roofy

256 Skillman Street

Brooklyn, NY 11205BBL 3-01941-0029Map

Owner of record: Skillman NY LLC

256 Skillman Street is a walk-up apartment building built in 1901 in Brooklyn, 11205. It has 4 residential units across 3 floors. The owner of record is Skillman NY LLC. HPD has recorded 2 housing violations here, most recently on July 18, 2005. 2 of the 2 most recent violations are still open.

HPD violations
2
DOB violations
6
ECB violations
13
HPD complaints
9

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
Last violation Jul 18, 2005

Date of the most recent HPD inspection that found a problem.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 2

  • A

    Paint with light colored paint to the satisfaction of this department ceiling center room 1st sty apt. .

    Jul 18, 2005

    Open — Nov sent out
  • B

    Section 27-2005,2007 admon. code: fire egress defective. remove obstructing bars or gates from at least 1 window. at 1st sty. apt. 1.

    Jul 18, 2005

    Open — Nov sent out

DOB building violations · 6

  • Construction other optional

    Stop all work immediately contact borough commissioner's 718 802-3677

    May 4, 2021

    Dob violation - dismissed
  • Construction other optional

    Stop all work immediately contact boro. comm. 718 802-3677

    May 4, 2021

    Dob violation - dismissed
  • Construction other optional

    Stop all work immediately contact borough comm. office at 718 802-3677

    May 4, 2021

    Dob violation - dismissed
  • Construction other optional

    Due to fire

    Nov 6, 2020

    Dob violation - dismissed
  • Construction other optional

    Borough commissioner has ordered all work stopped under permit#3215729 81 on.12-17-18/ stop all work immediately make site contact borough comm. office at 718 802-3677 for info

    Dec 20, 2018

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Jun 27, 2003

    Dob violation - dismissed

ECB violations · 13

  • Class - 1

    At time of inspection of alt 4 story building active jobsite observed sws installed at exp1, upon request from cp to see the daily inspection log, installation letter for sws non was provided or available at ti

    Nov 3, 2022 · Penalty $625

    Resolve
  • Class - 2

    At time of inspection of alt 4 story active jobsite observed supported scaffold installed at exp1,3,4 upon review the design drawings for supported scaffold, observed the tieback for supported scaffold does not

    Nov 3, 2022

    Resolve
  • Class - 2

    At time of inspection of alt 4 story building active jobsite observed jersey barriers installed at exp1, observed jersey barriers obstructed sidewalk and not achieved a clear path, free of obstruction, at least

    Nov 3, 2022

    Resolve
  • Class - 2

    At time of inspection of alt 4 story building active jobsite observed excessive debris on jobsite consists of combustible materials plastic bags, cartoon boxes and other debris this condition creates hazard of

    Nov 3, 2022

    Resolve
  • Class - 2

    Sidewalk shed does not meet code specification note:at the time of my inspection of a 3 story building i observed sidewalk shed at exp#1 with the following objections exposed bolts and inoperable light bulbs.th

    Dec 8, 2021

    Resolve
  • Class - 2

    Jobsite fence not constructed or maintained pursuant to subsection.at the time of my inspection i observed a temporary construction fence atexposure#1 inadequately maintained. i noted panels that were missing,l

    Mar 16, 2020 · Penalty $2,500

    Resolve
  • Class - 2

    Failure to maintain building in code compliant manner at time of my inspection i observed unenclosed perimeters at all window openings with material that was not installed in a code compliant manner allowed for

    Mar 16, 2020 · Penalty $1,562

    Resolve
  • Class - 1

    Bc 3306.5.a deficient drawings bc 3306.5.1 mandates demoltion drawingto have planand sections, details clealry showing sequence, estent andmeans and methods as wella s bracing and shoring with sequence throug

    Mar 18, 2019 · Penalty $2,530

    Resolve
  • Class - 1

    28-104.7.1 construction documents submittal is incomplete and not of sufficient clarity to indicate the location and entire nature in detail of the proposed work. the respondent who signed and sealed the projec

    Sep 6, 2018 · Penalty $625

    Resolve
  • Class - 1

    Bc3306.5.1 failure to provide adequate construction document; deficient demolition drawings. the respondent who signed and sealed the demolition drawings (dm-001-00) failed to ensure that the submittal document

    Sep 6, 2018 · Penalty $2,500

    Resolve
Show 3 more ↓
  • Class - 2

    Bc3309.8.failure to protect or adequately protect adjoining propertiesduring construction.at time of inspection it was osberved that the contractor removed bricks from the party wall at exp #2 and #4 compromisi

    Sep 4, 2018

    Resolve
  • Class - 2

    Failure to provide approved/accepted construction documents at job site at time of inspection.at the time of inspection alt i active jobsitei observed that upon request dd for:staircase,shoring branching suppor

    Sep 4, 2018 · Penalty $250

    Resolve
  • Class - 2

    Construction superintendent failed to perform duties as per code.at the time of inspection construction super ofier popovich was not observed on site and no competent person on site.fire rating in party wall co

    Sep 4, 2018 · Penalty $5,000

    Resolve

Complaints

  • Plumbing

    Shower-stall

    Jul 28, 2004 · Apt 1

    Close
  • General

    Cabinet

    Jul 28, 2004 · Apt 1

    Close
  • Heating

    Heat related

    Jan 8, 2004 · Apt 2

    Close
  • Heating

    Heat related

    Jan 6, 2004 · Apt 1 FL

    Close
  • Heating

    Heat related

    Jan 6, 2004 · Apt ENT

    Close
  • Plumbing

    Water supply

    Dec 26, 2003 · Apt 1 FL

    Close
  • Heating

    Heat related

    Mar 17, 2003 · Apt 1FL

    Close
  • Plumbing

    Water supply

    Mar 17, 2003 · Apt 1FL

    Close
  • Heating

    Heat related

    Mar 14, 2003 · Apt 1FL

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Walk-up apartment building (C3)
Year built
1901
Floors
3
Residential units
4
Building area
3,600 ft²
Lot area
2,040 ft²
Zoning
R6B
Community board
303
Council district
36
Block / lot
1941 / 29
Assessed value
$253,350
Landmark / historic district
No

Questions about 256 Skillman Street

Who owns 256 Skillman Street?

The owner of record in NYC Department of City Planning PLUTO data is Skillman NY LLC.

Does 256 Skillman Street have violations?

Yes. NYC HPD has recorded 2 housing violations at this property.

Is 256 Skillman Street rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 256 Skillman Street built?

City records list 1901 as the year it was built.

How many apartments are in 256 Skillman Street?

It has 4 residential units.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.