roofy

350 Hicks Street

Brooklyn, NY 11201BBL 3-00282-0050Map

Owner of record: Hicks St Cobble Hill LLC

350 Hicks Street is an office building built in 2020 in Brooklyn, 11201. It has 48 residential units across 20 floors. The owner of record is Hicks St Cobble Hill LLC. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
70
ECB violations
45
HPD complaints
0

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. The newest 10 per agency here; the full lists are a click away.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 70

  • Construction other optional

    Borough commissioner has ordered all work stopped underpermit# b01203167-i1 on 3/5/26. contractor withdrawal.

    Jun 10, 2026

    Dob violation - dismissed
  • Plumbing none

    Based on lmp withdrawn application. stop all plumbing work under job # 321189584 immediately.

    Apr 29, 2026

    Dob violation - dismissed
  • Construction other optional

    As per section 28-207.2 stop all work immediately under permit #321189584 due to permit holder has informed the department that she or he has withdrawn from the project withdrawal from the project and make site safe.

    Jan 20, 2026

    Dob violation - dismissed
  • Construction other optional

    As per section 28-207.2 stop all work immediately under permit #320911091 due to permit holder has informed the department that she or he has withdrawn from the project withdrawal from the project and make site safe.

    Jan 20, 2026

    Dob violation - dismissed
  • Immediate emergency anythingoptional

    Repair approdximately 25 linear feet of construction fence at exposure 1 (hicks street) to enclose site and safeguard the public

    Feb 3, 2025

    Dob violation - dismissed
  • Construction other optional

    Structure rendered non compliant at time of inspection damage observed to have been sustained to approx 25 linear feet on construction fence due to "amazon truck " impact , disloging construction fence fence must be maintained in code cmapiant manner

    Feb 2, 2025

    Dob violation - dismissed
  • Failure to post energy grade/score none

    Failure to display energy efficiency score and energy efficiency grade as per adcode sec. 28-309.12.3

    Dec 1, 2024

    Dob violation - dismissed
  • Failure to benchmark none

    Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4

    Aug 2, 2024

    Dob violation - dismissed
  • Failure to submit eer none

    Failure to submit an eer per ad. code sec. 28-308.4 - multiple years (2023)

    Jun 23, 2024

    Dob violation - dismissed
  • Failure to benchmark none

    Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4

    May 2, 2024

    Dob violation - dismissed
See all 70 DOB violations (10 shown here)

ECB violations · 45

  • Class - 1

    At time of inspection observed: proposed 20 story mixed-use nb at foundation stage. active job site. after reviewing logs, site was open multiple days fixing fence. upon searching on system site safety manager

    Aug 4, 2026 · Penalty $5,000

    Resolve
  • Class - 2

    Observed fence not maintained as required by code (bc 3307.7) - advertising and graffiti all over. maintain fence

    Dec 31, 2025 · Penalty $1,000

    Resolve
  • Class - 1

    Observed fence panel collapsed on expo #3 (bc 3307.7), creating hazard of unwanted public access (bc 3301.2). repair/maintain fence.

    Dec 31, 2025 · Penalty $10,000

    Resolve
  • Class - 1

    3304.8 and 3304.14.2. failure to dwain construction site of standing water. as noted: at time of inspection at an active jobsite for a proposed 7 story building already at the 1st floor level observed approxima

    May 20, 2025 · Penalty $2,500

    Resolve
  • Class - 1

    Bc 3304.8/3303.14.1. failure to drain construction site of standing water. as noted at time of inspection on a construction site was closed foundation phase. observed approx. 3 to 4ft inside the water tank of c

    Oct 31, 2024 · Penalty $12,500

    Active
  • Class - 1

    Failure to submit the required parking structure initial observation report for an existing parking structure or a periodic inspection of a parking structure(pips) report documenting the conditions of psid#b000

    Oct 1, 2024 · Penalty $6,250

    Resolve
  • Class - 1

    Failure to submit the required parking structure initial observation report for an existing parking structure or a periodic inspection of a parking structure(pips) report documenting the conditions of psid#b000

    Oct 1, 2024

    Resolve
  • Class - 2

    Failure to maintain building in code-compliant manner. at time of inspection, observed at construction site, temporary equipment (fence), approximately 460 linear feet, is in a state of disrepair. the 8 feet x

    Oct 3, 2023 · Penalty $625

    Active
  • Class - 2

    Temporary construction equipment on site-expired permit. fence or sidewalk shed. exist permit #321189584-01-eq-fn have expired at 12/29/2022., renew permit

    Aug 31, 2023 · Penalty $3,125

    Resolve
  • Class - 3

    Failure to maintain building in code compliant manner. noted, at time of inspection construction temporary fence have graffiti and posted ads approx. 200 liner ft. long on a expired fence permit 321189584-01-eq

    Aug 31, 2023 · Penalty $500

    Active
See all 45 ECB violations (10 shown here)

Complaints

No HPD complaints in our records

Complaint data is still being backfilled from NYC Open Data.

Sales history

DatePriceTypeUnits
Feb 18, 2026$33,200,000Office buildings50

Building details

Building type
Office building (O8)
Year built
2020
Floors
20
Residential units
48
Building area
145,845 ft²
Lot area
24,666 ft²
Zoning
R6
Community board
306
Council district
39
Block / lot
282 / 50
Assessed value
$1,592,550
Landmark / historic district
No

Questions about 350 Hicks Street

Who owns 350 Hicks Street?

The owner of record in NYC Department of City Planning PLUTO data is Hicks St Cobble Hill LLC.

Does 350 Hicks Street have violations?

NYC HPD has no housing violations on record for this property.

Is 350 Hicks Street rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 350 Hicks Street built?

City records list 2020 as the year it was built.

How many apartments are in 350 Hicks Street?

It has 48 residential units and 50 units in total.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.