605 Hart Street is a condominium built in 2019 in Brooklyn, 11221. It has 23 residential units across 6 floors. The owner of record is Occam Suy LLC. HPD has recorded 18 housing violations here, most recently on June 16, 2026. 14 of the 18 most recent violations are still open. City tax records listed 21 rent-stabilized apartments here in 2024.
- HPD violations
- 18
- DOB violations
- 0
- ECB violations
- 10
- HPD complaints
- 17
What to know
Immediately hazardous issues among recent violations are still open.
Date of the most recent HPD inspection that found a problem.
No balance due on recent ECB violations.
Rent stabilization
Counts come from owners' rent-stabilization filings shown on NYC Department of Finance tax bills, as extracted by JustFix. They tell you a building has stabilized apartments, not which ones.
Think your apartment is stabilized? Request its rent history from HCR (free), then check your renewal with the renewal calculator.
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 18
- BHazardous
Provide security in the event of a power outage by means of an acceptable mechanical heavy duty lock and latch set at the building entrance door
Jun 16, 2026
Closed — Violation dismissed - ANon-hazardous
Post a proper notice regarding rent stabilization law, in a form approved by the commissioner, in a conspicuous location within the common area at the buildings entrance. for more information about signage requirements, please visit: https://www.nyc.gov/site/hpd/services-and-information/required-signage.page
Jun 16, 2026
Open — Nov certified on time - CImmediately hazardous
Replace or repair the self-closing doors that is missing or defective hinges at compactor closet, 7th story
Jun 16, 2026
Closed — Violation closed - CImmediately hazardous
Remove the illegal fastening double cylinder lock at vestibule door
Jun 16, 2026
Open — Nov sent out - CImmediately hazardous
Remove the illegal fastening double cylinder lock at building entrance door
Jun 16, 2026
Open — Nov sent out - CImmediately hazardous
Remove the illegal fastening unacceptable electromagnetic locking device installed at building entrance door
Jun 16, 2026
Open — Nov sent out - ANon-hazardous
§ 329, m/d law and dept. rules and regs. provide a completed certificate of inspection visits in a proper frame at or near mailboxes, bottom edge of frame between 48-62 inches above floor missing at public hall, 1st story
Sep 28, 2023
Open — Nov sent out - CImmediately hazardous
Replace or repair the self-closing doors that is missing or defective hopper door at compactor closet at public hall, 3rd story
Sep 28, 2023
Open — Nov sent out - CImmediately hazardous
Repair the leaky and/or defective faucets at bathtub in the bathroom located at apt 309, 3rd story, 2nd apartment from east at south
Oct 27, 2022 · Apt 309
Open — Nov sent out - ANon-hazardous
§ 329, m/d law and dept. rules and regs. provide a completed certificate of inspection visits in a proper frame at or near mailboxes, bottom edge of frame between 48-62 inches above floor missing at public hall, 1st story
Oct 27, 2022
Open — Nov sent out
Show 8 more ↓
- CImmediately hazardous
Replace or repair the self-closing doors that is missing or defective at compactor closet, 3rd story
Jun 26, 2022
Closed — Violation closed - CImmediately hazardous
Replace or repair the self-closing doors that is missing or defective .. at compactor closet, 2nd story
Jun 26, 2022
Closed — Violation closed - ANon-hazardous
Post and maintain a proper notice on wall of the entrance story in english and spanish on the availability of the agencys housing information guide. a sample notice can be found at www.nyc.gov/hpd. at public hall, 1st story
Jun 26, 2022
Open — Nov sent out - ANon-hazardous
Post a proper notice of smoke detector requirements, in a form approved by the commissioner, at or near the mail box .. at public hall, 1st story
Jun 26, 2022
Open — Nov sent out - ANon-hazardous
Post and maintain a proper sign on wall of entrance story showing the registration number assigned by the department and the address of the building. at public hall, 1st story
Jun 26, 2022
Open — Nov sent out - CImmediately hazardous
Post notice, in form approved by the department, stating the name and location of the person designated by the owner to have key to buildings heating system .. at public hall, 1st story
Jun 26, 2022
Open — Nov sent out - ANon-hazardous
§ 329, m/d law and dept. rules and regs. provide a completed certificate of inspection visits in a proper frame at or near mailboxes, bottom edge of frame between 48-62 inches above floor at public hall, 1st story
Jun 26, 2022
Open — Nov sent out - ANon-hazardous
Post, in a form approved by the commissioner, and maintain a notice in a common area of the building regarding the procedures that should be followed when a gas leak is suspected at public hall, 1st story
Jun 26, 2022
Open — Nov sent out
DOB building violations · 0
No DOB violations on record
ECB violations · 10
- Class - 2
3307.2.1 failure to comply with dot regulations as per 34rcny2-05 and admin code provisions 19-107,19-108 or 19-121.at time of inspection ofan 8 story new building under construction,i observed a debris contain
Oct 25, 2021 · Penalty $620
Resolve - Class - 1
Permit holder failed to maintain the daily log identifying each workerand a copy of the sst card,a temporary sst card. multiple workers working on site w/ training documentation but not recorded in daily log. r
Mar 15, 2021 · Penalty $2,500
Resolve - Class - 2
Failure to maintain/display onsite documents required by chapter 33(daily inspection logs)at time of inspection observed a sidewalk shed with a supported scaffold in place at exposure 1 and a supported scaffold
Feb 18, 2021 · Penalty $625
Resolve - Class - 1
Bc3301.6 temp platform.note:at the time of my inspection of an 8 storybldg i observed a worker standing on plywood approx. 3x3 in size placed on top of pipe,hovering over a scaffold positioned below w/no guardr
Jan 14, 2021 · Penalty $1,250
Resolve - Class - 1
Bc3310.3 site safety plan.note:at the time of my inspection of an 8 story bldg w/work in progress,i requested to see the site safety plan atwhich time no ssp was provided,to show construction safety operations.
Jan 14, 2021 · Penalty $2,500
Resolve - Class - 1
Bc3307.4.7 storage work zone.note:at the time of my inspection i observed that there was a debris dumpster,sheet rock & other construction material stored in the street.material storage must be properly enclos
Jan 14, 2021 · Penalty $625
Resolve - Class - 2
Failure to institute & maintain safety equipment measures.note:at the time of my inspection of an 8 story bldg w/work in progress,i observeda worker on a makeshift working platform approx. 3x3 in width.i observ
Jan 14, 2021 · Penalty $5,000
Resolve - Class - 2
Failure to comply with executive order.at the time of my inspection on a proposed 8 story building observed approximately 8 workers walking out of the site leaving and the competent person on site stated that h
Apr 8, 2020 · Penalty $625
Resolve - Class - 1
Permit holder failed to ensure workers received site specific safety orientation. at time of inspection on active jobsite w/workers doing foundation worker(approx 8 workers i spoke w/licensed construction super
Oct 28, 2019 · Penalty $5,000
Resolve - Class - 1
Failure to maintain record of pre-shift meeting. at time of my inspection of an active 8 sty bldg currently @ foundation stage i observed approx 8 workers plus machine operators working in bottom of foundation.
Oct 28, 2019 · Penalty $2,500
Resolve
Complaints
- Door/window
Window frame
Jun 3, 2026 · Apt PH2
Close - Door/window
Door
May 31, 2026 · Apt PH6
Close - Water leak
Heavy flow
Jul 2, 2024 · Apt 205
Close - Water leak
Heavy flow
Jul 2, 2024 · Apt 205
Close - Water leak
Heavy flow
Apr 6, 2024 · Apt 407
Close - Paint/plaster
Ceiling
Apr 6, 2024 · Apt 407
Close - Paint/plaster
Ceiling
Apr 6, 2024 · Apt 407
Close - Appliance
Electric/gas range
Sep 25, 2023 · Apt 309
Close - General
Janitor/super
Sep 25, 2023 · Apt 309
Close - Appliance
Electric/gas range
Sep 15, 2023 · Apt 309
Close
Show 7 more ↓
- Appliance
Electric/gas range
Aug 17, 2023 · Apt 309
Close - Plumbing
Bathtub/shower
Oct 24, 2022 · Apt 309
Close - Plumbing
Bathtub/shower
Sep 13, 2022 · Apt 309
Close - Water leak
Heavy flow
Jun 20, 2022 · Apt 205
Close - Electric
Outlet/switch
Jun 20, 2022 · Apt 205
Close - Electric
Lighting
Jun 20, 2022 · Apt 205
Close - General
Bell/buzzer/intercom
Jun 3, 2022 · Apt 309
Close
Sales history
No recorded sales in our data
Building details
- Building type
- Condominium (RM)
- Year built
- 2019
- Floors
- 6
- Residential units
- 23
- Building area
- 70,734 ft²
- Lot area
- 11,788 ft²
- Zoning
- R6
- Community board
- 304
- Council district
- 34
- Block / lot
- 3217 / 7501
- Assessed value
- $8,449,200
- Landmark / historic district
- No
HPD registration #390061, last renewed Oct 8, 2025.
Questions about 605 Hart Street
Who owns 605 Hart Street?
The owner of record in NYC Department of City Planning PLUTO data is Occam Suy LLC.
Does 605 Hart Street have violations?
Yes. NYC HPD has recorded 18 housing violations at this property.
Is 605 Hart Street rent stabilized?
NYC Department of Finance tax bills listed 21 rent-stabilized units here in 2024 (about 91% of its 23 apartments). To confirm a specific apartment, request its rent history from NYS Homes and Community Renewal.
When was 605 Hart Street built?
City records list 2019 as the year it was built.
How many apartments are in 605 Hart Street?
It has 23 residential units and 26 units in total.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.