Owner of record: 3607 Greystone Realty LLC

3607 Greystone Avenue is a walk-up apartment building built in 2018 in Bronx, 10463. It has 15 residential units across 5 floors. The owner of record is 3607 Greystone Realty LLC. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
7
ECB violations
19
HPD complaints
3

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 7

  • Construction other optional

    Bc swo due to withdrawal of general contractor for job #220368484. the percentage of waork is around 35% completed

    Dec 1, 2022

    Dob violation - active
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Sep 2, 2020

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 26, 2019

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Nov 27, 2019

    Dob violation - dismissed
  • Construction other optional

    Support of excavation dwgs:upon ceu audit,it was observed that the 45 degree slope started less than 5 feet away from the foundation of adj properties 3605 greystone avenue exp2 and 3615 greystone avenue exp4 this is contrary to the code 3304.2 which requires a minimum of 5 feet comply with code

    Nov 20, 2019

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Sep 19, 2019

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    May 16, 2019

    Dob violation - dismissed

ECB violations · 19

  • Class - 2

    Upon inspection, observed no construction activities jobsite close. at exposure #1 observed a construction fence under permit number 220368484 which is expired since 10/01/2022.

    Oct 24, 2022

    Resolve
  • Class - 2

    Temporary construction equipment on site expired permit at the time of my inspection the siet was closed however on viewing the permits posted the fence permit 220368484-01 eq-fn expired 2-26-2021 on further re

    Apr 7, 2021 · Penalty $3,125

    Resolve
  • Class - 1

    Unlawful continued work while on notice of a stop work order-under ceuaudit,upon review of the special inspection report dated feb 28,2020 for structural steel welding inspections of two colums on the 4th floor

    Mar 16, 2020 · Penalty $5,000

    Active
  • Class - 1

    Bc 1704.4 failure to file a spectual inspection statement of responsibility to permit issuance and/or prior to start of work under special inspection requirment( no tri fo structual cold-from steel) @time of

    Oct 18, 2019 · Penalty $2,500

    Resolve
  • Class - 2

    Bc 3307.2.1 failure to comply with d.o.t regulations (no d.o.t permit)-@time of inspection, a debris construction container and a heavy machinery boom material lift was stored on the street in front of the cons

    Oct 18, 2019

    Resolve
  • Class - 2

    Jobsite fence no constructed or maintained pursuant to sub-section-@time of inspection, a fence was installed around the perimeter of the rear of the construction site. however the fence @exp#2 did not contain

    Oct 18, 2019

    Resolve
  • Class - 1

    Failure to institute/maintain safety equipment measures or temporary construction-no guardrails- @time of inspection inadequate guardrails were in place @the rear balcony of the upper floor. in addition, no

    Oct 18, 2019 · Penalty $5,000

    Resolve
  • Class - 1

    Failure to deisgnate and/or have construction superintendent present @site when required- @time of inspection, the registerd const super "alan bolton" was not on site. upon review of the daily logbook present

    Oct 18, 2019

    Resolve
  • Class - 1

    Work does not conform to approved documents and/or approved amendments.-@time of inspection: 1) the exterior wall @exp#4, which was near theshared side passageway of adjacent property, contained a layer of bric

    Oct 18, 2019 · Penalty $2,500

    Resolve
  • Class - 1

    Failure to provide special inspection that meet qualification requirement set forth in appendix a of rcny 101-06:under the ceu's audit,upon review of the special inspection reports performed by certified testin

    Sep 23, 2019 · Penalty $1,250

    Active
Show 9 more ↓
  • Class - 1

    B106 ac28-104.7.1 inadequate design documents/drawings:under ceu's audit,upon review of the latest structual drawings dated 7/8/19 prepared by anthony hatziioannou architect,p.c,the drawings are observed to be

    Aug 26, 2019

    Resolve
  • Class - 1

    Work does not conform to approved construction documents and or approved amendments as noted at time of my inspection observed no detail for () 2 addition column on the first floor (hss)column) (3) balcony deta

    Jun 19, 2019 · Penalty $12,500

    Active
  • Class - 2

    Construction fence. at the time of inspection of a 5 story new building under construction at 4th fl level. some workers were working on site. i also observed construction fence was leaning at exposure 3,creati

    Apr 18, 2019

    Resolve
  • Class - 1

    Bc 3301.6 design drawing for temporary construction. at the time of inspection of a 5 story new building under construction at 4th fl level.some workers were working on site. i also observed a temporary platfor

    Apr 18, 2019 · Penalty $625

    Resolve
  • Class - 2

    Log. at the time of inspection of a 5 story new building under construction at 4th fl level. some workers were working on site. i also observed the log book they provided not adequate. there are no sign and dat

    Apr 18, 2019 · Penalty $2,500

    Resolve
  • Class - 1

    Hand rails. at the time of inspection of a 5 story new building under construction at 4th fl level. some workers were working on site. i also observed all stairs have no hand rails throughout the building creat

    Apr 18, 2019 · Penalty $2,500

    Resolve
  • Class - 1

    Duties of construction superintendent. at the time of inspection of a 5 story new building under construction at 4th fl level. some workers were working on site. i also observed construction superintendent not

    Apr 18, 2019 · Penalty $2,500

    Resolve
  • Class - 1

    Failure to provide sidewalk shed where required. note: a 5 story new building under contruction 2nd floor p/ work stage i observed that there was no sidewalk shed in place. sidewalk shed shall be installed and

    Feb 16, 2019 · Penalty $2,400

    Resolve
  • Class - 1

    Bc28-105.12.1. work after hours variance without a permit. note: a 5 story building under construction 2nd floor work in progress. i observed two workers laying brick at exp#1 without a work after hours permit.

    Feb 16, 2019 · Penalty $625

    Active

Complaints

  • Heat/hot water

    Entire building

    Apr 22, 2026 · Apt BLDG

    Close
  • Heat/hot water

    Entire building

    Mar 17, 2026 · Apt BLDG

    Close
  • Heat/hot water

    Entire building

    Mar 14, 2026 · Apt BLDG

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Walk-up apartment building (C1)
Year built
2018
Floors
5
Residential units
15
Building area
10,935 ft²
Lot area
4,981 ft²
Zoning
R6
Community board
208
Council district
11
Block / lot
5771 / 59
Assessed value
$823,950
Landmark / historic district
No

Questions about 3607 Greystone Avenue

Who owns 3607 Greystone Avenue?

The owner of record in NYC Department of City Planning PLUTO data is 3607 Greystone Realty LLC.

Does 3607 Greystone Avenue have violations?

NYC HPD has no housing violations on record for this property.

Is 3607 Greystone Avenue rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 3607 Greystone Avenue built?

City records list 2018 as the year it was built.