257 Bowery
Manhattan, NY 10002BBL 1-00427-0007Map
Owner of record: West-One, LLC
257 Bowery is a public assembly built in 2009 in Manhattan, 10002. The owner of record is West-One, LLC. HPD has no housing violations on record for this property.
- HPD violations
- 0
- DOB violations
- 17
- ECB violations
- 38
- HPD complaints
- 1
What to know
No open immediately-hazardous violations among recent records.
HPD has not cited this building.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 0
No HPD violations on record
DOB building violations · 17
- Low pressure boiler boiler required
Violation issued-failure to file 2023 external low pressure inspection
Sep 23, 2024
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued-failure to file 2023 external low pressure inspection
Sep 23, 2024
Dob violation - active - Elevator elevatorrequired
E-elevator elevatorrequired
Jun 15, 2018
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
May 12, 2016
Dob violation - resolved - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2012 inspection report
May 15, 2014
Dob violation - dismissed - Elevator annual inspection / test elevatorrequired
Violation issued to elevator-failure to file category 1 2012 inspection/test
Mar 31, 2014
Dob violation - dismissed - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2011 inspection report
Mar 1, 2013
Dob violation - dismissed - Elevator annual inspection / test elevatorrequired
Violation issued to elevator-failure to file category 1 2011 inspection/test
Oct 1, 2012
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Apr 5, 2012
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Apr 5, 2012
Dob violation - resolved
Show 7 more ↓
- Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jun 15, 2011
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jun 15, 2011
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Oct 28, 2010
Dob violation - resolved - Construction other optional
Work does not conform to approved construction documents and/or approv ed amenments noted: upon inspection rods secured to adjoining building at exposure 2/4 to secure forms for concrete foundation not on plans/ and or not accepted stop all work! along exposure 2/4 of adjoining bld g remedy: conform to approved documents or amendments call excavation
Sep 9, 2009
Dob violation - dismissed - Construction other optional
Contractor installed structural steel i beams at exp 2 and stretchs ac ross to exp 4 for bracing steel bracing is not provided for on approve d plans remedy: coform to approved plans remedy: conform to approved documents or amendments
Aug 17, 2009
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Nov 12, 2007
Dob violation - resolved - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Jan 31, 2005
Dob violation - dismissed
ECB violations · 38
- Class - 1
Sec. 3303.12 temporary elevator or hoist when ever construction or demolition work reaches a height greater than 75ft. elevator shall be kept in(readiness)at at all times for fire dept use. stop all work above
Aug 16, 2010 · Penalty $1,600
Resolve - Class - 1
3308.3 failure to maintain verticle nets @ time of inspection observed verticle nets detached from guard rail system @ exp 3 on all fls remedy: maintain verticle nets
Aug 11, 2010 · Penalty $1,600
Resolve - Class - 1
Sec. 3303.12 failure to have elevator in readiness. at the time of my inspection bldg structure up 8 story approx 55 workers on site. i observed approx 5 rigging worker(dismantling) hoist & workers is working
Jul 28, 2010 · Penalty $1,600
Resolve - Class - 2
Failure to maintain adequate housekeeping per section requirements. atthe time of my inspection bldg structure upto 8 story approx 55 workeron site. i observed from the 2 fl to the 8 fl corridor & walkway block
Jul 28, 2010
Resolve - Class - 2
Sec bc 3301.1.2 misc viol: fail to comply w/nyc fire code. observed hot work in progress by using compressed gases. upon request no certificate of fitness has been provided for the operator. no fire extinguishe
Jul 15, 2010 · Penalty $400
Resolve - Class - 1
Failure to maintain adequate housekeeping per section requirements. noted at time of inspection on active job site w/interior & exterior trades working observed on all hoist area run-backplatforms on all 8 flrs
Jul 8, 2010 · Penalty $2,400
Resolve - Class - 1
Failure to institute/maintain safety equipment measures or temporary construction (no guard rails). noted @ time of inspection on active job site w/interior & exterior trades working observed on 6th flr level
Jul 8, 2010 · Penalty $2,400
Resolve - Class - 1
Sec. 3308.3. vertical safety netting requirements. noted at time of inspection on active job site w/exterior facade panels work and interiortrades working. observed on 6th flr at exp 1 set-back terrace bldg
Jul 8, 2010 · Penalty $1,600
Resolve - Class - 1
Failure to institute/maintain safety equipment measures or temporary construction (no toe boards). noted at time of inspection on active job site w/elevator shaft, mechanical systems, exterior facade panel
Jul 8, 2010 · Penalty $1,000
Resolve - Class - 2
Failure to provide approved plans at premises at time of inspection. noted at time of inspection observed (8) story nb with elevator shaft work in operation. observed wood work platforms erected at flr level
May 18, 2010 · Penalty $500
Resolve
Show 28 more ↓
- Class - 2
3303.7.fail to comply w/nyc fire code.observed a worker welding w/o a certificate of fitness from fdny.remedy:discontinue welding comply code.
Apr 29, 2010
Resolve - Class - 1
Inadequate safety manner. operation of crane/derrick/hoisting equipment in an unsafe manner. at time of inspection knuckle boom erecting window panel on 6th fl corner window. i asked the foreman to bring it dow
Apr 29, 2010 · Penalty $4,800
Resolve - Class - 1
Failure to safeguard all persons and prop affected by const operationsat time of inspection knuckleboom erecting window panel in windy conditions with no flag mentor stopping of pedestrian or vehicle traffic. b
Apr 29, 2010 · Penalty $2,400
Resolve - Class - 1
At time of inspection articulating boom crane w.o a certificate of operation. apprx 3:30pm on 4/29/2010, equipment was being used outside ofthe exception of bc 3319.3(10) in that the articulating boom crane was
Apr 29, 2010
Resolve - Class - 2
3310.8.3.fail to maintain a log as per rule promulgated by the commissioner. @ time of inspection, upon request the respondent failed to provide log for entire duration of his duty.he claimed his log is in his
Apr 29, 2010
Resolve - Class - 1
3303.7.fail to comply w/nyc fire code.observed welding operation in progress on 8th fl.no fire watch has been provided during hot work on hot work area.no caution sign has been provided.remedy:comply the fire c
Apr 29, 2010 · Penalty $1,600
Resolve - Class - 1
Failure to institute/maintain safety equipment measures-no guard rail.observed a flr opening on 9th flr (roof).no guard rail has been provided.opening size is approx 6'x6'.rem:provide guardrail
Apr 26, 2010 · Penalty $2,400
Resolve - Class - 2
Failure to safeguard all persons and property affected by const operations @ time of inspection observed the standpipe valves are located onthe open shaft of stairwell.that area is obstructed by guardrail.valve
Apr 20, 2010
Resolve - Class - 2
Sec. 28-103.8 matters not provide for no design/drawing/log book for concrete embedded safety strap. observed a concrete structure of 8 story. all flrs poured. safety strap installed on different locations.
Apr 5, 2010
Resolve - Class - 1
Failure to institute/maintain safety equipment measures - no toe boards. observed flr edges are not protected by providing toe boards on 6th to 9th flr. along elevator shaft,edge of the open flr & openings are
Apr 5, 2010 · Penalty $1,000
Resolve - Class - 1
1906.6.12 failure to secure reshores w/in 10'ft of facade from fall noted at time of insp on active job site w/ concrete from work on 7th fl in operation observed on both the fourth & fifth fl at rear of bldg s
Feb 18, 2010 · Penalty $1,600
Resolve - Class - 1
Bc3303.8 failure to provide or maintain required temporary or permanent standpipe noted at time of insp work in operation observed at both 1st & 2nd fl of bldg at expose #3 rear staircase standpipe hose valve l
Feb 18, 2010 · Penalty $1,600
Resolve - Class - 2
Sec. 3307.5.1. site watch person. noted at time of inspection 8 sty bldg under construction no watch person on site during after hours of operations. time of inspection 10:07am thru 11:00am. remedy: provide
Jan 30, 2010
Resolve - Class - 1
Failure to safeguard all persons and property affected by constructionoperations. noted at time of inspection observed construction site w/dot permit storage area on "bowery" w/stored rebar material, bending
Jan 30, 2010 · Penalty $2,400
Resolve - Class - 1
Sec. 3308.1.3. failure to provide horizontal nets. at the time of my inspection bldg structural up to 6th flr. approx 30 workers on site, no horizontal nets have been provided at the required height by code.
Jan 7, 2010 · Penalty $1,600
Resolve - Class - 1
Sec. 3306.12. failure to provide elevator in readiness. at the time ofmy inspection. approx 30 workers on site. structural up to 6th flr approx 86' in height, no elevator in readiness at the required height as
Jan 7, 2010 · Penalty $1,600
Resolve - Class - 1
Ng of concrete,no escape hatch e a escape hatch. as noted: at time ofinspection on a active construction site,concrete placement on flr 5. on flr 4 there is approx 10(culce salamaders)for temporary heating dur
Dec 22, 2009 · Penalty $1,600
Resolve - Class - 1
Fail to safeguard all persons & property affected by const operations noted:@ time of inspection on active construction site 2nd flr front sdwlk shed is being used as wrk station & setback 2nd flr rear these 2
Dec 1, 2009 · Penalty $2,400
Resolve - Class - 2
Sdwlk shed does not meet code specifications noted:@ time of inspection sidewalk shed extended adjoining property 259 bowery residential bldg material piled up on sdwlk shed 259 side obstructing egress in case
Dec 1, 2009 · Penalty $2,400
Resolve - Class - 2
Bc3307.8(misc)standard guardrail noted @ time of insp on active job site forming 3rd flr deck guardrail system not up to code wood posts arespaced greater than 8ft apart.rem:comply w/notice of violation wood pa
Dec 1, 2009
Resolve - Class - 2
Bc28-105.12.8(misc)wrk is not in accordance w/site safety plan noted on active job site.site safety indicates area front of bldg street to be storage & hoisting ofmaterial with 4'foot barriers & light every 30'
Dec 1, 2009 · Penalty $800
Resolve - Class - 2
Work does not conform to approved construction documents and/or approved amendments. noted: at time of inspection, at above active site, construction work in progress. observed fence erected in front of site at
Oct 14, 2009 · Penalty $250
Resolve - Class - 2
Sec 1905.6.3.2 misc viol: fail to remove cylinders stored for a periodup to 48 hrs. as noted: at time of inspection cylinders for strength test was molded on 9/11/09 by delta test lab. stored in curing box, wa
Sep 15, 2009
Resolve - Class - 2
Work does not conform to approved construction documents and/or approved amendments.noted:upon inspection rods secured to adjoining bldg at exposure 2/4 to secure forms for concrete foundation not on plans,and
Sep 9, 2009
Resolve - Class - 2
Provision of law 1905.6.3.2 curing box noted: at the time of inspection respondent failed to provide testing lab (delta) with curing box fofr stroage of concrete cylinders (samples) rem: provide curing box as
Aug 19, 2009 · Penalty $4,000
Resolve - Class - 2
Provision of law bc1704.4 failure to provide adequate testing in accordance with bc 1704.4 noted: at the time of inspection respondent failed to provide "b" meter c-231 astm and scale for unit measuring testing
Aug 19, 2009 · Penalty $400
Resolve - Class - 2
Misc violation failure to provide required lot line construction fenceat time of inspection contractor failed to provide required 8ft high construction fence at exp 3 rear of site. fence apprx 6ft in height.
Aug 17, 2009
Resolve - Non-hazardous
Failure to maintain building defect is missing fire rating on 5th floor ceiling.
Nov 21, 1997 · Penalty $2,500
Resolve
Complaints
- Heat/hot water
Apartment only
Jan 22, 2019 · Apt 4
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Public assembly (P7)
- Year built
- 2009
- Floors
- 8
- Residential units
- —
- Building area
- 20,200 ft²
- Lot area
- 2,500 ft²
- Zoning
- C6-1
- Community board
- 103
- Council district
- 1
- Block / lot
- 427 / 7
- Assessed value
- $3,142,800
- Landmark / historic district
- No
Questions about 257 Bowery
Who owns 257 Bowery?
The owner of record in NYC Department of City Planning PLUTO data is West-One, LLC.
Does 257 Bowery have violations?
NYC HPD has no housing violations on record for this property.
Is 257 Bowery rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 257 Bowery built?
City records list 2009 as the year it was built.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.