roofy

520 Chauncey Street

Brooklyn, NY 11233BBL 3-01517-0009Map

Owner of record: Cuevas, Sinencio Antonio

520 Chauncey Street is a walk-up apartment building built in 2004 in Brooklyn, 11233. It has 3 residential units across 3 floors. The owner of record is Cuevas, Sinencio Antonio. HPD has recorded 18 housing violations here, most recently on May 8, 2026. 6 of the 18 most recent violations are still open.

HPD violations
18
DOB violations
1
ECB violations
21
HPD complaints
4

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
Last violation May 8, 2026

Date of the most recent HPD inspection that found a problem.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 18

  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    May 8, 2026

    Open — Nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 20, 2025

    Closed — Violation dismissed
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Jun 13, 2025

    Open — Nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 29, 2024

    Closed — Violation dismissed
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Apr 17, 2024

    Open — Nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 22, 2023

    Closed — Violation dismissed
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Mar 31, 2023

    Open — Nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 14, 2022

    Closed — Violation dismissed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Mar 9, 2022

    Closed — Violation dismissed
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Mar 9, 2022

    Open — Nov sent out
Show 8 more ↓
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Apr 19, 2021

    Closed — Violation dismissed
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Apr 19, 2021

    Open — Nov sent out
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 4, 2019

    Closed — Violation dismissed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Oct 26, 2018

    Closed — Violation dismissed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Dec 8, 2017

    Closed — Violation dismissed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 28, 2016

    Closed — Violation dismissed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Oct 20, 2015

    Closed — Violation dismissed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Mar 4, 2015

    Closed — Violation dismissed

DOB building violations · 1

  • Construction other optional

    C-construction other optional

    May 25, 2005

    Dob violation - dismissed

ECB violations · 21

  • Hazardous

    Job site fence defective: noted: two sheets of plywood for job site fence located at front of premises is unsupported, creating a dangerous condition in the event of strong wind, also leaving job site open to

    May 20, 2005 · Penalty $500

    Resolve
  • Hazardous

    Failure to maintain : defect noted : various debris at front of premise. debris includes but not limited to wood, paper, plastic, metal. approx 10 - 15 yards remedy : remove debris

    Aug 4, 2004 · Penalty $800

    Resolve
  • Hazardous

    No guard rails; no guard rails at 2nd floor door opening it is a drop of approx 12 - 16 ft. to ground remedy : provide guard rails

    Aug 4, 2004

    Resolve
  • Hazardous

    Job site fence defective violation # 34406118p at time of inspection no one was working however site was open accessable to the public with opening on floors and walls remedy repair and or replace fence

    Jan 22, 2004

    Resolve
  • Non-hazardous

    Expired permit # 301432359 nb is under construction and nb permit has expired on 11/9/03 remedy stop all work renew permit

    Dec 30, 2003

    Resolve
  • Hazardous

    Failure to maintain hazardous defect noted a portion of sidewalk const fence is missing and other park defective creating a hazardous condition for pedestrians remedy make site safe repair defective fence

    Dec 3, 2003 · Penalty $800

    Resolve
  • Hazardous

    Failure to maintain adequate housekeeping at time of inspection large amount of combustible debris was stored on construction site, wood, paper. remedy: maintain adequate housekeeping.

    Oct 2, 2003 · Penalty $500

    Resolve
  • Hazardous

    Failure to safeguard public and propery affected by construction operation. following unsafe condition exist 91) 16 ft section of construction fence missing at front of structure. remedy: safeguard public & pro

    Oct 2, 2003

    Resolve
  • Hazardous

    Job site fence defective approximately 16 ft section of fence is missig allowing access to site. remedy: repair/or replace fence

    Oct 2, 2003 · Penalty $500

    Resolve
  • Hazardous

    No guard rails: no guard rails provided at stair openings from 1st to 3rd floors. no guard rails provided at balcony opening from 2&3 floor at rear of structure & from 3 floor at front of structure.

    Oct 2, 2003

    Resolve
Show 11 more ↓
  • Hazardous

    No guard rails at time of inspection men were working 1st fl and it time observed that there were opening on 1st , 2 fl approx 6-0 wide with no protection remedy provide guardrails

    Jul 28, 2003 · Penalty $500

    Resolve
  • Non-hazardous

    Failure to provide approval plans at premises at time of inspection at time of inspection men were working on beams sub fl and there were no approved plans on site for inspection remedy stop all work provide

    Jul 28, 2003 · Penalty $250

    Resolve
  • Hazardous

    Questionable construction at time of inspection man were workin on beams sub flooring and it was observed that there were no stopping on parapet wall as per code remedy stop all work and provide stops as per

    Jul 28, 2003 · Penalty $500

    Resolve
  • Non-hazardous

    Failure to post contractors sign at time of inspection men were working and there were no contractors sign posted remedy: provide contractor sign

    Jul 28, 2003 · Penalty $500

    Resolve
  • Hazardous

    Job site fence defectice at time of inspection men were working and there was an opening of 12-0' wide with plywood nail to 2x2 4-0' high remedy repair and or replace fence

    Jul 28, 2003 · Penalty $500

    Resolve
  • Non-hazardous

    Work without a valid permit: note permit #30143235901 nb expire 4/25/03. work noted, construction of three story concrete block structure. remedy: stop all work: obtain a valid permit.

    Jul 10, 2003

    Resolve
  • Non-hazardous

    Failure to post contractor sign defect is contractor sign not posted. remedy: post contractor sign.

    Jul 10, 2003 · Penalty $500

    Resolve
  • Non-hazardous

    Failure to post work permit. work noted: at front of building (east) construction work in progress no work permit posted (new building) on fence. remedy: post work permit. immediately.

    Jun 26, 2003

    Resolve
  • Hazardous

    Failrure to provide protection at sides of excavation.at time of inspection site excavated.foundation footing forming is underway and no protection provided at sides of excavation depth approx 10ft, angle 90o

    May 29, 2003 · Penalty $1,000

    Resolve
  • Hazardous

    Failure to safeguard public and property.at time of inspection side excavated workers forming footings.violation noted:1)construction site is not fully enclosed and accessible to public 2)tow-truck is on the

    May 29, 2003 · Penalty $1,000

    Resolve
  • Hazardous

    Failure to provide safe means of egress;site excavated workers forming footing & no safe egress provided.

    May 24, 2003 · Penalty $1,000

    Resolve

Complaints

  • Paint/plaster

    Wall

    Jul 14, 2019 · Apt 3

    Close
  • Heat/hot water

    Apartment only

    Nov 19, 2015 · Apt 2FL

    Close
  • Nonconst

    Rubbish

    May 13, 2011 · Apt 1

    Close
  • Nonconst

    Vermin

    May 13, 2011 · Apt 1

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Walk-up apartment building (C0)
Year built
2004
Floors
3
Residential units
3
Building area
4,056 ft²
Lot area
2,600 ft²
Zoning
R6
Community board
316
Council district
37
Block / lot
1517 / 9
Assessed value
$81,300
Landmark / historic district
No

HPD registration #382589, last renewed Apr 30, 2024.

Questions about 520 Chauncey Street

Who owns 520 Chauncey Street?

The owner of record in NYC Department of City Planning PLUTO data is Cuevas, Sinencio Antonio.

Does 520 Chauncey Street have violations?

Yes. NYC HPD has recorded 18 housing violations at this property.

Is 520 Chauncey Street rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 520 Chauncey Street built?

City records list 2004 as the year it was built.

How many apartments are in 520 Chauncey Street?

It has 3 residential units.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.