Owner of record: 2912 40th Ave LLC

29-14 40 Avenue is a hotel built in 2014 in Queens, 11101. The owner of record is 2912 40th Ave LLC. HPD has recorded 6 housing violations here, most recently on June 13, 2025.

HPD violations
6
DOB violations
19
ECB violations
57
HPD complaints
1

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
Last violation Jun 13, 2025

Date of the most recent HPD inspection that found a problem.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 6

  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Jun 13, 2025

    Closed — Violation dismissed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 29, 2024

    Closed — Violation dismissed
  • I

    And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.

    Nov 22, 2023

    Closed — Violation dismissed
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Mar 31, 2023

    Closed — Violation dismissed
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Mar 10, 2022

    Closed — Violation dismissed
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    Apr 20, 2021

    Closed — Violation dismissed

DOB building violations · 19

  • No report and / or late filing (facade) facade required

    Failed to file fisp cycle 9c technical report by 2/21/2024

    Feb 22, 2024

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jan 17, 2020

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jan 17, 2020

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Dec 17, 2018

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Dec 17, 2018

    Dob violation - resolved
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Mar 22, 2017

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 11, 2017

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 11, 2017

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 11, 2017

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 11, 2017

    Dob violation - dismissed
Show 9 more ↓
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 11, 2017

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Dec 19, 2016

    Vp*-violation unserved ecb- dismissed
  • Construction other optional

    C-construction other optional

    Oct 12, 2016

    Vp*-violation unserved ecb- dismissed
  • Construction other optional

    C-construction other optional

    Oct 12, 2016

    Vp*-violation unserved ecb- dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Mar 9, 2016

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Jan 4, 2016

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 31, 2014

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Feb 26, 2014

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Feb 12, 2014

    Dob violation - dismissed

ECB violations · 57

  • Class - 1

    At the time of inspection observed 6 hot water heaters installed on the 10th floor with no permits on file checked bis/dobnow no permits on file contrary to pc 106.1 - plumbing work, including water heater inst

    Sep 3, 2026 · Penalty $2,500

    Active
  • Class - 2

    Observed throughout the building, standpipe is installed above 5 feet above the finish floor, which is contrary to code bc 905.4 and nfpa 14, repair and/or replace

    Sep 2, 2025

    Resolve
  • Class - 2

    Failure to certify corrections for violation number 39125423y, file a certificate of correction

    Jul 10, 2025

    Resolve
  • Class - 2

    Failure to certify corrections for violation number 39125054h, file a certificate of correction

    Jul 10, 2025

    Resolve
  • Class - 2

    Failure to certify corrections for violation number 39125626y, file a certificate of correction

    Jul 10, 2025

    Resolve
  • Class - 2

    Failure to submit an acceptable required cycle 9c report of critical examination documenting condition of exterior wall and appurtenances required by 28-302.4 for control#918141.rem:submit acceptable required t

    Apr 8, 2025

    Resolve
  • Class - 2

    I observed on the 10th floor the mechanical room with no remote shut-down for the gas-fired units as required in mc 1006.8.1.; mc 1006.8.1, comply with code; provide remote shut-down.

    Sep 20, 2024 · Penalty $3,125

    Resolve
  • Class - 1

    I observed in the electrical closets on the 10,8,6,4,& 2 flrs and the main electrical room the installation of data wiring and equipment. as per ec 110.25 only electrical distribution equipment is permitted. al

    Sep 20, 2024 · Penalty $3,000

    Resolve
  • Class - 1

    I observed in the water meter room the failure to properly install the ground conductor for the electrical service. i noted the wire installed past the water shut off valve and the various elbows which is an im

    Sep 20, 2024 · Penalty $12,000

    Resolve
  • Class - 1

    Failure to maintain building in code-compliant manner: no fire stopping per bc 712.3 (2014 code); 27-345; bc 711.2.4 (2022 code. observed excessive hole penetrations in the electrical rooms throughout the build

    Sep 20, 2024 · Penalty $6,250

    Resolve
Show 40 more ↓
  • Class - 2

    Exit door not self-closing. observed non self closing doors throughout the basement. potential fire hazard., repair/replace door

    Sep 20, 2024 · Penalty $1,562

    Resolve
  • Class - 2

    Observed excessive combustible storage in the rpz room and also in thewater meter room., repair and/or replace

    Sep 16, 2024 · Penalty $1,562

    Resolve
  • Class - 2

    Observed two painted sprinkler heads in the mechanical room located onthe 8th floor ,1 painted sprinkle cap on the 5th floor and another painted sprinkler head in the water meter room. paint can cause the sprin

    Sep 16, 2024 · Penalty $1,562

    Resolve
  • Class - 2

    Noted no extra sprinkler heads while conducting my inspection. as 903.5 of the fire code there shall be kept available at all times in the premises a supply of at least six extra sprinkler heads., repair and/or

    Sep 16, 2024 · Penalty $1,562

    Resolve
  • Class - 1

    Observed ceiling penetration in the gas meter room located in the basement/cellar. if a fire or smoke event shout take place this gives the smoke and or fire a way to travel throughout the building., repair and

    Sep 16, 2024 · Penalty $3,125

    Resolve
  • Class - 1

    Bc3303.12 hoist/elevator at time of inspection observed that the hoist/elevator certificate of use was expired. on 08/25/17. hoist/elevator not in readiness. stop all use of elevator/hoist. stop all work above

    Aug 28, 2017 · Penalty $4,000

    Resolve
  • Class - 1

    Bc3301.2 failure to maintain at time of inspection observed wood doors installed on the elevator shaft. at stories 2,3, and4. doors were secured with a slide bolt application on the inside. slide bolts were acc

    Aug 28, 2017 · Penalty $1,600

    Resolve
  • Class - 2

    Sec. 3301 exit signs. observed no exit signs at 10th fl,8th fl,7th fl,6th fl,3rd fl & 4th floor. remedy: provide exit signs.

    Feb 23, 2017

    Resolve
  • Class - 1

    Housekeeping. observed debris consisting of sheetrock,metal & combustibles at 7th,8th & 9th fl. remedy: maintain housekeeping.

    Feb 23, 2017 · Penalty $12,000

    Resolve
  • Class - 2

    Sec. 3301.2 holes/penetrations. in stairwell a observed 6" diameter hole at 9th & 10th fl. covered but not shot down. remedy: comply w/code.

    Feb 23, 2017

    Resolve
  • Class - 1

    Bc3316.4 temporary use certificate expired at time of inspection,of 10 story new bldg under construction has temp elevator installed.device #ea1419/13 has expired on 11/12/16 with no renewal presented stop al

    Dec 19, 2016 · Penalty $1,600

    Resolve
  • Class - 2

    Bc3301.7 design required by the provision of chapt 33 at time of inspection has ( ) truck dropping deliveries off onto proposal 11 story construction site with overhead protection (makeshift) with no pe des

    Dec 19, 2016

    Resolve
  • Class - 1

    Work does not conform to approved construction documents & for approved amendments.@time of inspection of 10stry new bldg w. supported pipe scaffold needlebeams under permit #440252405,@exp #2&#4 have not been

    Oct 25, 2016 · Penalty $1,000

    Resolve
  • Class - 2

    3303.8 standpipe systems during construction,alteration,demolition.10stry new bldg under construction has temp.standpipe not painted red.no considered to be in a state of rediness.rem:painted standpipe red imme

    Oct 23, 2016 · Penalty $400

    Resolve
  • Class - 1

    Sec: bc3303.12. no elevator in readiness. noticed @ time of insp nb in progress. 10 story bldg topped off. elevator not in service on site. elevator is broken down & not operating. rem: stop all work above 6th

    Oct 12, 2016 · Penalty $1,600

    Resolve
  • Class - 1

    Sec: bc3301.7. no design drawing, noticed @ time of insp nb in progress. noticed plank platform erected on roof over stair case for workers to work on top laying block. no design drawing for platform on site. r

    Oct 12, 2016 · Penalty $1,000

    Resolve
  • Class - 2

    Sec: bc3301.7. no design drawing. noticed @ time of insp job site fence erected @ exp#1 no design for fence on site. rem: provide design for fence.

    Oct 12, 2016 · Penalty $500

    Resolve
  • Class - 1

    Failure to safe guard. notice @ time of insp debris installed on roof level have no rebar caps installed endangering workers working around rebars. workers can fall & be punctured or injured from rebar. rem: sa

    Oct 12, 2016 · Penalty $10,000

    Resolve
  • Class - 1

    Failure to perform duties of a site safety manager. noticed @ time of insp elevator not in readiness & broke down. ssm on site dominique paraison failed to report no elevator in readiness to the dept. workers o

    Oct 12, 2016 · Penalty $1,600

    Resolve
  • Class - 2

    3310.6,designated site safety manager:not provide.note:observed activejobsite 6 fl above ground steel const.site safety manager dominique paraison lic #1226 has been on site for last under site safety manager.e

    Dec 23, 2015

    Resolve
  • Class - 1

    Failure to maintain:guardrails note:observed active jobsite erected to the 6th fl level.the 6th fl (slab) poured,workers on fl installing crew block.the guardrail in place is inadequate:made up of vertical net

    Dec 14, 2015 · Penalty $1,200

    Resolve
  • Class - 1

    3309.10 no roof protection in place.note:observed active jobsite workers @6th fl install cmu block @shaft & exp#3 rear of site directly over adjacent roof where there is no protection or over head protection in

    Dec 14, 2015 · Penalty $1,600

    Resolve
  • Class - 1

    Work does not conform to approved const docs &/or approved amendments.note-observed active jobsite erected to the 6th fl observed @exp#2,3,4 horizontal safety netting not in place as per approved site safety pl

    Dec 14, 2015 · Penalty $1,000

    Resolve
  • Class - 1

    Unlawfully continued work while on notice of a stop work order.note:observed concrete pump in place at the 5th floor level.observed 6-8 men on the 5th floor preping (deck) for concrete pour.the job site is unde

    Sep 22, 2015 · Penalty $4,800

    Resolve
  • Class - 1

    Failure to maintain:guardrails.note:observed @the 5th story level working deck sections of guardrail missing @exp#4,exp#2.@the center of thefloor there is an opening approx 4 x 6 ft w/no guardrail in place,loos

    Sep 22, 2015 · Penalty $1,200

    Resolve
  • Class - 1

    Work does not conform to approved construction documents &/or approvedamendments. note: 10 sty bldg under construction bldg erected to the 5th fl steel decking is fixed in place & walkable. site safety plan

    Sep 21, 2015 · Penalty $1,000

    Resolve
  • Class - 1

    Sec. 3314.8 no guardrails-toeboards on supported scaffold. note: 10 sty bldg in progress,steel erected to 5th fl. observed at exp#2 & 3 a supported scaffold erected w/no guardrails or toeboards in place. scaffo

    Sep 21, 2015 · Penalty $1,600

    Resolve
  • Class - 1

    Failure to safeguard all persons & property affected by construction operations. note: 10 sty bldg under construction 5th fl steel erected &in place. note: stairs(metal)from 4-5th fl the pans are not filled on

    Sep 21, 2015 · Penalty $2,400

    Resolve
  • Class - 1

    Sec. 3307.6.2 areas to be protected: no overhead protection. note: 10 sty bldg under construction 5th fl steel erected & in place. observed at exp#3 no overhead protection in place for workers in egress to set

    Sep 21, 2015 · Penalty $1,600

    Resolve
  • Class - 2

    Sec. 3308.3 vertical safety netting not per code. note: 10 sty bldg under construction,5th fl erected & deck in place. at exp#1 & 3 observedinadequate netting in place floors 2-4,netting system made from 1 5/8

    Sep 21, 2015 · Penalty $400

    Resolve
  • Class - 2

    Failure to safeguard all persons & property affected by construction operations. at time of inspection observed jobsite,not active. at exp#1along 40th ave. the sidewalk in front of site is damaged cracked. note

    Jun 1, 2015 · Penalty $1,200

    Resolve
  • Class - 2

    Sec. 3307.7.1 viewing panels. not provided. at time of inspection observed jobsite. fence erected approx for 50 feet along 40 ave-no viewingpanels cut into fene making ot hard to determine if anyone was on site

    Jun 1, 2015

    Resolve
  • Class - 2

    28-104.7 submittal of construction documents a re-inspection call ceu @ 212-393-2730 as noted:@ time of insp.@ the construction site,observed @:(a)shear connection(b)beam & column base plates(c)beams base plate

    Oct 7, 2014 · Penalty $800

    Resolve
  • Class - 1

    Failure to safeguard all persons and property affected by constructionops. at time of inspection observed n.b. under construction q-decking installed to 2nd flr.no overhead protection has been provided for adjo

    Sep 29, 2014 · Penalty $2,400

    Resolve
  • Class - 1

    Work does not conform to approved structural drawings. at time of inspection observed n.b. under construction to 2nd flr steel frame and block. beams at beam pockets are not anchored or grouted as per approved

    Sep 29, 2014 · Penalty $1,000

    Resolve
  • Class - 1

    Failure to have site safety manager/coordinator present as required.@ time of insp observed active nb under cons.approx 8 workers onsite no site safety manager present.search of daily ssm logbook shows for appr

    Sep 23, 2014 · Penalty $2,400

    Resolve
  • Class - 2

    Work does not conform to approved const doc.@ time of insp observ n.b.under const.approved site safety plan shows adjoining prop @ expo 3 asvacant lot.actual field conditions show 2 story bldg & rear yard.also

    Jun 25, 2014

    Resolve
  • Class - 2

    Work does not conform to approved const documents.note @ time of insp observed a section of foundation wells between column(b) & (e) being removed.work in contrary to the apporved foundation plans on site.stop

    Jun 19, 2014

    Resolve
  • Class - 2

    3309.1,failure to protect adjoining structure.note @ time of insp bulding reacher a height of approx 14'-0" & no protection installed @ rearyard of adjacent property as required & indicated on the approved site

    Jun 19, 2014

    Resolve
  • Class - 1

    Failure to safeguard all persons and property affected by constructionoperations. job#420524524.n.b. under construction.foundation wall erected rebar stickout from foundation w/o caps. rmdy:stop all work.make

    Nov 27, 2013 · Penalty $2,400

    Resolve

Complaints

  • Unsanitary condition

    Pests

    Mar 26, 2021 · Apt 903

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Hotel (H3)
Year built
2014
Floors
10
Residential units
—
Building area
27,899 ft²
Lot area
5,550 ft²
Zoning
M1-3/R7X
Community board
401
Council district
26
Block / lot
402 / 28
Assessed value
$4,298,400
Landmark / historic district
No

HPD registration #432845, last renewed Sep 11, 2025.

Questions about 29-14 40 Avenue

Who owns 29-14 40 Avenue?

The owner of record in NYC Department of City Planning PLUTO data is 2912 40th Ave LLC.

Does 29-14 40 Avenue have violations?

Yes. NYC HPD has recorded 6 housing violations at this property.

Is 29-14 40 Avenue rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 29-14 40 Avenue built?

City records list 2014 as the year it was built.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.