577 9 Avenue
Manhattan, NY 10036BBL 1-01051-7503Map
Owner of record: Unavailable Owner
577 9 Avenue is a condominium built in 2014 in Manhattan, 10036. It has 45 residential units across 28 floors. The owner of record is Unavailable Owner. HPD has recorded 6 housing violations here, most recently on April 18, 2024.
- HPD violations
- 6
- DOB violations
- 0
- ECB violations
- 37
- HPD complaints
- 26
What to know
No open immediately-hazardous violations among recent records.
Date of the most recent HPD inspection that found a problem.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 6
- ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
Apr 18, 2024
Closed — Violation dismissed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Nov 15, 2023
Closed — Violation dismissed - ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
Mar 31, 2023
Closed — Violation dismissed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Nov 3, 2022
Closed — Violation dismissed - ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
Mar 10, 2022
Closed — Violation dismissed - ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
Apr 20, 2021
Closed — Violation dismissed
DOB building violations · 0
No DOB violations on record
ECB violations · 37
- Class - 2
Failure to file acceptable amended cycle 9c report indicating correction of unsafe conditions described in initial facades report required by 28-302.5 for control #917329. remedy: file acceptable report.
Apr 20, 2026 · Penalty $1,200
Active - Class - 1
Failure to take/provide required action to secure public safety at a designated unsafe building facade as per the technical report unsafe 917329-9c-001.at time of inspection observed sidewalk shed in place at e
Feb 29, 2024 · Penalty $10,000
Resolve - Class - 2
2,x,10 phone inoperative repair.
Aug 16, 2022
Resolve - Class - 1
Alarm system defective repair, communication defective repair re inspection required, (cease used)
Jul 20, 2020 · Penalty $1,250
Resolve - Class - 1
Door restrictor not working, repair, re inspection required, (cease used)
Jul 20, 2020 · Penalty $1,250
Resolve - Class - 2
Failure to maintain building in code-compliant manner. noted: at electrical closet located cellar front observed water penetrating from foundation wall and floor. rem: repair/maintain water leak.
Jul 24, 2018
Resolve - Class - 1
Bc3301.1.3/manufavturer specification:note at time of inspection of a 28 story new building that is topped out.i observe workers walking on genie-gs1930 scissor lift in use.i ask for training as per manufacture
Oct 23, 2017 · Penalty $1,600
Resolve - Class - 1
Bc3301.1.2/fire code:note at time of inspection of a 28 story new building that is topped off.i observed flr 24-28 story with no exits signsin place.this creates a hazardous condition for inspector,1st response
Oct 23, 2017 · Penalty $1,600
Resolve - Class - 1
Sec. 3307.2.6 requirements for sidewalk,temporary walkways,foot bridges & pathways. note: at the time of my inspection of a 28 sty bldg at bulkhead level,construction work in progress. i observed temporary walk
Sep 8, 2017 · Penalty $1,600
Resolve - Class - 1
Sec. 3307.7 fences. note: at the time of my inspection of a 28 sty bldg at bulkhead level,construction work in progress. i observed that there was a chain link fence w/debris netting supported by sand bag and
Sep 8, 2017 · Penalty $1,600
Resolve
Show 27 more ↓
- Class - 1
Sec. 3307.7.5 design of fence. note: at the time of my inspection of a28 sty bldg at bulkhead level,construction work in progress. i observed a chain link fence w/debris netting supported w/sand bag erected at
Sep 8, 2017 · Penalty $1,600
Resolve - Class - 2
Failure to institute safety measures in response to a reported incident,where a worker was stuck in the neck from falling plywood,which happened when bracing became loose & plywood fell,upon request for design
Sep 7, 2017 · Penalty $5,000
Resolve - Class - 1
Failure to safeguard people public property,note @ the 28 fl observed 2 workers installing permanant metal stair components.neither worker was tied off leaving workers exposed to falls of over 10 ft.the site fa
Aug 1, 2017
Resolve - Class - 1
Failure to maintain: guardrails. note: @ the 28 flr- 24 flr the hoist ran @ exp#4 is not enclosed. there are 2 flrs w/ no verticle nets leaving open bay w/ immediate fall hazard & the flrs w/ v-netting is inade
Aug 1, 2017
Resolve - Class - 2
Failure to maintain on site documents.note observed 28 story hoist run@ exp4,dismantling in progress.the site safety log states the hoist temporary cert has been expired since 6/1/17 when i asked for an updated
Aug 1, 2017
Resolve - Class - 2
Failure to provide accepted plans at job site at time of inspection. noted: at time of inspection no plans for c-hook could be provide. remedy: provide accepted construction documents.
Feb 16, 2017 · Penalty $250
Resolve - Class - 1
Sec. 3314.4.3.3 installation inspection,all components of & attachments to the scaffold & all supports & anchorages of the scaffold shall beinspected prior to use to verify they are safe. noted: at time of insp
Feb 16, 2017 · Penalty $800
Resolve - Class - 1
Licensed rigger designated an unquialified foreman. pswo suspended scaffold. noted: at time of inspection there is 6 men working on suspended scaffolds w/c-hook foreman radoslaw korlowski does not have dob fore
Feb 16, 2017 · Penalty $400
Resolve - Class - 1
3301.2 27.1009(a)holes/penetratins/openings not vocered/secured.at the time of inspection observed openings over4" in diameter and approx 1'-6 x2'-6 open and uncovered. creating a potential dange for debris a
Nov 9, 2016 · Penalty $800
Resolve - Class - 1
Failure to institue/maintain safety equipment measures or temporary construction no handrails:note @time of inspection of a 28stry new bldg @bulkhead level i observed no handrails a stair b 3stry to 2nd stry th
Nov 7, 2016 · Penalty $1,000
Resolve - Class - 1
3301.2 holes/openings not covered.@time of inspection if a new 28stry bldg @bulkhead level.i observed several holes on the 27&28stry not covered or (worked).openings were if different sizes that is large enough
Nov 7, 2016 · Penalty $1,600
Resolve - Class - 1
Failure to institute/maintain safety equipment measures or temporary construction no toeboards:note @time of inspection of a 28stry new bldg@bulkhead level.i observe inadequate toeboards @27stry @exp #1 & #4.ac
Nov 7, 2016 · Penalty $1,000
Resolve - Class - 1
Failure to maintaun adequate housekeeping pw sevtion requirements.note@time of inspection of a 28stry new bldg under construction @bulkhead level.i observed inadequate house keeping @various locate the flrs and
Nov 7, 2016 · Penalty $800
Resolve - Class - 1
Work does not conform to approved construction documents and/or approved amendments. noted: at time of inspection of incident at 28sty new building under construction has installed data system at exp1,2 has
Oct 19, 2016 · Penalty $1,000
Resolve - Class - 1
Failure to safeguard all persons and property affected by constructionoperations. at time of inspection, the following was observed.site safety manager and lifting crew stated while lifting concrete bucket
Oct 19, 2016 · Penalty $10,000
Resolve - Class - 1
Bc3307.5 flag persons. at time of inspection the following was observed. while responding to incident of crane lifting concrete bucket, statement from witness states no flag person used to stop traffic just bef
Oct 19, 2016 · Penalty $1,600
Resolve - Class - 1
Work w/o a permit. at time of inspection the following was observed d() formwork platforms from 29-26 flr apprx with no permit as requiredstop all work (exterior d() form work platforms.concrete generations.
Oct 19, 2016 · Penalty $800
Resolve - Class - 1
Inadequate safety measure operation of crane in an unsfe manner at time of inspection of tower crane cd #3021 cn#870/14, observed safety devices not working. anti-two block device not working, low boom limit de
Aug 8, 2016 · Penalty $10,000
Resolve - Class - 1
Supervision or use of power operated hoisting machine w/o a hoisting machine opertors license:performed audit inspection for tower crane cd#3021 cn#87014. at time of inspection observed hmo operator #7968
Jun 9, 2016 · Penalty $1,600
Resolve - Class - 1
Failure to provide unobstructed exot passageway. at time of inspectionnoted at several areas of job site that the exit passageway was ibstructed w/materials & debris,potencial for emergency crews not being able
May 4, 2016 · Penalty $1,200
Resolve - Class - 2
Sec. 3308.5 vertical netting shall be installed & maintained to cover all unclosed perimeters. at time of inspection noted that the vertical netting thru-out the job site is inadequate there are opening at the
May 4, 2016 · Penalty $400
Resolve - Class - 2
Failure to safeguard all persons & property affected by construction operations. at time of inspection noted 2 workers working of an a frameladder leaning againsts the wall not open as it showed by properly use
May 4, 2016 · Penalty $5,000
Resolve - Class - 1
Failure to safeguard all persons & property affected by construction operations. at time of inspection noted a worker on a platform on a elevator shaftway not tied off to any fall protection system approx 4 sty
May 4, 2016 · Penalty $10,000
Resolve - Class - 2
Work does not conform to approved construction documents and/or approved amendments.at time of inspection the following was observed:safety strap installed at proposed 28sty building at 1st (missing) floor have
Sep 23, 2015 · Penalty $250
Resolve - Class - 1
Failure to safeguard.incident inspection:worker fell down inside elevator shaft (at 54 feet down) after platform gave way under his weight;taken to hospital unconscious by ambulance.swo issued prusuant to 28-20
Aug 25, 2015 · Penalty $2,400
Resolve - Class - 2
Fail to maintain lighting under sidewalk shed. noted: shed at exp 1 under pmt 110443388 has inoperable lights. remedy: maintain lighting under shed.
Mar 18, 2009 · Penalty $2,400
Resolve - Non-hazardous
83##/63m07 83# failure to set up appionment to notify department of building of dismantle condition under ebn794/94 for device #1s287 removestationary convey or belt using shaftway hazardous conditions remedy
Sep 12, 2003 · Penalty $180
Resolve
Complaints
- Plumbing
Toilet
Mar 31, 2025 · Apt 6L
Close - Unsanitary condition
Pests
Feb 2, 2024 · Apt 1013
Close - Unsanitary condition
Pests
Feb 1, 2024 · Apt 1731
Close - Plumbing
Toilet
May 14, 2023 · Apt 4I
Close - Nonconst
Rubbish
Jul 23, 2008 · Apt 1
Close - Nonconst
Vermin
Jul 23, 2008 · Apt 1
Close - Heating
Heat related
Jan 5, 2008 · Apt 1
Close - Heating
Heat related
Oct 29, 2007 · Apt 1
Close - Nonconst
Smoke detector
Oct 29, 2007 · Apt 1
Close - Electric
Lighting
Oct 29, 2007 · Apt 1
Close
Show 16 more ↓
- Electric
Lighting
Sep 9, 2007 · Apt BLDG
Close - Electric
Lighting
Sep 9, 2007 · Apt BLDG
Close - Electric
Wiring
Apr 24, 2007 · Apt 2
Close - Nonconst
Rubbish
Nov 30, 2006 · Apt 4
Close - Heating
Heat related
Jan 24, 2006 · Apt 1
Close - Plumbing
Basin/sink
Jan 21, 2006 · Apt 1
Close - General
Locks
Jan 21, 2006 · Apt 1
Close - Nonconst
Rubbish
Jan 21, 2006 · Apt 1
Close - Heating
Heat related
Dec 23, 2005 · Apt 1
Close - Plumbing
Water-leaks
Dec 23, 2005 · Apt 1
Close - Plumbing
Water-leaks
Nov 11, 2005 · Apt 1
Close - Electric
Lighting
Nov 11, 2005 · Apt 1
Close - Electric
Electric-supply
Jun 12, 2005 · Apt 1
Close - Plumbing
Water-leaks
Apr 17, 2005 · Apt 1
Close - Plumbing
Water-leaks
Aug 12, 2004 · Apt BLDG
Close - General
Cooking gas
May 22, 2004 · Apt BLDG
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Condominium (RM)
- Year built
- 2014
- Floors
- 28
- Residential units
- 45
- Building area
- 219,215 ft²
- Lot area
- 17,892 ft²
- Zoning
- C6-4
- Community board
- 104
- Council district
- 3
- Block / lot
- 1051 / 7503
- Assessed value
- $62,045,099
- Landmark / historic district
- No
HPD registration #144855, last renewed Aug 21, 2025.
Questions about 577 9 Avenue
Who owns 577 9 Avenue?
The owner of record in NYC Department of City Planning PLUTO data is Unavailable Owner.
Does 577 9 Avenue have violations?
Yes. NYC HPD has recorded 6 housing violations at this property.
Is 577 9 Avenue rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 577 9 Avenue built?
City records list 2014 as the year it was built.
How many apartments are in 577 9 Avenue?
It has 45 residential units and 49 units in total.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.