62 Martense Street is a walk-up apartment building built in 2024 in Brooklyn, 11226. It has 10 residential units across 4 floors. The owner of record is 62m Realty LLC. HPD has recorded 1 housing violation here, most recently on June 16, 2025. City tax records listed 10 rent-stabilized apartments here in 2024.
- HPD violations
- 1
- DOB violations
- 4
- ECB violations
- 10
- HPD complaints
- 0
What to know
No open immediately-hazardous violations among recent records.
Date of the most recent HPD inspection that found a problem.
No balance due on recent ECB violations.
Rent stabilization
Counts come from owners' rent-stabilization filings shown on NYC Department of Finance tax bills, as extracted by JustFix. They tell you a building has stabilized apartments, not which ones.
Think your apartment is stabilized? Request its rent history from HCR (free), then check your renewal with the renewal calculator.
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 1
- ANon-hazardous
File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.
Jun 16, 2025
Closed — Violation dismissed
DOB building violations · 4
- Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Mar 20, 2024
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jan 3, 2024
Dob violation - dismissed - Construction other optional
Due to the withdrawal of the construction superintendent of record the borough commissioners office has ordered all work under job 321189423 stopped until a new superintendent is in place as per article 116 of chapter 1 of the ac, kindly contact the commissioners office at 718 802-3677 in response to this letter
Aug 23, 2022
Dob violation - dismissed - Construction other optional
Due to the withdrawal of the construction superintendent of record the borough commissioners office has ordered all work under job 321189423 stopped until a new superintendent is in place as per article 116 of chapter 1 of title 28 of the ac, kindly contact the commissioners office at 718 802-3677 in response to this letter.
Aug 23, 2022
Dob violation - dismissed
ECB violations · 10
- Class - 1
At the time of inspection i observed that construction work was continued while a notice of swo was issued on 10/02/23 and stop all work at exp.# 2 and 10 feet back from the leading edge, comp. # 3929480, viol
Feb 15, 2024 · Penalty $5,000
Resolve - Class - 1
At the time of inspection on active job site, i observed needle beam on 3rd floor at exposure 2 using for overhead & roof protection was contrary to plans, tension members not in place threading rod & clam
Oct 2, 2023 · Penalty $625
Resolve - Class - 1
Protection of windows at the of inspection on an active job site currently at 4th floor, i observed windows at exposure 2 on each floor where not protected as per code requirement and was exposed to all potent
Oct 2, 2023 · Penalty $2,500
Resolve - Class - 2
Storage on top of overhead protection at the time of inspection on an active job site currently at 4th floor. i observed at exposure 1 storage on top of overhead protection consisting of scaffolds parts and o
Oct 2, 2023
Resolve - Class - 1
At the time of my inspection of a 4 story new building construction work in progress at 3rd floor level, i observed 2 workers on site with invalid 40hrs site safety card after scanning them. this creates a haza
Aug 8, 2023 · Penalty $5,000
Resolve - Class - 1
At the time of my inspection of a 4 story new building construction work in progress at 3rd floor level, upon review of construction superintendent log book i observed that he was not signing in or out for 6 sa
Aug 8, 2023 · Penalty $2,500
Resolve - Class - 2
At the time of my inspection of a 4 story new building construction work in progress at 3rd floor level, i observed at exposure #3 construction fence was missing and there were separation between construction s
Aug 8, 2023 · Penalty $500
Resolve - Class - 1
At the time of my inspection of a 4 story new building construction work in progress at 3rd floor level, i observed at exposure # 2 and 4 that there were no overhead protection provided to protect neighbor when
Aug 8, 2023 · Penalty $1,250
Resolve - Class - 1
At the time of my inspection of a 4 story new building construction work in progress at 3 floor level, upon review of site safety plan that was at job site it was only for foundation and excavation phase. this
Aug 8, 2023 · Penalty $2,500
Resolve - Class - 1
At the time of my inspection of a 4 story new building,upon review of construction superintendent log book i observed that he was not signing in or out for 6 days site was left unsupervised and no alternate was
Aug 8, 2023 · Penalty $5,000
Resolve
Complaints
No HPD complaints in our records
Sales history
No recorded sales in our data
Building details
- Building type
- Walk-up apartment building (C1)
- Year built
- 2024
- Floors
- 4
- Residential units
- 10
- Building area
- 9,513 ft²
- Lot area
- 3,243 ft²
- Zoning
- R7A
- Community board
- 314
- Council district
- 40
- Block / lot
- 5089 / 131
- Assessed value
- $986,400
- Landmark / historic district
- No
HPD registration #391347, last renewed Sep 9, 2025.
Questions about 62 Martense Street
Who owns 62 Martense Street?
The owner of record in NYC Department of City Planning PLUTO data is 62m Realty LLC.
Does 62 Martense Street have violations?
Yes. NYC HPD has recorded 1 housing violations at this property.
Is 62 Martense Street rent stabilized?
NYC Department of Finance tax bills listed 10 rent-stabilized units here in 2024 (about 100% of its 10 apartments). To confirm a specific apartment, request its rent history from NYS Homes and Community Renewal.
When was 62 Martense Street built?
City records list 2024 as the year it was built.
How many apartments are in 62 Martense Street?
It has 10 residential units.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.