roofy

402 Marion Street

Brooklyn, NY 11233BBL 3-01521-0015Map

Owner of record: Owners 402 Marion LLC

402 Marion Street is a walk-up apartment building built in 1899 in Brooklyn, 11233. It has 3 residential units across 2 floors. The owner of record is Owners 402 Marion LLC. HPD has recorded 20 housing violations here, most recently on November 24, 2025. 16 of the 20 most recent violations are still open.

HPD violations
20
DOB violations
1
ECB violations
9
HPD complaints
19

What to know

Concern
3 open Class C

Immediately hazardous issues among recent violations are still open.

Good
Last violation Nov 24, 2025

Date of the most recent HPD inspection that found a problem.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 20

  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 24, 2025

    Open — Info nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Dec 4, 2024

    Open — Info nov sent out
  • C

    Provide an adequate supply of heat for the apartment in the 1st room from north located at apt 1, 1st story, 1st apartment from east at south

    Jan 18, 2024 · Apt 1

    Open — Nov sent out
  • C

    Provide adequate supply of cold water for the fixtures .. in the entire apartment located at apt 1, 1st story, 1st apartment from east at south

    Jan 18, 2024 · Apt 1

    Open — Nov sent out
  • C

    Provide adequate supply of hot water for the fixtures .. in the entire apartment located at apt 1, 1st story, 1st apartment from east at south

    Jan 18, 2024 · Apt 1

    Closed — Violation dismissed
  • B

    Repair or replace the carbon monoxide detecting device(s). that is missing in the entire apartment located at apt 1, 1st story, 1st apartment from east at south

    Jan 18, 2024 · Apt 1

    Open — Nov sent out
  • B

    Properly repair or replace the broken or defective mortise lock at door to apartment in the entrance located at apt 1, 1st story, 1st apartment from east at south

    Jan 18, 2024 · Apt 1

    Open — Nov sent out
  • B

    Replace with new the missing window glass pane at building entrance door, building front

    Jan 18, 2024

    Open — Nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 28, 2023

    Open — Info nov sent out
  • C

    Provide adequate supply of hot water for the fixtures at wash basin in the bathroom located at apt 1, 1st story, 1st apartment from east at south

    Sep 23, 2023 · Apt 1

    Closed — Violation closed
Show 10 more ↓
  • C

    Provide adequate supply of cold water for the fixtures at wash basin in the bathroom located at apt 1, 1st story, 1st apartment from east at south

    Sep 23, 2023 · Apt 1

    Closed — Violation closed
  • B

    Abate the infestation consisting of mice in the entire apartment located at apt 1, 1st story, 1st apartment from east at south

    Sep 23, 2023 · Apt 1

    Open — Nov sent out
  • B

    Repair the broken or defective plastered surfaces and paint in uniform color at ceiling and east wall in the bathroom located at apt 1, 1st story, 1st apartment from east at south

    Sep 23, 2023 · Apt 1

    Open — Nov sent out
  • C

    Provide hot water at all hot water fixtures in the entire apartment located at apt 1, 1st story, 1st apartment from east at south

    Sep 23, 2023 · Apt 1

    Closed — Violation closed
  • C

    Abate the infestation consisting of rodents : rats at the front yard of the building , 1st story

    May 8, 2023

    Open — Nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 17, 2022

    Open — Info nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Mar 16, 2022

    Open — Info nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Apr 21, 2021

    Open — Info nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 7, 2019

    Open — Info nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Jan 8, 2018

    Open — Info nov sent out

DOB building violations · 1

  • Plumbing none

    P-plumbing none

    Feb 8, 1989

    Dob violation - dismissed

ECB violations · 9

  • Class - 2

    Failure to comply with storm /rain drainage requirements for yard: observed at exposure 1 41/2in. cast iron sewer pipe protruding from breaching in wall at 1st floor to allow water flow onto side walk , which c

    May 14, 2026 · Penalty $6,250

    Active
  • Class - 1

    Observed active jobsite with alt permit b00655019-i1-gc expired on 09/20/2025. workers were performing interior renovation throughout the site under the supervision of the owner's representative. no updated log

    Jan 20, 2026 · Penalty $2,500

    Active
  • Class - 2

    Alteration of a 4 story building. observed inadequate roof protection not fully covering 20ft of the adjacent property with a pump jack scaffold on top at exp#2 contrary to approved site safety plans. stored m

    Aug 22, 2025

    Resolve
  • Class - 2

    Alteration of a 4 story building. observed erected sidewalk shed at exp#1 and pump jack scaffold at exp#2 when requested for drawings and manufacture's specifications, none was provided.

    Aug 22, 2025

    Resolve
  • Class - 2

    Upon inspection i observed a fence installed at exposure 1 not constructed or maintained according to code. gray door installed on fence (fence not fully hunter green). 8ft height requirement not met above entr

    May 27, 2025 · Penalty $1,000

    Active
  • Class - 2

    Upon inspection i observed a fence installed at expos 1 with no fence project info panel provided contrary to code 3301.9.1 fence project information panel. where a site is enclosed with a fence in accordance w

    May 27, 2025 · Penalty $1,250

    Active
  • Class - 1

    Assess granted observed on second floor stove was removed exposing the gas line and removal of sink exposing waste line failure to matane holes in walls and ceiling on first and second floor., obtain permit

    Feb 28, 2024 · Penalty $6,250

    Resolve
  • Class - 2

    Assess granted observed on second floor stove was removed exposing the gas line and removal of sink exposing waste line failure to matane holes in walls and ceiling on first and second floor., repair and/or rep

    Feb 28, 2024 · Penalty $3,125

    Active
  • Non-hazardous

    Work without a permit. noted: gut demo on1st floor with new partitions erected. remedy: stop all work immediately, obtain approvals, permits and plans from deparment of building.

    Feb 13, 2003 · Penalty $500

    Resolve

Complaints

  • General

    Cooking gas

    Aug 3, 2024 · Apt 1

    Close
  • Heat/hot water

    Apartment only

    Jan 16, 2024 · Apt 1

    Close
  • Door/window

    Door

    Nov 16, 2023 · Apt 1STFLO

    Close
  • Plumbing

    Water supply

    Nov 7, 2023 · Apt 1

    Close
  • Plumbing

    Water supply

    Sep 22, 2023 · Apt 1

    Close
  • Unsanitary condition

    Pests

    Sep 22, 2023 · Apt 1

    Close
  • Paint/plaster

    Wall

    Sep 22, 2023 · Apt 1

    Close
  • Unsanitary condition

    Mold

    Sep 22, 2023 · Apt 1

    Close
  • Unsanitary condition

    Garbage/recycling storage

    Jun 18, 2023 · Apt BLDG

    Close
  • Unsanitary condition

    Garbage/recycling storage

    Jun 18, 2023 · Apt BLDG

    Close
Show 9 more ↓
  • Unsanitary condition

    Pests

    Apr 16, 2023 · Apt 1

    Close
  • Unsanitary condition

    Pests

    Mar 30, 2023 · Apt PVTRAT

    Close
  • Unsanitary condition

    Mold

    Nov 27, 2018 · Apt FL1

    Close
  • Paint/plaster

    Ceiling

    Nov 27, 2018 · Apt FL1

    Close
  • Unsanitary condition

    Pests

    Nov 27, 2018 · Apt FL1

    Close
  • Heat/hot water

    Entire building

    Feb 9, 2017 · Apt 2

    Close
  • Heat/hot water

    Entire building

    Jan 31, 2017 · Apt 1

    Close
  • Heat/hot water

    Entire building

    Jan 16, 2017 · Apt 1

    Close
  • Heating

    Heat related

    Mar 1, 2005 · Apt 2FL

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Walk-up apartment building (C0)
Year built
1899
Floors
2
Residential units
3
Building area
2,080 ft²
Lot area
2,000 ft²
Zoning
R6
Community board
316
Council district
41
Block / lot
1521 / 15
Assessed value
$59,100
Landmark / historic district
No

HPD registration #816197, last renewed Sep 28, 2016.

Questions about 402 Marion Street

Who owns 402 Marion Street?

The owner of record in NYC Department of City Planning PLUTO data is Owners 402 Marion LLC.

Does 402 Marion Street have violations?

Yes. NYC HPD has recorded 20 housing violations at this property.

Is 402 Marion Street rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 402 Marion Street built?

City records list 1899 as the year it was built.

How many apartments are in 402 Marion Street?

It has 3 residential units.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.