roofy

692 Myrtle Avenue

Brooklyn, NY 11205BBL 3-01750-0024Map

Owner of record: 144 Spencer Realty Corp

692 Myrtle Avenue is an elevator apartment building built in 1937 in Brooklyn, 11205. It has 92 residential units across 6 floors. The owner of record is 144 Spencer Realty Corp. HPD has recorded 1 housing violation here, most recently on March 20, 2021. 1 of the 1 most recent violations are still open.

HPD violations
1
DOB violations
95
ECB violations
57
HPD complaints
1

What to know

Concern
1 open Class C

Immediately hazardous issues among recent violations are still open.

Good
Last violation Mar 20, 2021

Date of the most recent HPD inspection that found a problem.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 1

  • C

    Trace and repair the source and abate the visible mold condition... at west wall aprox +/-55 sq feet aprox in the 2nd room from east located at apt 313, 3rd story, 2nd apartment from south at west , section at west

    Mar 20, 2021 · Apt 313

    Open — Notice of issuance sent to tenant

DOB building violations · 95

  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Aug 2, 2023

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued-failure to file 2018 external hgh pressure inspection

    Jun 20, 2023

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued-failure to file 2018 internal hgh pressure inspection

    Jun 20, 2023

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued-failure to file 2019 external hgh pressure inspection

    Jun 20, 2023

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued-failure to file 2019 internal hgh pressure inspection

    Jun 20, 2023

    Dob violation - dismissed
  • Failure to benchmark none

    Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4

    Aug 2, 2022

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Oct 7, 2021

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Oct 7, 2021

    Dob violation - resolved
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jul 21, 2021

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Nov 11, 2020

    Dob violation - dismissed
Show 40 more ↓
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Sep 30, 2020

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Sep 9, 2020

    Dob violation - resolved
  • High pressure boiler boiler required

    Violation issued - failure to file 2017 internal high pressure boiler inspection

    Mar 16, 2020

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued - failure to file 2017 internal high pressure boiler inspection

    Mar 16, 2020

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued - failure to file 2017 internal high pressure boiler inspection

    Mar 16, 2020

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued - failure to file 2017 external high pressure boiler inspection

    Mar 16, 2020

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued - failure to file 2017 external high pressure boiler inspection

    Mar 16, 2020

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued - failure to file 2017 external high pressure boiler inspection

    Mar 16, 2020

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 11, 2019

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Aug 29, 2019

    Dob violation - resolved
  • Failure to benchmark none

    Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4

    May 3, 2019

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Mar 6, 2019

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jul 20, 2017

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jul 20, 2017

    Dob violation - resolved
  • Elevator affirmation of correction elevatorrequired

    Vio issued to elevator - fail to correct defects on 2014 cat 1 insp/tst

    Nov 14, 2016

    Dob violation - dismissed
  • Elevator affirmation of correction elevatorrequired

    Vio issued to elevator - fail to correct defects on 2014 cat 1 insp/tst

    Nov 14, 2016

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Sep 23, 2016

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Aug 10, 2016

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Aug 10, 2016

    Dob violation - resolved
  • Residential elevator periodic inspection/test elevatorrequired

    Failure to perform category 5 inspection

    Jun 1, 2016

    Dob violation - dismissed
  • Residential elevator periodic inspection/test elevatorrequired

    Failure to perform category 5 inspection

    Jun 1, 2016

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 6, 2015

    Dob violation - resolved
  • High pressure boiler boiler required

    Violation issued for failure to file 2013 annual high pressure boiler inspection

    Mar 3, 2015

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued for failure to file 2013 annual high pressure boiler inspection

    Mar 3, 2015

    Dob violation - dismissed
  • High pressure boiler boiler required

    Violation issued for failure to file 2013 annual high pressure boiler inspection

    Mar 3, 2015

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 7, 2014

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 7, 2014

    Dob violation - resolved
  • Failure to benchmark none

    Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4

    May 1, 2014

    Dob violation - dismissed
  • Elevator annual inspection / test elevatorrequired

    Violation issued to elevator-failure to file category 1 2012 inspection/test

    Mar 31, 2014

    Dob violation - dismissed
  • Elevator annual inspection / test elevatorrequired

    Violation issued to elevator-failure to file category 1 2012 inspection/test

    Mar 31, 2014

    Dob violation - dismissed
  • No report and / or late filing (facade) facade required

    Failed to file fisp cycle 7b technical report by 08/21/2012

    Aug 30, 2013

    Dob violation - active
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Apr 3, 2013

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Apr 3, 2013

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 15, 2012

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 15, 2012

    Dob violation - resolved
  • Failure to benchmark none

    Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4

    May 3, 2012

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 6, 2011

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 6, 2011

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 12, 2010

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    May 12, 2010

    Dob violation - resolved

ECB violations · 57

  • Class - 2

    Observed installation of exterior storefront work, including a projecting sign, facade band signage, and a fixed metal awning/soffit system, all installed without required dob permits or approved plans. work is

    Dec 1, 2025 · Penalty $1,250

    Active
  • Class - 2

    Atoi of occupied multiple dwelling jobsite observed open drywall, debris, excessive dust, material in common area corridors & elevator bank of occupied floors. observed failure to comply with active tpp stating

    Aug 29, 2024

    Resolve
  • Class - 2

    Missing in case of fire sign in basement. replace worn gibs where needed. secure gibs where needed. defective car phone (wrong contractor ). clean tiller rope for proper inspection. adjsut hoistway door access

    Mar 5, 2024

    Resolve
  • Class - 1

    Failure to maintain building in code compliant manner.noted:at the time of inspection observed cracked/damaged/spalled and defective concrete masonry stucco and bricks at all exposures at several locations,also

    Feb 1, 2023

    Resolve
  • Class - 1

    Work without a permit.noted:at time of inspection,observation was madeinside of her commercial space/warehouse new renovation consisting of a new partition walls.new electrical install of bx cable wire outlets.

    Apr 27, 2021

    Resolve
  • Class - 1

    I observed in public corridors and hallways of entire building gas piping still existing and not removed as per certificate of correction issued to dob stating it was removed, comply with code

    Aug 12, 2020

    Resolve
  • Class - 1

    In supermarket commercial cooking equipment removed. multiple gas pipes do not have equipment connected. no permit on file to remove commercial cooking equipment, obtain permit

    Jul 7, 2020 · Penalty $1,250

    Resolve
  • Class - 1

    Failure to maintain; prohibited materials i observed throughout building residential gas flex connectors installed on commercial gas dryers and flexible gas vents on several gas dryers. prohibited gas fittings

    Feb 20, 2020

    Resolve
  • Class - 1

    Failure to maintain; prohibited location i observed throughout building in hallways and public corridors gas piping installed. the gas piping is threaded and not welded which is prohibited and not code complian

    Feb 20, 2020

    Resolve
  • Class - 2

    Burnham gas steam boiler 175,000btu in 6th floor boiler room is not registered-the safety discharge pipe is missing-the steam control is missing wire cover-manual reset pressure control is missing-remote contro

    Feb 20, 2020 · Penalty $312

    Resolve
Show 40 more ↓
  • Class - 1

    I observed in sprinkler control room in cellar an infrared gas fired heater with gas piping. no permits on file therefore no proper testing was performed on gas line as per dob, perform test

    Feb 20, 2020

    Resolve
  • Class - 1

    Cease use.. hazardous.. hanging gas hot air heater in cellar that is not vented to the outdoors, maintain boiler; and correct all hazardous conditions immediately and call dob 212 3932784 to lift the cease use

    Feb 20, 2020 · Penalty $1,250

    Resolve
  • Class - 1

    I observed in sprinkler control room in cellar a gas fired infrared wall hung heater installed and no permits on file for heater in cellar, obtain permit

    Feb 20, 2020

    Resolve
  • Class - 1

    I observed in sprinkler room in cellar an infrared gas fired heater with no permits on file therefore no proper inspections and/or certification as per dob for gas usage, file for required permits and have nece

    Feb 20, 2020

    Resolve
  • Class - 1

    Cease use 59x10-repair brake monitoring switches.

    Aug 16, 2019 · Penalty $1,250

    Resolve
  • Class - 2

    Failure to maintain building walls or appurtenances. observed on exterior walls at exposure 2 and 4 the stucco cracked and will fall down the lintel on 4th floor stucco cracked will fall down. paint on facade w

    Mar 14, 2019 · Penalty $1,250

    Resolve
  • Class - 1

    An unlawful act. failure to comply with an order of the commissioner. failure to correct and certify summons#39000978z, for work without a permit, issued on 12/17/18. remedy: comply with ec code/obtain permit

    Feb 20, 2019

    Resolve
  • Class - 2

    Failure to comply w/ commissioner's order contained in summons/violation#35329448j issued on 4/11/18,and to file a certificate of correctionpursuant to 28.201.1 and 1rcny 102-01(d)(2). an acceptable certificate

    Feb 14, 2019 · Penalty $1,250

    Resolve
  • Class - 1

    Work without permit, obtain permit

    Dec 17, 2018

    Resolve
  • Class - 2

    Failure to maintain bldg walls or appurtenances. observed exp#1 brick masonry w/substantial cracks from warehouse door openings in approx 5 locations. remedy: maintain exterior bldg wall obtain engineers report

    Aug 21, 2018 · Penalty $3,125

    Resolve
  • Class - 2

    Failure to comply with the commissioners order contained in summons/violation #35328913l issued on 04/16/18 and to file a certificate of correction pursuant to 28-201.1 and 1rcny 102-01.rem:comply with commissi

    Jun 8, 2018

    Resolve
  • Class - 2

    Electrical work without a permit.mc cable and awning removed from above entrance doors of property.no electrical application on file.also noted:installations of wall park light with photo sensor to the right of

    Jun 8, 2018 · Penalty $400

    Resolve
  • Class - 3

    Erect illuminated awning approx 8ft wide x 3ft overhang x 3ft high reading "superior matenance supply" w/o a permit. remedy: comply w/notice of violation.

    Apr 16, 2018 · Penalty $250

    Resolve
  • Class - 1

    Failure to maintain building in code compliant manner.noted:approx 2ftof unsanthed electrical bx cable in open-top awning exposed to the elements.rem:comply with notice of violation

    Apr 16, 2018

    Resolve
  • Class - 2

    Work w/o a permit. work noted: front facade 1st fl erected marquee size approx 8-3" width metal frame anchored into brick wall supporting 3'x10' glass plate awning projecting 3' out of bldg line & also noted

    Apr 11, 2018 · Penalty $1,250

    Resolve
  • Class - 2

    Failure to file an acceptable cycle 7 technical report in compliance with code provisions: periodic inspection of exterior walls & appurtenances as required by article 28-302 & the dept of bldgs rules & regulat

    Aug 4, 2014

    Resolve
  • Class - 2

    03x10 - firemen service phase 2 inside car does not work - repair.

    Sep 24, 2013

    Resolve
  • Class - 2

    42b07,56b07,61b07 - provide city id numbers.

    Sep 24, 2013

    Resolve
  • Class - 2

    40p07,34p07. 40,34-provide access to first opening to hoistway and access to machine room to verify elevator devices dismantled state.

    Sep 24, 2013

    Resolve
  • Non-hazardous

    Plumbing work w/o a permit - hazardous. in staircase removed all hose valves on standpipe,hose connections from 1st floor to roof,removed roof manifold. sprinkler head on roof level painted. remedy: obtain the

    Sep 8, 2007

    Resolve
  • Hazardous

    Failure to maintain building. noted: at east elevation, spencer st public stairwell-dislodged, cracked masonary window sills & linters in danger of further dislodgedment. exposed electrical wires, missing light

    May 13, 2003 · Penalty $2,000

    Resolve
  • Non-hazardous

    Altered building occupied without a valid certificate of occupancy is requred for job #301121765 permit issued 8/14/01 convert 2 floor from in 21 individual spaces used as drtists in residence (2 spaces inspect

    Jan 28, 2003 · Penalty $300

    Resolve
  • Hazardous

    Failure to maintain defects are the fire exit door at 1st story east that lead too and from elevator bank is missing now increasing the flame spread in the event of a fire (2) stack of mattress foam approx 8ft

    Jan 7, 2003 · Penalty $800

    Resolve
  • Hazardous

    Work without a permit hazardous (100% of work complete)noted wooden loft constructed with 4"x4"posts and floor joist with spawns up to 20 ft (approx)sagging under weight of piles of cloth workers and sewing mac

    May 16, 2002 · Penalty $800

    Resolve
  • Hazardous

    Exit door total obstruction noted door to street at first fl of public stairwell obstructed by locked rolldown steel gate escape route from upper floor lofts and 1st floor industrial space tottaly obstructed lo

    May 16, 2002 · Penalty $480

    Resolve
  • Non-hazardous

    Use of illegal hardware noted industrialarea approx one city block at first fl level with only exit door to street locked with key at myrtle ave side a 2nd exit door also locked with key at spencer st side whic

    May 16, 2002 · Penalty $350

    Resolve
  • Non-hazardous

    Directional sign defective fails to meet building code standards noted only one proper exit sign with no lighting all other signs are printed with no lighting no exit signs or lightrs in mattress factory

    May 16, 2002 · Penalty $250

    Resolve
  • Hazardous

    Failure to maintain building building noted no fire proof self closing door at spencer st stairwell a second adjacent doorhas no door knobs no lighting at any level of stairwell with no plates on electric boxes

    May 16, 2002 · Penalty $800

    Resolve
  • Hazardous

    Failure to provide at least 2 means of egress where required from room or space noted mattress factory on 1st fl of industrial mid loftarea of city block approx with only one entrance mattress piled up to ceili

    May 16, 2002 · Penalty $480

    Resolve
  • Hazardous

    Work contrary to approved plans / hazarodus work noted: gas lines to stoves and at apt 209 and 220 (2nd fl) showers installed in bathrooms creating 3 pc bathrooms w/ basin ,w/c and shower stall) remedy: amend p

    Mar 8, 2000 · Penalty $500

    Resolve
  • Non-hazardous

    Illegal occupancy : occupancy contrary to that allowed by c of o # 118314 occupancy change from factory to residence at the six floor. remedy: obtain a valid certificate of occupancy ao discontinue the illegal

    Feb 25, 2000 · Penalty $800

    Resolve
  • Non-hazardous

    Work without a permit. work noted: roll down gate installed at north west and south east bulk head exit door leading to roof at fifth story interior . remedy: obtain a permit if feasible or restore the premises

    Jan 27, 2000

    Resolve
  • Non-hazardous

    Work without a permit. work noted: frame plywood partition constructedat one story west extension center created a north & south section (2) plywood mezzanine floor w/ wood steps constructed at above location

    Nov 17, 1999

    Resolve
  • Non-hazardous

    Failure to maintain exterior building wall. defect is: missing and defective masonry work at west wall 2nd story north section. remedy: make all necessary repairs and submit engineers report as to structura

    Nov 17, 1999

    Resolve
  • Hazardous

    Failure to provide adequate protection for sidewalk during construction operations. workers on hanging scaffold removing loose cement from facade pices falling to sidewalk. no sidewalk shed was erected. remedy

    Nov 5, 1998

    Resolve
  • Hazardous

    27-127 failure to maintain exterior building wal. defect: part of concrete around window linter at sixth floor has fell to side walk at various locations. remedy: make safe immediatly

    Sep 16, 1998

    Resolve
  • Hazardous

    A concrete lintel at the 6 story east elevation collapsed.areas of facade in various locations appear loose & defective remedy provide protection obtain permits and approvals and submit an engineers report as t

    Sep 16, 1998 · Penalty $800

    Resolve
  • Non-hazardous

    Failure to submit a fourth round technical report: periodic inspectionexterior walls and appurtenances as required by local law 10 of 1980 and the department of buildings rules and regulations.remedy:file the

    Aug 18, 1998 · Penalty $400

    Resolve
  • Hazardous

    Failure to submit a 4th round technical report: periodic inspection ofexterior walls & appurtenances as required by ll 10 of 1980 & the deptof bldgs rules & regulations. remedy: file the required report.

    Jun 18, 1998 · Penalty $400

    Resolve
  • Non-hazardous

    Exit door not self chosing location 1st story north/west exit remedy repair/rephace exit door

    Jan 29, 1998 · Penalty $180

    Resolve

Complaints

  • Plumbing

    Water supply

    Dec 25, 2007 · Apt 411

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Elevator apartment building (D7)
Year built
1937
Floors
6
Residential units
92
Building area
147,209 ft²
Lot area
44,943 ft²
Zoning
M1-2
Community board
303
Council district
33
Block / lot
1750 / 24
Assessed value
$5,530,950
Landmark / historic district
No

Questions about 692 Myrtle Avenue

Who owns 692 Myrtle Avenue?

The owner of record in NYC Department of City Planning PLUTO data is 144 Spencer Realty Corp.

Does 692 Myrtle Avenue have violations?

Yes. NYC HPD has recorded 1 housing violations at this property.

Is 692 Myrtle Avenue rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 692 Myrtle Avenue built?

City records list 1937 as the year it was built.

How many apartments are in 692 Myrtle Avenue?

It has 92 residential units and 94 units in total.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.