roofy

1189 Fulton Street

Brooklyn, NY 11216BBL 3-02000-0042Map

Owner of record: L2 Development Partners LLC

1189 Fulton Street is a vacant lot in Brooklyn, 11216. The owner of record is L2 Development Partners LLC. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
8
ECB violations
21
HPD complaints
17

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 8

  • Emergency none

    Egncy-emergency none

    Dec 23, 2009

    Dob violation - dismissed
  • Construction other optional

    Stop all work immediately until the dept.objections are addressed

    Oct 22, 2007

    Dob violation - dismissed
  • Unsafe buildings none

    Ub-unsafe buildings none

    Mar 29, 2007

    V%*-dob violation - dismissed
  • Immediate emergency anythingoptional

    Amended

    Mar 21, 2007

    Dob violation - dismissed
  • Immediate emergency anythingoptional

    Imegncy-immediate emergency anythingoptional

    Feb 16, 2007

    Dob violation - dismissed
  • Immediate emergency anythingoptional

    Imegncy-immediate emergency anythingoptional

    Jan 18, 2006

    Dob violation - dismissed
  • Immediate emergency anythingoptional

    Imegncy-immediate emergency anythingoptional

    Jan 18, 2006

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Jun 7, 2005

    Dob violation - dismissed

ECB violations · 21

  • Class - 3

    Work w/o permit. note: plywood construction fence erected t front of stalled construction site no permit. at time of inspection found ply wood insalled apprx 8' in height at stalled site at front no permit

    Nov 26, 2018

    Resolve
  • Class - 3

    Work w/o permit illegal work noted at side & front of vacant lot and appx 8ft high plywood chain link fence been erected w/o permit note viol #34826903n issued on 1/7/10 for some condition fence erected w/o per

    Jun 1, 2010 · Penalty $250

    Resolve
  • Class - 2

    Work w.o permit. noted: at the time of inspection at the above listed address bldg already removed/demo w.o any demo permit. remedy: stop all work & obtain permit, call best squad for reinspection 212-669-7043.

    Jan 7, 2010 · Penalty $4,000

    Resolve
  • Class - 2

    Work w.o permit. noted: at the time of inspection on demo job, fence erected around site w.o every permit to erect fence. dob record show no permit was issued. remedy: obtain permit.

    Jan 7, 2010 · Penalty $4,000

    Resolve
  • Class - 1

    Sec. 3303.13.2 abandoned & discontinued operations. noted: full demo of building on lot below grade level exposing adjoining rubble wall foundation with substantial damage to shared brick party wall at exposure

    Nov 24, 2009 · Penalty $8,000

    Resolve
  • Class - 1

    Sec. 3303.13.1 abandoned & discontinued operations failure to provide a solid 8 foot construction fence where construction,excavation,or demolition operations have been abandoned,discontinued,or interrupted.

    Nov 24, 2009 · Penalty $8,000

    Resolve
  • Class - 1

    Work w/o a permit. (hazardous) noted: job site fence inadequately erected around,excavated,demoed lot w/o any job filings. hazardous. remedyobtain permit or restore to prior legal condition.

    Nov 24, 2009 · Penalty $8,000

    Active
  • Class - 2

    Failure to maintain adequate housekeeping per section requirements. construction material & debris not properly stored or removed from site.noted: excessive debris throughout entire site consisting of garbage &

    Nov 24, 2009 · Penalty $4,000

    Resolve
  • Class - 1

    Sec-3309.8-failure to maintain adjoining walls exposed or breached as a result of demolition or construction operations.noted:4 story bldg demoed below grade level exposing rubble wall foundation & damaging sha

    Nov 24, 2009 · Penalty $8,000

    Resolve
  • Hazardous

    Failure to maintain. noted: no fence was observed around the sides of the lot which had a structure demolished w/materials (debris etc) fromthis process litters entire lot. remedy: maintain fence around lot.

    Feb 26, 2008 · Penalty $10,000

    Resolve
Show 11 more ↓
  • Hazardous

    Failure to adequately grade drain or protect site after demolition. noted: rubble debris from demolished structure observed throughout the lot. remedy: remove construction debris, grade site to level.

    Feb 26, 2008 · Penalty $10,000

    Resolve
  • Hazardous

    Failure to maintain note:wood fence at front is in disrepair w/inadequate supports & leaning inward 2)constr. rubble garbage & debris thru-out lot.remedy:maintain bldg property.

    Oct 10, 2007 · Penalty $2,500

    Active
  • Hazardous

    Failure to adequately grade drain or protect site aftere demolitian note: 1)rubble & debris of demo. bldg thru-out site 2)fence at front is in disrepair & leaning over 3)damage to exterior of # 1191 when struct

    Oct 10, 2007 · Penalty $5,000

    Resolve
  • Hazardous

    Work w/o permit. bldg demo down to 1st fl ceiling joist w/ exposed framing. construction fence installed at front. all done w/o permits.(no activity at site). remedy:obtain permit prior to any further work.

    Jun 21, 2007 · Penalty $2,500

    Active
  • Hazardous

    Failure to maintain bldg. note rear section of bldg from 1st fl to roof is missing, missing mortar joints & bricks at various locations, east & west sides parapet walls are leaning inwards & the entire interior

    Feb 15, 2007 · Penalty $2,500

    Resolve
  • Non-hazardous

    Work w/o a permit note: at rear of bldg excavation work done & new foundation walls approx 10'h x 25'l x 20'w erected w/o a permit. remedy: obtain a permit if feasible or obtain a permit to restore to prior

    Feb 15, 2007 · Penalty $2,500

    Active
  • Non-hazardous

    Permit posting.noted:major construction emergency work is being performed w/ the removal of entire rear wall of a 3 storied & commercial spaced structure as per appl # 302063282 issued 9/28/06,exp 5/19/08

    Dec 2, 2006 · Penalty $2,500

    Active
  • Non-hazardous

    Failure to provide contractors sign:as noted:emergency construction work is being performed @ a 3 story & comm.space w/no contractor info visible.remedy:provide contractor sign

    Dec 2, 2006 · Penalty $1,000

    Resolve
  • Hazardous

    Failure to maintain bldg. noted: premises has partially collapsed onto 1185 fulton st & rear chimney is in danger of collapse also interior fls in rear have totally collapsed. remedy: repair or remove structure

    Jan 15, 2006 · Penalty $2,500

    Resolve
  • Hazardous

    Failure to maintain building : defect is : at front between 1st & 2ndfloor level loose & defective plywood sheeting, defective & broken windows defecive & broken brick work & cement mortar joints missing at ex

    Jan 27, 2003 · Penalty $2,500

    Active
  • Hazardous

    Failure to maintain exterior building wall defect is front facade brown store is spalling s' defective in variours locations & in imminent danger of falling to sidewalk & front egress of premises below. remedy:

    Sep 11, 1996

    Resolve

Complaints

  • Heating

    Heat related

    Mar 8, 2005 · Apt 2

    Close
  • General

    Windows

    Mar 8, 2005 · Apt 2

    Close
  • Paint/plaster

    Ceiling

    Mar 8, 2005 · Apt 2

    Close
  • Construction

    Roof

    Mar 8, 2005 · Apt 2

    Close
  • Nonconst

    Vermin

    Mar 8, 2005 · Apt 2

    Close
  • Paint/plaster

    Wall

    Mar 8, 2005 · Apt 2

    Close
  • Heating

    Heat related

    Feb 12, 2005 · Apt 2

    Close
  • General

    Windows

    Feb 12, 2005 · Apt 2

    Close
  • Paint/plaster

    Ceiling

    Feb 12, 2005 · Apt 2

    Close
  • Paint/plaster

    Window/frame

    Feb 10, 2005 · Apt 2

    Close
Show 7 more ↓
  • Heating

    Heat related

    Feb 10, 2005 · Apt 2

    Close
  • Heating

    Heat related

    Jan 26, 2005 · Apt 2

    Close
  • Heating

    Heat related

    Jan 26, 2005 · Apt 1FL

    Close
  • Plumbing

    Water supply

    Jan 26, 2005 · Apt 1FL

    Close
  • Heating

    Heat related

    Jan 22, 2005 · Apt 2

    Close
  • Heating

    Heat related

    Jan 20, 2005 · Apt 2

    Close
  • Heating

    Heat related

    Jan 19, 2005 · Apt 2

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Vacant lot (V1)
Year built
—
Floors
—
Residential units
—
Building area
—
Lot area
2,120 ft²
Zoning
R7D
Community board
303
Council district
36
Block / lot
2000 / 42
Assessed value
$204,750
Landmark / historic district
No

Questions about 1189 Fulton Street

Who owns 1189 Fulton Street?

The owner of record in NYC Department of City Planning PLUTO data is L2 Development Partners LLC.

Does 1189 Fulton Street have violations?

NYC HPD has no housing violations on record for this property.

Is 1189 Fulton Street rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.