roofy

786 Park Place

Brooklyn, NY 11216BBL 3-01240-0020Map

Owner of record: Aom 786 Pp LLC

786 Park Place is an elevator apartment building built in 2017 in Brooklyn, 11216. It has 6 residential units across 6 floors. The owner of record is Aom 786 Pp LLC. HPD has recorded 1 housing violation here, most recently on November 7, 2022. 1 of the 1 most recent violations are still open.

HPD violations
1
DOB violations
4
ECB violations
11
HPD complaints
1

What to know

Concern
1 open Class C

Immediately hazardous issues among recent violations are still open.

Good
Last violation Nov 7, 2022

Date of the most recent HPD inspection that found a problem.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 1

  • C

    Abate the infestation consisting of rodents rats, building front yard

    Nov 7, 2022

    Open — Nov sent out

DOB building violations · 4

  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 27, 2017

    Dob violation - active
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 27, 2017

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 27, 2017

    Dob violation - active
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 27, 2017

    Dob violation - dismissed

ECB violations · 11

  • Class - 2

    At time of inspection observed temp construction fence in place at exposure-1 perimeter. dept records indicate no active applicable permit filed for installation as per code 28-105.1, obtain temporary construct

    Apr 18, 2025 · Penalty $1,250

    Resolve
  • Class - 1

    Failure to maintain property in code compliant manner with unpermitted temp construction fence in place at exposure-1 perimeter in a state of disrepair. multiple sheets of damaged/unsecured plywood hanging loos

    Apr 18, 2025 · Penalty $625

    Resolve
  • Class - 2

    Pedestrian protetcion does not meet code specification at time of inspection i observed a sidewlak shed instaled at exposure #1 with no lighting method installed this is a conflict with 3307.6.4.8 this will res

    Sep 4, 2019 · Penalty $2,400

    Resolve
  • Class - 1

    Failed to have construction superintendent or a construction superintendent present at site as required. note: at the time of my inspection of a 6 sty bldg at 4th fl level,construction work in progress. upon

    Oct 2, 2017

    Resolve
  • Class - 2

    Failure to institute & maintain safety equipment measures & temporary construction. note: at the time of my inspection construction work in progress of a 6th sty bldg at 4th fl level. i observed a worker workin

    Oct 2, 2017

    Resolve
  • Class - 2

    Sec. 3301-02(d) logs. note: at the time of my inspection of a 6 sty bldg at 4th fl level,construction work in progress. upon request for designated construction superintendent logs to verify compliance & presen

    Oct 2, 2017 · Penalty $400

    Active
  • Class - 1

    Construction superintendent failed to perform duties as per rule. the following hazardous conditions were observed & stop work order was issued to this construction site on this date.1)no approved plans on site

    Oct 2, 2017 · Penalty $10,000

    Active
  • Class - 2

    Failed to provide approved/accepted plan at job site at time of inspection. note: at the time of my inspection of a 6 sty bldg at 4th fl level,construction work in progress. upon request for aproved & accepted

    Oct 2, 2017 · Penalty $250

    Active
  • Class - 1

    Work w/o a permit. note: at the time of my inspection of a 6 sty new bldg at 4th fl level,construction work in progress. review of dept records reveal that new bldg permit#32116608z was not issued for construct

    Oct 2, 2017 · Penalty $1,600

    Active
  • Class - 1

    Sidewalk shed where required. note: at the time of my inspection of a 6 sty bldg at 4th fl level,approx 30feet above sidewalk at property line construction wokr in progress. i observed that there were no sidewa

    Oct 2, 2017 · Penalty $4,800

    Active
Show 1 more ↓
  • Class - 2

    Sec: bc3307.3.2. failure to provide construction fence @ exp#2 & 3. @ time of insp observed & active construction site w/ pile drilling work in progress. missing construction fence as required by code. rem: com

    Feb 22, 2017

    Resolve

Complaints

  • Unsanitary condition

    Pests

    Oct 24, 2022 · Apt EVERYW

    Close

Sales history

DatePriceTypeUnits
Jan 23, 2026$950,000Rentals - elevator apartments6

Building details

Building type
Elevator apartment building (D1)
Year built
2017
Floors
6
Residential units
6
Building area
5,304 ft²
Lot area
1,657 ft²
Zoning
R6A
Community board
308
Council district
36
Block / lot
1240 / 20
Assessed value
$211,500
Landmark / historic district
No

Questions about 786 Park Place

Who owns 786 Park Place?

The owner of record in NYC Department of City Planning PLUTO data is Aom 786 Pp LLC.

Does 786 Park Place have violations?

Yes. NYC HPD has recorded 1 housing violations at this property.

Is 786 Park Place rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 786 Park Place built?

City records list 2017 as the year it was built.

How many apartments are in 786 Park Place?

It has 6 residential units.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.