roofy

261 Van Brunt Street

Brooklyn, NY 11231BBL 3-00530-0002Map

Owner of record: 267 Vanbrunt Realty LLC

261 Van Brunt Street is an elevator apartment building built in 2015 in Brooklyn, 11231. It has 19 residential units across 3 floors. The owner of record is 267 Vanbrunt Realty LLC. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
6
ECB violations
21
HPD complaints
0

Available now in this building

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 6

  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Dec 7, 2020

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Nov 13, 2019

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Nov 13, 2019

    Dob violation - resolved
  • Elevator annual inspection / test elevatorrequired

    Violation issued to elevator-failure to file category 1 2015 inspection/test

    Dec 1, 2016

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Apr 8, 2015

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 14, 2015

    Dob violation - dismissed

ECB violations · 21

  • Class - 2

    Work does not conform to approved construction documents and/or approved amendments.insp dwg 02.06.15 premises under alt 2 #320820929 loc. at time of inspection found. plan does not indicate boiler room and spr

    Feb 15, 2017 · Penalty $2,500

    Resolve
  • Class - 2

    Sec. 28-110.1 failure to provide osha 10 cards. at time of inspection i observed an active construction site 3 sty new bldg. i noted carpernters,electricians & labors working on the site. randomly i asked the

    Apr 1, 2016

    Resolve
  • Class - 2

    Partial stop work order for supported scaffold issued pursuant to 28-207.2 & posted at premises. failure to maintain adequate housekeeping per section requirements. note: observed construction materials & debri

    Mar 31, 2016

    Resolve
  • Class - 1

    Partial stop work order for supported scaffold issued pursuant to 28-207.2 & posted at premises. failure to safeguard all persons & propertyaffected by construction operation. note: observed supported scaffold

    Mar 31, 2016 · Penalty $2,400

    Resolve
  • Class - 1

    Sec. 3314.8.1 partial stop work order for supported scaffold issued pursuant to 28-207.2 & posted at premises unsafe conditions. note: observed supported scaffold have been erected all around the bldg. scaffold

    Mar 31, 2016 · Penalty $1,600

    Resolve
  • Class - 1

    Sec. 3314.4.3.3 partial stop work order for supported scaffold issued pursuant to 28-207.2 & posted at premises. installation report. note: observed supported scaffold have been erected all around the bldg.

    Mar 31, 2016 · Penalty $1,600

    Resolve
  • Class - 1

    Sec. 3314.5.5 partial stop work order for supported scaffold issued pursuant to 28-207.2 & posted at premises. unsafe condition. note: observed supported scaffold have been erected all around the bldg. scaffold

    Mar 31, 2016 · Penalty $1,600

    Resolve
  • Class - 1

    Sec. 3314.13.2 partial stop work order for supported scaffold. issued pursuant to 28-207.2 & posted at premises. unsafe conditions. note: observed supported scaffold have been erected all around the bldg. scaff

    Mar 31, 2016 · Penalty $1,600

    Resolve
  • Class - 1

    Sec. 48 partial stop work order for supported scaffold issued pursuantto 28-207.2 & posted at premises. failure to adequately supervise workat a construction site,so as to maintain a safe construction site.

    Mar 31, 2016 · Penalty $1,600

    Resolve
  • Class - 2

    Failure to comply w/ the comm's order to file a cert of correction w/ the dob.ecb vio#35121746p,011015bs06m102 issued 1/10/15 has no record of correction on file.rem file a cert of correction

    Aug 3, 2015 · Penalty $830

    Resolve
Show 11 more ↓
  • Class - 3

    Failure to post permit.noted: no permits posted from 340247192,340155389,321087006.only nb 320962231 is posted at time of inspection. rmdy: post all permits.

    Jun 5, 2015

    Resolve
  • Class - 1

    Failure to notify the dob within 24 to 48 hours of the start of excavation. jobsite was excavated at a depth of apprx 40" and the dob was not notified of the start of excavation.rmdy: officially notify the do

    Mar 3, 2015

    Resolve
  • Class - 1

    Bc3303.4.1 failure to maintain areas used by public upon inspection noted frozen snow and ice covered the entire area of the sidewalk in front of this demolition site creating extreme slippery condition for

    Jan 10, 2015 · Penalty $8,000

    Resolve
  • Class - 2

    No viewing panels upon inspection noted viewing panels not provided onthe solid construction fence erected at this demolition site. rmdy: comply w/the code.

    Jan 10, 2015

    Resolve
  • Class - 1

    Bc3303.4.1 failure to maintain areas used by public.upon inspection,noted forzen snow covered the entire area of the side walk in front of this demolition site creating extreme slippery condition for the pedes

    Jan 10, 2015 · Penalty $8,000

    Resolve
  • Class - 2

    No viewing panel- upon inspection, noted viewing panels not provided on the solid construction fence erected at this demolition site. rmdy: comply w/code.

    Jan 10, 2015 · Penalty $830

    Resolve
  • Class - 2

    No viewing panels upon inspection,noted viewing panels not provided onthe solid construction fence erected at this demolition site. rmdy:comply w/the code.

    Jan 10, 2015

    Resolve
  • Class - 2

    Failure to provide/accepted plans at job site at time of inspection. note: at time of inspection demolition work in progress. upon request for approved plans for work being done none was provided.rmdy: stop al

    Oct 15, 2014 · Penalty $530

    Resolve
  • Class - 1

    Bc3307.3.2 failure to provide fence as required. noted: at time of my inspection demolition work in progress. i observed that there were no fence provided at exp2,where adjacent property rear yard exist and th

    Oct 15, 2014 · Penalty $1,600

    Resolve
  • Class - 2

    Work does not conform to approved cons docs & or approved ammends.@ time of insp noted that the sidewalk shed erected on sidewalk was erected improperly.the plans call for the shed to extend from the bldg prope

    Sep 25, 2014 · Penalty $530

    Resolve
  • Class - 2

    Project info panel/sidewalk shed parapet panel const sign not providedor not in compliance with section,@ time of pre-demolition insp noted that the sidewalk shed installed on the site did not have affixed on t

    Sep 25, 2014 · Penalty $830

    Resolve

Complaints

No HPD complaints in our records

Complaint data is still being backfilled from NYC Open Data.

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Elevator apartment building (D1)
Year built
2015
Floors
3
Residential units
19
Building area
18,089 ft²
Lot area
11,500 ft²
Zoning
R5
Community board
306
Council district
38
Block / lot
530 / 2
Assessed value
$2,402,550
Landmark / historic district
No

HPD registration #388169, last renewed Aug 18, 2025.

Questions about 261 Van Brunt Street

Who owns 261 Van Brunt Street?

The owner of record in NYC Department of City Planning PLUTO data is 267 Vanbrunt Realty LLC.

Does 261 Van Brunt Street have violations?

NYC HPD has no housing violations on record for this property.

Is 261 Van Brunt Street rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 261 Van Brunt Street built?

City records list 2015 as the year it was built.

How many apartments are in 261 Van Brunt Street?

It has 19 residential units.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.