1358 Odell Street is a vacant lot in Bronx, 10462. The owner of record is Dnf Builders INC. HPD has no housing violations on record for this property.
- HPD violations
- 0
- DOB violations
- 11
- ECB violations
- 25
- HPD complaints
- 0
What to know
No open immediately-hazardous violations among recent records.
HPD has not cited this building.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 0
No HPD violations on record
DOB building violations · 11
- Construction other optional
Soe drwgs,job#220152313,faild 2 meet min. req. outlined.in 3304.2 req plans w. all dimensions indicatd. soe-004 missng dims for the cant piles. the deficient dwgs r a hazard to public & prperty. remedy: stop all excavatn wrk.submit soe plans&calcs 4 proposd cantilevered soldier piles illustrated on soe-004 by 2/7/25
Feb 5, 2025
Dob violation - active - Construction other optional
Stop all work immediately regarding revocation of approvals and permit s for job #220596086
Jul 16, 2018
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Dec 13, 2017
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Dec 13, 2017
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Dec 13, 2017
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Dec 13, 2017
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Dec 13, 2017
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Nov 15, 2017
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Nov 15, 2017
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Nov 15, 2017
Dob violation - dismissed
Show 1 more ↓
- Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Nov 15, 2017
Dob violation - dismissed
ECB violations · 25
- Class - 2
Temporary construction equipment or installation on site expired permit. as noted at time of inspection 6 story new building vacate land. observed plywood construction fence permit had expired on 07/30/2025. pe
Jan 9, 2026 · Penalty $1,250
Active - Class - 2
Observed construction fence @ perimeter of jobsite. exposure 1 plywood panel for construction fence falling off and leaning as well as fence gate is off hinges and leaning creating a open gap with potential for
Mar 7, 2025 · Penalty $1,000
Resolve - Class - 1
At time of inspection of a active jobsite during my inspection i noticed excavation work in progress observed hole not maintain 45 degree hole about approx 7 feet dept not support as per code 3304.4.4 codes sta
Jan 3, 2025 · Penalty $5,000
Resolve - Class - 2
Job site fence not constructed or maintained; noted at exposure 2 of property line construction fence observed approximately 16 feet of construction fence panels unattached to posts and down on ground and on pa
Jan 18, 2024 · Penalty $1,000
Resolve - Class - 2
Inactive closed jobsite, i observed existing construction jobsite fence (220152313-01-eq-fn) in places at lotline with expired fence permit with expiration dated 06/28/2018 and not renewed in both department bi
Aug 30, 2023 · Penalty $1,250
Resolve - Class - 2
The temporary construction fence permit # 220252313-01-eq-fn at the vacant land expired on 06/28/2018. summons issued for expired fence permit., renew permit; renew permit.
Jul 27, 2023 · Penalty $1,250
Resolve - Class - 2
Temporary construction equipment on site; expired permit: as noted at the time of my inspection observed that fence permit #220152313-01-eq-fn issued on 06-28-2017 and 6/28/2018 expired on further review of dob
Jun 29, 2023 · Penalty $1,250
Resolve - Class - 2
Jobsite fence not maintained pursuant to subsection. at the time of my inspection of a 6 story nb, empty lot job not started. the job site fence at exp 2 is falling down, boards are broken and splintered creati
Nov 21, 2018
Resolve - Class - 1
Failure to certify correction.the respondent failed to comply with an order of the commissioner issued pursuant to section ac28-201,1 oath summons no 35270016m with date of occurrece 08/25/2017.is in violation
Feb 9, 2018 · Penalty $6,000
Resolve - Class - 1
Failure to certify correction-the respondent failed to comply with an order of the commissioner issued pursuant to section ac 28-201.1 oath summons #35270017y with date of occurrence 08/25/2017.hearing date was
Jan 5, 2018
Resolve
Show 15 more ↓
- Class - 1
Failure to certify correction-the respondent failed to comply with an order of the commissioner issued pursuant to section ac 28-201.1 oath summons #35270018x with date of occurrence 08/25/2017.hearing date was
Jan 5, 2018
Resolve - Class - 2
The respondent (permit holder)failed to maintain the fence at 1358 odell st.bronxexposure #2 safe as mandated in bc 3307.7.7 bc3307.7.7 condition of fences states "all fences shall be installed,adjusted repaire
Nov 14, 2017 · Penalty $400
Resolve - Class - 1
Work does not conform to approved construction documents &/or approvedamendments. at time of inspection observed an active construction site w/excavation work for support of excavation on progress,during inspec
Aug 25, 2017 · Penalty $1,000
Resolve - Class - 2
Sec. 3301.2 missing rebar cap. at time of inspection observed construction site w/excavation work on progress,during inspection noted at exp#2,3&4 missing rebar cap. remedy: comply w/code.
Aug 25, 2017 · Penalty $400
Resolve - Class - 2
Rcny 101-06(c)(1) the respondent is identified as the special insp appl for job no #220152313 per tr1 dated 05/20/17 & is not registered w/the dob to conduct those insps 1rcny 101-06(c)(1) mandates,"all agencie
Aug 25, 2017 · Penalty $400
Resolve - Class - 1
Bc 107.7.1 the respondent failed to meet the minimum requirements of the code (ac 28-101.2) & produced foundation/cellar plan (fo-100.00 for job #220152313 that did not identify the bottom of adjacent footings
Aug 25, 2017 · Penalty $1,600
Resolve - Class - 1
Work does not conform to approved construction documents &/or approvedamendments. at time of inspection observed an active construction site w/excavation work for support of excavation on progress. noted the co
Aug 25, 2017 · Penalty $1,000
Resolve - Class - 1
Work does not conform to approved construction documents &/or approvedamendments. at time of inspection observed an active construction sitew/excavation wokr "foundation walls on progress,during inspection note
Aug 25, 2017 · Penalty $500
Resolve - Class - 1
Bc 1704.1.2 the respondent has failed to perform the(responsibilities)of the special insp agencies bc 1704.1.2 mandates the special insp agency shall observe work subject to special insp to confirm that the wor
Aug 25, 2017
Resolve - Class - 2
Sec. 3301.2 no guardrails. at time of inspection observed an active construction site w/excavation work on progress,during inspection noted the contractor failure to install guardrails at exp#3&4 when worker ar
Aug 25, 2017 · Penalty $400
Resolve - Class - 2
Failure to comply w/astm c31 standard for concrete cylinder test samples.@time of insp observed an active const site w/excavation concrete & rebar work on progress,during insp noted the contractor has cylinder
Aug 25, 2017 · Penalty $1,600
Resolve - Class - 1
Bc 3309.4.4;bc 3309.6 the respondent failed to identify the monitoring program (bc 3309.16)under job #220596086,professionally certied.drawings #g-001.00,f-001.00,f-002.00 included excavation/foundation coonst
Aug 25, 2017
Resolve - Class - 1
Construction superintendent failed to perform duties as per rule. at time of inspection observed an active construction site w/excavation "support of excavation" on progress,during inspection noted the construc
Aug 25, 2017 · Penalty $10,000
Resolve - Class - 1
Bc 1704.1; 1rcny 101-06(c)(1). bc 1704.1 requires that the special insp agencies meet ac 28-114.1 & ac 28-115.1 & are retained by the owner to provide insp during consts. @the time of insp,the respondent has fa
Aug 25, 2017 · Penalty $1,600
Resolve - Class - 1
Bc 107.7.1 the respondent failed to meet the minimum reqs of the code (ac 28-101.2) & produced foundation/earthwork drawings for job #220596086,professionally certified that did not identify the bottom of adjac
Aug 25, 2017 · Penalty $1,600
Resolve
Complaints
No HPD complaints in our records
Sales history
No recorded sales in our data
Building details
- Building type
- Vacant lot (V1)
- Year built
- —
- Floors
- —
- Residential units
- —
- Building area
- —
- Lot area
- 2,575 ft²
- Zoning
- R6
- Community board
- 209
- Council district
- 18
- Block / lot
- 3934 / 37
- Assessed value
- $61,200
- Landmark / historic district
- No
Questions about 1358 Odell Street
Who owns 1358 Odell Street?
The owner of record in NYC Department of City Planning PLUTO data is Dnf Builders INC.
Does 1358 Odell Street have violations?
NYC HPD has no housing violations on record for this property.
Is 1358 Odell Street rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.