roofy

21 Meserole Street

Brooklyn, NY 11206BBL 3-03040-0044Map

Owner of record: 97-101 LLC

21 Meserole Street is an elevator apartment building built in 2021 in Brooklyn, 11206. It has 24 residential units across 5 floors. The owner of record is 97-101 LLC. HPD has recorded 1 housing violation here, most recently on August 29, 2024. City tax records listed 8 rent-stabilized apartments here in 2024.

HPD violations
1
DOB violations
7
ECB violations
13
HPD complaints
1

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
Last violation Aug 29, 2024

Date of the most recent HPD inspection that found a problem.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

Rent-stabilized units in 2024
8
About 33% of the building's 24 apartments
Down from 11 in 2023

Counts come from owners' rent-stabilization filings shown on NYC Department of Finance tax bills, as extracted by JustFix. They tell you a building has stabilized apartments, not which ones.

Stabilized units by tax-bill year

Think your apartment is stabilized? Request its rent history from HCR (free), then check your renewal with the renewal calculator.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 1

  • B

    Properly repair with similar material the broken or defective 3rd story ceiling and south wall with fire retardent material at public hall

    Aug 29, 2024

    Closed — Violation dismissed

DOB building violations · 7

  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Feb 13, 2004

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    May 4, 1998

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Sep 16, 1997

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Aug 29, 1995

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Jun 1, 1994

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Aug 16, 1993

    Dob violation - active
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Jun 1, 1993

    Dob violation - dismissed

ECB violations · 13

  • Class - 2

    Adjust hoistway door access holes where needed. top landing is an illegal vestibule; conform to 2.11.6.5. missing maintenance log. defective machine room ambient temperature control.

    Jul 8, 2025 · Penalty $1,562

    Active
  • Class - 2

    At time of inspection at exposure #3 there was a construction fence inthe rear yard with expired permit since 02/21/2024, renew permit; obtain permit

    Apr 11, 2025 · Penalty $1,250

    Resolve
  • Class - 2

    At time of inspection i observed the construction fence in the rear yard wasn't maintained properly. there was gaps along the fence and at both ends. the fence was leaning on a tree that was preventing it from

    Apr 11, 2025 · Penalty $1,000

    Resolve
  • Class - 2

    Shorten hoist ropes. top landing is an illegal vestibule condition; conform to 2.11.6.5. missing fire extinguisher. missing maintenance log. missing category 1 tag. missing brake maintenance tag. missing cab mi

    Jan 24, 2024 · Penalty $312

    Resolve
  • Class - 2

    Observed 5 stories building topped off and enclosed, doing further inspection observed that the chimney of the adjacent building at exp#4 (23 meserole street brooklyn) was not extended above the highest point o

    Feb 15, 2023

    Resolve
  • Class - 2

    Work doesnt conform to approved drawing-supported scf i observed active worksite w/1worker on scf@exp3 sweeping.scf has loose planks&levels not fully planked on a2l exps.scf@exp2,3 has 3'w frame not show on pla

    Feb 22, 2022

    Resolve
  • Class - 1

    Bc3314.3.4&bc3301.6.3 loads impose&capacities i observe active worksite w/supported scf on top of sws@exp1&on top of adj property [email protected] request for loads imposed letter by pe none was provided.also roo

    Feb 22, 2022 · Penalty $1,250

    Resolve
  • Class - 1

    Permit holder failed to designate a competent person to conduct pre-shift safety meeting or to ensure that such competent person. note: at time of inspection of 5 sty nb currently at foundation level work in pr

    Jul 2, 2021 · Penalty $5,000

    Resolve
  • Class - 1

    Permit holder failed to ensure workers receive site safety orientationor refresher. note: at time of inspection of 5 sty nb currently at footing elevation,work in progress. i observed workers were performed wor

    Jul 2, 2021

    Resolve
  • Class - 1

    Construction superintendent failed to perform duties as per code. noteat time of inspection of 5 sty nb,currently at foundation level,work in progress. i observed the superintendent failed to perform his duties

    Jul 2, 2021 · Penalty $2,500

    Resolve
Show 3 more ↓
  • Class - 1

    Work does not conform to approved construction documents. at the time of inspection i observe active const on site they are doing housekeeping and support of excavation work. upon reviewing the soe plans and ss

    Jun 2, 2021 · Penalty $625

    Resolve
  • Class - 2

    Failure to comply with commissioners order contained in summons/violation #35362881p issued on 12-28-2018, and to file a certificate of correction pursuant to 28-201.1 and rcny 102-01(d)(2).an acceptibel certif

    Nov 13, 2019 · Penalty $625

    Resolve
  • Class - 3

    Failure to maintain bldg/lot in a code compliant manner. observed vacant lot w/refuse: black garbage bags,litter,plywood & dead storage of awhite van w/o license plates. also observed chain link fence leaning &

    Dec 28, 2018 · Penalty $500

    Resolve

Complaints

  • Water leak

    Slow leak

    Jan 28, 2024 · Apt 304

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Elevator apartment building (D7)
Year built
2021
Floors
5
Residential units
24
Building area
31,273 ft²
Lot area
7,500 ft²
Zoning
R6
Community board
301
Council district
34
Block / lot
3040 / 44
Assessed value
$4,141,350
Landmark / historic district
No

HPD registration #390781, last renewed Aug 24, 2025.

Questions about 21 Meserole Street

Who owns 21 Meserole Street?

The owner of record in NYC Department of City Planning PLUTO data is 97-101 LLC.

Does 21 Meserole Street have violations?

Yes. NYC HPD has recorded 1 housing violations at this property.

Is 21 Meserole Street rent stabilized?

NYC Department of Finance tax bills listed 8 rent-stabilized units here in 2024 (about 33% of its 24 apartments). To confirm a specific apartment, request its rent history from NYS Homes and Community Renewal.

When was 21 Meserole Street built?

City records list 2021 as the year it was built.

How many apartments are in 21 Meserole Street?

It has 24 residential units and 25 units in total.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.