103 North 13 Street is an office building built in 2017 in Brooklyn, 11249. The owner of record is 103 North 13th Street LLC. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
5
ECB violations
14
HPD complaints
0

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 5

  • Failure to benchmark none

    Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4

    May 2, 2024

    Dob violation - dismissed
  • Failure to benchmark none

    Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4

    Jun 2, 2021

    Dob violation - dismissed
  • Failure to submit eer none

    Failure to submit an eer per ad. code sec. 28-308.4 in 2019

    Jun 29, 2020

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Sep 22, 2017

    Dob violation - dismissed
  • Failure to benchmark none

    Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4

    May 2, 2017

    Dob violation - dismissed

ECB violations · 14

  • Class - 1

    Work does not conform to approved construction documents or approved amendments. at the time of inspection i observed window work or hoisting operations at expo#1. upon further inspection of the site safety pla

    Jun 18, 2021 · Penalty $625

    Resolve
  • Class - 1

    Work does not conform to approved plans or amendment. at the time of inspection i observed plastic barriers or yodocks in place at expo#1. upon further inspection i noticed that the plastic barricade were not f

    Jun 18, 2021 · Penalty $625

    Resolve
  • Class - 2

    Work without a permit(fdny permit expired).as noted:at time of inspection on an active construction.i observed 2 storage case of oxygen and tanks of acetylene was placed on site,and fdny permit#f0020541 has exp

    Aug 19, 2020

    Resolve
  • Class - 1

    3308.6=failure to provide horizontal safety netting system note at time of my inspection of a 8 story building at roof level approx 109 feet in height actiev construction in progress i observed missing horizont

    Jun 3, 2020

    Resolve
  • Class - 1

    Failure to provide protetction fo pedestrians at tiem of my inspection i noticed a storag ezoen next to a container of a 8 st0ry building actiev siet i observed no solid barger protecting teh pedestrian sidewal

    Jun 3, 2020

    Resolve
  • Class - 2

    Work does not conform to approved construction documents and or approved amednments at time of inspection on an actiev jobsiet i observed a needle beam on the 2nd lfoor that was inadeqaute with 7 planks under o

    Jan 13, 2020 · Penalty $2,500

    Resolve
  • Class - 2

    Work does not conform to approved construction documents and/or approved amendments-needle beams. at time of inspection on an active 8 storyalt construction site,notice needle beams at exposure#4 of the buildin

    Oct 28, 2019

    Resolve
  • Class - 2

    Design drawings for platform @time of inspection on an active 8 sty alt construction site, notice in the elevator & on site @exp#4 platform that contractor had no design drawings for which is require as per

    Oct 28, 2019

    Resolve
  • Class - 2

    Failure to safeguard all persons & property affected by coonst operations. @time of inspection on an active 8 sty alt const site, notice @exp#2 a brick party wall that went from the 1st floor to bottom of 2nd

    Oct 28, 2019 · Penalty $5,000

    Resolve
  • Class - 1

    Failure to provide adequate housekeeping. at time of inspection of active construction jobsite,i observed construction debris scattered in piles throughout the jobsite. steel rods scattered around which is a tr

    Sep 24, 2019 · Penalty $625

    Resolve
Show 4 more ↓
  • Class - 1

    Sec. 3307.5.2 failure to have flag men. noticed at time of inspection alt work in progress. noticed bob cat machine moving dirt from pile on street. bob cat backing in & out of active roadway w/o any flag men.

    Aug 1, 2017 · Penalty $1,600

    Resolve
  • Class - 2

    Sec. 3307.2.1 contrary to dot permit. noticed at time of ijnspection alt work. noticed pedstrian sidewalk at exp blocked by dirt pile approx 5feet high. dot permit shows occupancy of sidewalk but must maintain

    Aug 1, 2017 · Penalty $2,000

    Resolve
  • Class - 2

    Construction superintendent fals to maintain jobsite log at time of inspection construction super rafael rabinowitz's logbook was not properly maintained no time out noted. signature was printed from a device h

    Jul 12, 2017

    Resolve
  • Class - 1

    Sec: bc1704.1.1. missiing tri not filed. @ time of insp observed an active construction site @ foundation stage. during insp noted that special insp/statement of responsibility tri not filed & no record in the

    Dec 13, 2016 · Penalty $1,600

    Resolve

Complaints

No HPD complaints in our records

Complaint data is still being backfilled from NYC Open Data.

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Office building (O6)
Year built
2017
Floors
7
Residential units
—
Building area
62,779 ft²
Lot area
12,500 ft²
Zoning
M1-2
Community board
301
Council district
33
Block / lot
2279 / 34
Assessed value
$6,466,050
Landmark / historic district
No

Questions about 103 North 13 Street

Who owns 103 North 13 Street?

The owner of record in NYC Department of City Planning PLUTO data is 103 North 13th Street LLC.

Does 103 North 13 Street have violations?

NYC HPD has no housing violations on record for this property.

Is 103 North 13 Street rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 103 North 13 Street built?

City records list 2017 as the year it was built.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.