to cellar arearemedy:stop all work!except tp cover holes &make site safe.contact dob

    Oct 17, 2006 · Penalty $500

    Resolve
  • Hazardous

    No guardrails. noted:no guard rails installed at front & rear of 2nd & 3rd level during construction activities in progress. remedy:provide guard rails.

    Oct 6, 2006 · Penalty $5,000

    Resolve
  • Hazardous

    Opening/holes not covered. noted:opening hole of approx 4' x 6' in front side of bldg at 1st fl level during construction activities.remedy:cover holes or provide guard rails.

    Oct 4, 2006 · Penalty $500

    Resolve
  • Hazardous

    Opening/holes not covered.noted:opening/hole of approx 4' x 6' in front side of bldg at 1st fl level during construction activities. remedy:cover holes or provide guard rails.

    Oct 4, 2006 · Penalty $5,000

    Resolve
  • Hazardous

    Opening/holes not covered. noted:opening/hole of approx 4' x 6' feet in front side of bldg at 1st fl level during construction activities. remedy:cover holes or provide guardrails.

    Oct 4, 2006 · Penalty $500

    Resolve
  • Hazardous

    Opening/holes not covered. noted:opening/hole of approx 4' x 6' in front side of bldg at 1st fl level during construction activities . remedy:cover holes or provide guardrails.

    Oct 4, 2006 · Penalty $500

    Resolve
  • Hazardous

    Opening/holes not covered.noted:opening hole of approx 4' x 6' in front side & approx 5' x 5' at middle section of bldg at 1st fl level of bldg during construction activities. remedy:cover holes or provide

    Oct 4, 2006 · Penalty $500

    Resolve
  • Hazardous

    Opening/holes not covered. noted:opening/hole of approx 4' x 6' in front side of bldg at 1st fl level during construction activities. remedy:cover holes or provide guard rails.

    Oct 4, 2006 · Penalty $500

    Resolve
  • Hazardous

    No guard rails. noted:no guard rails installed at front side & rear side of second & third fl level during construction activities is in progress. remedy:provide guard rails.

    Oct 4, 2006 · Penalty $500

    Resolve
  • Hazardous

    No guard rails. noted:no guard rails installed at front & rear side of second & third fl level during construction activities in progress. remedy:provide guard rails.

    Oct 4, 2006 · Penalty $500

    Resolve
  • Hazardous

    No guard rails.noted:no guard rails installed at front & rear side of 2nd & 3rd fl level during construction activities in progress. remedy:provide guard rails.

    Oct 4, 2006 · Penalty $500

    Resolve
  • Hazardous

    No guard rails. noted:no guard rails installed at front & rear side of 2nd & 3rd fl level during construction activities in progress. remedy:provide guard rails.

    Oct 4, 2006 · Penalty $5,000

    Resolve
  • Hazardous

    No guard rails. noted:no guard rails installed at front & rear of second & 3rd fl level during construction activities in progress. remedy:provide guard rails.

    Oct 4, 2006 · Penalty $500

    Resolve

Complaints

  • Paint/plaster

    Ceiling

    Feb 9, 2026 · Apt 2

    Close
  • Plumbing

    Toilet

    Aug 1, 2021 · Apt B

    Close
  • Heat/hot water

    Apartment only

    Feb 2, 2019 · Apt 3

    Close
  • Heat/hot water

    Apartment only

    Feb 14, 2016 · Apt 2

    Close
  • General

    Mold

    Sep 27, 2013 · Apt 2

    Close
  • Plumbing

    Sewer

    Sep 27, 2013 · Apt 2

    Close
  • General

    Mold

    Jul 18, 2013 · Apt BSMNT

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Condominium (R3)
Year built
2006
Floors
3
Residential units
18
Building area
16,052 ft²
Lot area
1,800 ft²
Zoning
R6A
Community board
303
Council district
36
Block / lot
1809 / 7501
Assessed value
$627,478
Landmark / historic district
No

HPD registration #382418, last renewed Oct 24, 2025.

Questions about 537 Gates Avenue

Who owns 537 Gates Avenue?

The owner of record in NYC Department of City Planning PLUTO data is Unavailable Owner.

Does 537 Gates Avenue have violations?

Yes. NYC HPD has recorded 15 housing violations at this property.

Is 537 Gates Avenue rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 537 Gates Avenue built?

City records list 2006 as the year it was built.

How many apartments are in 537 Gates Avenue?

It has 18 residential units.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.