2160 Broadway
Manhattan, NY 10024BBL 1-01168-0021Map
Owner of record: 2160 Broadway LLC
2160 Broadway is a store building built in 1920 in Manhattan, 10024. The owner of record is 2160 Broadway LLC. HPD has no housing violations on record for this property.
- HPD violations
- 0
- DOB violations
- 23
- ECB violations
- 34
- HPD complaints
- 0
What to know
No open immediately-hazardous violations among recent records.
HPD has not cited this building.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 0
No HPD violations on record
DOB building violations · 23
- Low pressure boiler boiler required
Violation issued-failure to file 2018 external low pressure inspection
Jun 20, 2023
Dob violation - active - Construction other optional
Vehicle impacting sidewalk shed
Jul 29, 2021
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
May 28, 2019
Dob violation - resolved - Elevator affirmation of correction elevatorrequired
Vio issued to elevator - fail to correct defects on 2016 cat 1 insp/tst
Jan 26, 2018
Dob violation - dismissed - Elevator affirmation of correction elevatorrequired
Vio issued to elevator - fail to correct defects on 2015 cat 1 insp/tst
Jan 3, 2017
Dob violation - dismissed - Elevator affirmation of correction elevatorrequired
Vio issued to elevator - fail to correct defects on 2014 cat 1 insp/tst
Nov 14, 2016
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
May 29, 2015
Dob violation - resolved - Elevator affirmation of correction elevatorrequired
Vio issued to elevator - fail to correct defects on 2012 cat 1 insp/tst
May 30, 2014
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2012 inspection report
May 15, 2014
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Apr 3, 2013
Dob violation - resolved
Show 13 more ↓
- Elevator elevatorrequired
E-elevator elevatorrequired
Jul 24, 2012
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Nov 22, 2011
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Dec 28, 2010
Dob violation - resolved - Construction other optional
C-construction other optional
Mar 9, 2008
Dob violation - dismissed - Elevator elevatorrequired
1p17995
Nov 7, 2002
Dob violation - active - Elevator elevatorrequired
1p17999
May 30, 2000
Dob violation - resolved - Elevator elevatorrequired
1p17995
May 30, 2000
Dob violation - resolved - Elevator elevatorrequired
1p17996
May 30, 2000
Dob violation - resolved - Elevator elevatoroptional
Ll1081-local law 10/81 - elevator elevatoroptional
Jan 6, 1998
Dob violation - dismissed - Elevator elevatoroptional
Ll1081-local law 10/81 - elevator elevatoroptional
Jan 13, 1997
Dob violation - active - Elevator elevatoroptional
Ll1081-local law 10/81 - elevator elevatoroptional
Jan 13, 1997
Dob violation - dismissed - Elevator elevatoroptional
Ll1081-local law 10/81 - elevator elevatoroptional
Apr 17, 1995
Dob violation - dismissed - Construction other optional
C-construction other optional
Aug 27, 1991
Vp-violation unserved ecb-active
ECB violations · 34
- Class - 1
At time of inspection, observed foundation wall at exposure #3 partially demolished. upon review of approved construction documents, no details were provided for the demolition work performed, contrary to ac 28
Oct 20, 2026 · Penalty $2,500
Active - Class - 1
Observed proposed 13 story nb in excavation/demo phase, at time of inspection drilling operations were taking place on exp 2. vibration monitoring that exceeded threshold was not notified to the dept. these con
Oct 13, 2026 · Penalty $2,500
Active - Class - 1
Observed proposed 13 story nb in excavation/demo phase, at time of inspection drilling operations were taking place on exp 2. upon request of approved plans, no approved plans were provided to reflect drilling
Oct 13, 2026 · Penalty $2,500
Active - Class - 2
At time of inspection, observed an office trailer installed at the construction site that was not indicated on the approved site safety plan, potentially interfering with planned site safety measures and creati
Oct 12, 2026 · Penalty $1,250
Active - Class - 2
At time of inspection, observed standing water within active excavation during foundation and drilling operations, creating potential soil instability, contrary to bc 3303.14.3. remove accumulated water from e
Oct 12, 2026 · Penalty $2,500
Active - Class - 2
At time of inspection, observed a hose lying directly across the public sidewalk at the construction site entrance without protective covering or a pedestrian bridge, obstructing the pedestrian walkway and crea
Oct 12, 2026 · Penalty $2,500
Active - Class - 1
Failure to comply with 15 rcny 20-08. demolition operation connected split and hoses to the fire hydrant on west 76 street without backflow prevention equipment in contrary with dep's rules and requirements for
Apr 15, 2026 · Penalty $2,500
Resolve - Class - 1
Full demolition of a 4 story building active site, partially demolished. observed adjoining property wall with 4 ft step crack loose exterior wall/voids cracks without crack monitoring gauges existing 2 yellow
Apr 2, 2026 · Penalty $2,500
Resolve - Class - 1
Demolition of a 4 story building active site. partially demolished. observed workers on steel beams at exp#4 performing torching/cutting sparks flames without hot work permits issued onsite contrary to fdny fir
Apr 2, 2026 · Penalty $1,250
Resolve - Class - 1
Failure to comply and maintain as per code specifications 3314.1, 3314.4.3.2, 3314.9.2, 3314.8.1. observed supported scaffold on 3rd floor interior level was missing essential components "mudsills, guardrails,
Mar 4, 2026 · Penalty $5,000
Resolve
Show 24 more ↓
- Class - 2
Observed supported scaffold with multiple planked platforms at expo# 1 & 4 the scaffold was not tied to the structure as per plan , this condition warrants an ecb violation , comply with code stop all use of th
Feb 25, 2026 · Penalty $1,250
Resolve - Class - 2
Observed snow on top of sidewalk shed at expo's # 1 & 4 this condition poses a potential hazard walking pedestrians that are walking underneath the sidewalk shed ( weight of the snow can cause collapse of sca
Feb 25, 2026 · Penalty $2,400
Resolve - Class - 2
Observed at a demolition 4 story building a sidewalk shed installed at the perimeter of the building. at exposure #4, a fire hydrant/standpipe connection was present with no red light or required illumination i
Jan 12, 2026 · Penalty $2,400
Resolve - Class - 1
At time of inspection of a 4-story building,active demolition jobsite i observed jobsite using fire hydrant on west 76 street upon requesting permit for use of fire hydrant none was found or available as per co
Oct 30, 2025 · Penalty $2,500
Resolve - Class - 2
At time of inspection, observed work zone beneath sidewalk shed missing required fencing and barriers; and barriers not interlocked and area accessible to public. contrary to bc 3307.4.7, failure to provide req
Oct 28, 2025 · Penalty $2,500
Resolve - Class - 2
At time of inspection of a 4 stories building under demolition activities i observed debri chute installed and mounted on supported scaffold and cross over sidewalk shed into the container on the street upon re
Oct 27, 2025 · Penalty $625
Resolve - Class - 1
Note: at time of inspection, i observed demolition operations had been commenced without the required notification to the department, also inadequate notification was giving to the adjoining property, (descript
Oct 17, 2025 · Penalty $2,500
Resolve - Class - 2
Note: at time of inspection ongoing demolition operations, i observed a supported pipe scaffold erected on top of the sidewalk shed, upon request for the pe load-imposed letter to verify structural adequacy of
Oct 17, 2025 · Penalty $2,500
Resolve - Class - 1
Note: at the time of inspection, i observed that demolition operations had commenced without the prior removal of glass from windows and doors, contrary to code 3306.9.8.3. this poses significant safety hazards
Oct 17, 2025 · Penalty $5,000
Resolve - Class - 2
Note: at the time of inspection, construction debris and materials were observed scattered throughout the floor areas on levels 1, 2, and 3. this condition creates multiple safety hazards including increased ri
Oct 17, 2025
Resolve - Class - 3
Work does not conform to aproved construction documents &/or approved amendments. work noted 2 a/c units compressors installed on roof underpermit #122830482 locations of these 2 units are not conforming to app
Nov 29, 2016 · Penalty $100
Resolve - Class - 2
Work does not conform to approved plans.(supported scaffold)noted: at time of my inspection plans show that exp 4 of the scaffold shall haveonly 1 full planked. main level & only 6 planked bracket main level &
Jan 21, 2015
Resolve - Class - 1
Sec. 3314.8.1 pswo issued & posted at service entrance were permits are posted. supported scaffold does not meet code specifications. noted:at time of my inspection the scaffold was missing end rails,midrails,
Jan 21, 2015 · Penalty $1,600
Resolve - Class - 2
Partial swo issued for over the sidewalk chute ursuant 28-207.2 and posted on premises failed to obtain permit for temporary construction equipment. noted: at time of inspection over the sidewalk chute is insta
Sep 9, 2014 · Penalty $830
Resolve - Class - 1
Failure to safeguard public and property effected by construction operations noted pump truck hose on sidewalk person also fell tripping on hose no flagperson no dot permits to occupy street no safeguard in pla
Sep 22, 2009 · Penalty $2,400
Resolve - Class - 1
Failure to safeguard public and property affected by construction operations concrete truck blocking 2 lanes of street no dot permits no flag person at street diceeting traffic concrete being poured into concre
Sep 22, 2009 · Penalty $2,400
Resolve - Non-hazardous
73m#. device no 1p8910 is under dismantle status dept of build record shows however my inspection rieveals device was removed illegally propelly file weth the dept of building.
May 20, 2002
Resolve - Non-hazardous
Failure to maintain exterior building wall noted:west parapet wall at 4th floor elevation has step cracks begining at the corners and ascending towards center and leveling off approximately 2'0'from top of pa
Mar 1, 2001 · Penalty $800
Resolve - Hazardous
Failure to maintain bldg wall (hazardous)(exterior)noted:west parapet at the 4th floor elevation has step cracks beginning at the corners and ascending upward toward the center of bldg and leveling off approx 2
Oct 16, 2000 · Penalty $2,500
Resolve - Hazardous
Failure to maintain exterior bldg. wall.noted:west parapet at the 4th fl. elevation has step cracks beginning at the corners and ascending upward toward the center of bldg. and leveling off. approx. 2' down fro
Jun 14, 2000
Resolve - Non-hazardous
Failure to maintain: failure to provide self closing fire-rated doors at open elevator shaft at 1st floor. remedy: seal, open elevator shaft or provide fire-rated self closing doors.
Aug 27, 1991 · Penalty $1,000
Resolve - Non-hazardous
Pa contrary to approved plan. remedy: obtain approved plans.
Jan 24, 1990 · Penalty $400
Resolve - Non-hazardous
Pa contrary to approved plan. remedy: amend pa palns shows changes.
Dec 1, 1989 · Penalty $400
Resolve - Unknown
Work without a permit installation of a fire extinguishing system firststory kitchen rear basement kitchen center location alameda restaurant remedy obtain a permit & approvals
Dec 1, 1988 · Penalty $250
Resolve
Complaints
No HPD complaints in our records
Sales history
No recorded sales in our data
Building details
- Building type
- Store building (K7)
- Year built
- 1920
- Floors
- 4
- Residential units
- —
- Building area
- 8,820 ft²
- Lot area
- 2,210 ft²
- Zoning
- C4-6A
- Community board
- 107
- Council district
- 6
- Block / lot
- 1168 / 21
- Assessed value
- $3,827,700
- Landmark / historic district
- No
Questions about 2160 Broadway
Who owns 2160 Broadway?
The owner of record in NYC Department of City Planning PLUTO data is 2160 Broadway LLC.
Does 2160 Broadway have violations?
NYC HPD has no housing violations on record for this property.
Is 2160 Broadway rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 2160 Broadway built?
City records list 1920 as the year it was built.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.