roofy

2413 Third Avenue

Bronx, NY 10451BBL 2-02319-0109Map

Owner of record: Rxr 2413 Third Owner LLC

2413 Third Avenue is an elevator apartment building built in 2021 in Bronx, 10451. It has 200 residential units across 27 floors. The owner of record is Rxr 2413 Third Owner LLC. HPD has recorded 27 housing violations here, most recently on October 6, 2026. 27 of the 27 most recent violations are still open. City tax records listed 175 rent-stabilized apartments here in 2024.

HPD violations
27
DOB violations
12
ECB violations
37
HPD complaints
19

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Watch
Last violation Oct 6, 2026

Date of the most recent HPD inspection that found a problem.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

Rent-stabilized units in 2024
175
About 88% of the building's 200 apartments
Down from 179 in 2023

Counts come from owners' rent-stabilization filings shown on NYC Department of Finance tax bills, as extracted by JustFix. They tell you a building has stabilized apartments, not which ones.

Stabilized units by tax-bill year

Think your apartment is stabilized? Request its rent history from HCR (free), then check your renewal with the renewal calculator.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 27

  • A

    Post and maintain a proper sign on wall of entrance story showing the registration number assigned by the department and the address of the building., 1st story

    Oct 6, 2026

    Open — Nov sent out
  • A

    Post, in a form approved by the commissioner, and maintain a notice in a common area of the building regarding the procedures that should be followed when a gas leak is suspected, 1st story

    Oct 6, 2026

    Open — Nov sent out
  • A

    Post sign on wall of entrance story bearing name, address including apartment number if any, and telephone number of superintendent, janitor or housekeeper., 1st story

    Oct 6, 2026

    Open — Nov sent out
  • A

    Post a proper notice of smoke detector requirements, in a form approved by the commissioner, at or near the mailbox, 1st story

    Oct 6, 2026

    Open — Nov sent out
  • A

    Post a proper notice of carbon monoxide detecting device requirements, in a form approved by commissioner, in a common area of a class a multiple dwelling near inspection certificate or provide notice to tenants in private dwellings

    Oct 6, 2026

    Open — Nov sent out
  • A

    § 329, m/d law and dept. rules and regs. provide a completed certificate of inspection visits in a proper frame at or near mailboxes, bottom edge of frame between 48-62 inches above floor, 1st story

    Oct 6, 2026

    Open — Nov sent out
  • A

    Post and maintain a proper notice on wall of the entrance story in english and spanish on the availability of the agencys housing information guide. a sample notice can be found at www.nyc.gov/hpd., 1st story

    Oct 6, 2026

    Open — Nov sent out
  • A

    File annual bedbug report in accordance with hpd rule as described on the back of this notice of violation or as described on hpds website, www.nyc.gov\hpd, search bed bugs.

    May 11, 2026

    Open — Nov sent out
  • B

    Repair, replace or provide an approved and operational smoke detecting device, installed in accordance with department of buildings rules and regulations deffective in the entire apartment located at apt 609, 6th story, 1st apartment from north at east

    Mar 4, 2026 · Apt 609

    Open — Nov sent out
  • B

    Repair, replace or provide an approved and operational carbon monoxide detecting device, installed in accordance with applicable law and rules deffective in the entire apartment located at apt 609, 6th story, 1st apartment from north at east

    Mar 4, 2026 · Apt 609

    Open — Nov sent out
Show 17 more ↓
  • B

    Properly repair or replace the broken or defective ptec heating system unit in the 3rd room from east located at apt 609, 6th story, 1st apartment from north at east

    Mar 4, 2026 · Apt 609

    Open — Nov sent out
  • B

    Properly repair or replace the broken or defective ptec heating system unit in the 1st room from east located at apt 609, 6th story, 1st apartment from north at east

    Mar 4, 2026 · Apt 609

    Open — Nov sent out
  • B

    Properly repair or replace the broken or defective ptec heating system unit in the 2nd room from east located at apt 609, 6th story, 1st apartment from north at east

    Mar 4, 2026 · Apt 609

    Open — Nov sent out
  • B

    Properly repair with similar material the broken or defective wood laminate floor in the 1st room from north at west located at apt 705, 7th story, 1st apartment from west at north

    Mar 1, 2026 · Apt 705

    Open — Nov sent out
  • B

    Properly repair with similar material the broken or defective wood laminate floor in the foyer located at apt 705, 7th story, 1st apartment from west at north

    Mar 1, 2026 · Apt 705

    Open — Nov sent out
  • B

    Properly repair with similar material the broken or defective wood laminate floor in the 1st room from north at east located at apt 705, 7th story, 1st apartment from west at north

    Mar 1, 2026 · Apt 705

    Open — Nov sent out
  • B

    Repair the broken or defective plastered surfaces and paint in a uniform color all walls in the 1st room from north at east located at apt 705, 7th story, 1st apartment from west at north

    Mar 1, 2026 · Apt 705

    Open — Nov sent out
  • B

    Repair the broken or defective plastered surfaces and paint in a uniform color the east wall, south wall, and the west wall in the 1st room from north at west located at apt 705, 7th story, 1st apartment from west at north

    Mar 1, 2026 · Apt 705

    Open — Nov sent out
  • B

    Repair the broken or defective plastered surfaces and paint in a uniform color all walls in the closet in the 1st room from north at west located at apt 705, 7th story, 1st apartment from west at north

    Mar 1, 2026 · Apt 705

    Open — Nov sent out
  • B

    Properly repair with similar material the broken or defective wood laminate floor in the closet in the 1st room from north at west located at apt 705, 7th story, 1st apartment from west at north

    Mar 1, 2026 · Apt 705

    Open — Nov sent out
  • B

    Properly repair with similar material the broken or defective wood floor in the kitchen located at apt 705, 7th story, 1st apartment from west at north

    Mar 1, 2026 · Apt 705

    Open — Nov sent out
  • B

    Repair the broken or defective plastered surfaces and paint in a uniform color the west wall in the kitchen located at apt 705, 7th story, 1st apartment from west at north

    Mar 1, 2026 · Apt 705

    Open — Nov sent out
  • B

    Properly repair with similar material the broken or defective wood laminate floor in the closet in the kitchen located at apt 705, 7th story, 1st apartment from west at north

    Mar 1, 2026 · Apt 705

    Open — Nov sent out
  • B

    Repair the broken or defective plastered surfaces and paint in a uniform color all walls in the closet in the kitchen located at apt 705, 7th story, 1st apartment from west at north

    Mar 1, 2026 · Apt 705

    Open — Nov sent out
  • B

    Repair the broken or defective plastered surfaces and paint in a uniform color the north wall, south wall, and the west wall in the foyer located at apt 705, 7th story, 1st apartment from west at north

    Mar 1, 2026 · Apt 705

    Open — Nov sent out
  • A

    Paint with light colored paint to the satisfaction of this department the north wall, east wall, and the west wall at public hall, 7th story

    Mar 1, 2026

    Open — Nov sent out
  • B

    Properly repair with similar material the broken or defective fire retardant material at the north wall, east wall, and the west wall at public hall, 7th story

    Mar 1, 2026

    Open — Nov sent out

DOB building violations · 12

  • Elevator annual inspection / test elevatorrequired

    Violation issued to elevator-failure to file category 1 2016 inspection/test

    Sep 15, 2017

    Dob violation - dismissed
  • Elevator affirmation of correction elevatorrequired

    Vio issued to elevator - fail to correct defects on 2015 cat 1 insp/tst

    Jan 3, 2017

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jan 29, 2016

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jan 8, 2015

    Dob violation - resolved
  • Elevator annual inspection / test elevatorrequired

    Violation issued to elevator-failure to file category 1 2012 inspection/test

    Mar 31, 2014

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jan 16, 2014

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Sep 25, 2009

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Dec 14, 2007

    Dob violation - resolved
  • Elevator elevatoroptional

    Ll1081-local law 10/81 - elevator elevatoroptional

    Apr 2, 2007

    Dob violation - dismissed
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Feb 6, 2007

    Dob violation - resolved
Show 2 more ↓
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Oct 14, 2004

    Dob violation - resolved
  • Construction other optional

    C-construction other optional

    Jan 24, 2001

    Dob violation - dismissed

ECB violations · 37

  • Class - 2

    At time of inspection, observed at exp. 1 on left side on adjacent property a section of sidewalk shed that was removed without building department approval. on site safety plan this section is label as sidewal

    Sep 8, 2023 · Penalty $1,250

    Resolve
  • Class - 1

    Observed suspended scaffolds at all exposures of jobsite on roof.review of approved cd5 show tie backs to l angles to be installed to concrete slab on ground, l angles are installed on ceiling of bulk head and

    Mar 29, 2023 · Penalty $625

    Resolve
  • Class - 1

    Observed suspended scaffolds on all exposures of jobsite on roof and 24 floor of jobsite. upon request for the manufactures specs for the outrigger beams and a frames in use, none were provided.*stop all use of

    Mar 29, 2023 · Penalty $625

    Resolve
  • Class - 2

    27 story nb active site. i observed multipoint suspended scaffold attached to building with wire rope and outriggers in place at exp#1,2. permit#x00676759 with masonary work incomplete.observed lifeline anchora

    Jan 30, 2023 · Penalty $625

    Resolve
  • Class - 2

    27 nb active site. observed heavy construction materials (bricks, steel, posts)/debris stored on top of shed. as per bc 3307.6.5.4, no items shall be stored or be placed upon a sidewalk shed. observed no parape

    Jan 30, 2023

    Resolve
  • Class - 1

    A 27-story nb active site. observed suspended scaffold in use at all expos. observed 2in foam underneath mudsill base level, lifelines/wirerope on structural members unprotected, turnbuckles on tiebacks all con

    Jan 30, 2023 · Penalty $625

    Resolve
  • Class - 2

    27 story nb active site.observed temporary construction in place at exp#2.overhead protection with supported scaffolding on top overhead protection had bricks/heavy construction materials.upon request to contra

    Jan 30, 2023 · Penalty $1,280

    Resolve
  • Class - 2

    27 story nb active site. observed inadequate housekeeping in multiple areas on-site. workers walking on top of sheetrock debris in close proximately and wires on floor creating a potential tripping hazard. cons

    Jan 30, 2023 · Penalty $1,280

    Resolve
  • Class - 1

    A 27 story nb active. observed sidewalk shed in place at exp#1 with supported scaffolding on top approximately 70 ft at exp#2 in use. further inspection it was observed that shed was missing guardrails also sca

    Jan 30, 2023 · Penalty $5,030

    Resolve
  • Class - 1

    A 27-story nb active site. observed workers on suspended scaffold at all expos. observed angled tiebacks at roof level for lifelines and scaffold. upon request for pull test for safe anchorage to ensure anchora

    Jan 30, 2023 · Penalty $625

    Resolve
Show 27 more ↓
  • Class - 1

    Failure to safeguard person and property (ies) - partial stop work order to all windows installation / operation due to a panal approx 2' x 5' operable window pane fell off the 27th floor to adjoining property

    Dec 12, 2022 · Penalty $25,000

    Resolve
  • Class - 2

    Failure to institute safety measure: carpenter caring 8ft long 4 metal flat stocks himself from 4th to 3rd floor, tripped on steps & fell to 3rd floor. went hospital by ambulance. long metal flat stocks suppose

    Nov 14, 2022 · Penalty $5,000

    Resolve
  • Class - 1

    Failure to notify department of incident that resulted in fatality or injury.note:worker carrying eight foot long piece of metal form work tripped on confuits experienced shoulder pain taken to hospital.as per

    Oct 20, 2022 · Penalty $5,000

    Resolve
  • Class - 1

    Note: worker tripped with electrical conduit cable lay down on floor at lobby, when caring metal form, working on 27th floor. went to hospital by ambulance. also observed accident evidence related materials 8ft

    Sep 22, 2022 · Penalty $6,250

    Resolve
  • Class - 1

    Failure to institute safety measure: worker tripped with electrical conduit cable lay down on floor(3303.4.1.2) at lobby, when caring metal form, working on 27th floor. went to hospital by ambulance with should

    Sep 22, 2022 · Penalty $10,030

    Resolve
  • Class - 1

    Note: worker tripped with electrical conduit cable lay down on floor at lobby, when caring metal form, working on 27th floor. also observed toe board missing on guard rail system at 6th floor exp1,2,4, creating

    Sep 22, 2022 · Penalty $12,500

    Resolve
  • Class - 1

    Note: worker tripped with electrical conduit cable lay down on floor at lobby, when caring metal form, working on 27th floor. also observed rebar caps missing at roof level creating impale hazard when people( 1

    Sep 22, 2022 · Penalty $2,500

    Resolve
  • Class - 2

    Note: worker tripped with electrical conduit cable lay down on floor at lobby, when caring metal form, working on 27th floor. also observed holes around ducting, around pipes on several floor area creating debr

    Sep 22, 2022 · Penalty $5,030

    Resolve
  • Class - 1

    Respondent permitted tower crane cn#1045/20 cd#5554 to perfrom construction activities without ensuring that climbing frame was lowered to just above tie-in #1 as per phase 2 drawing # tc-003.01. crane climbed

    Jul 19, 2022 · Penalty $6,250

    Resolve
  • Class - 1

    Respondent(master rigger) climbed crane to phase 2 on 06/15/22 but did not lower climbing frame to just above tie-in #1 as per approved drawing #tc-003.01 approved 06/10/22., conform work to approved constructi

    Jul 19, 2022 · Penalty $2,500

    Resolve
  • Class - 1

    Respondent signed cd8 stating that tower crane cn#1045/20 cd#5554 was in its amended phase 2, (lowered to just above tie-in #1 as per phase 2 drawing # tc-003.01.) but it was not. crane climbed 06/15/22. phase

    Jul 19, 2022 · Penalty $2,500

    Resolve
  • Class - 1

    Respondent used tower crane cn#1045/20 cd#5554 to perfrom construction activities without ensuring that climbing frame was lowered to just above tie-in #1 as per phase 2 drawing # tc-003.01. crane climbed 06/15

    Jul 19, 2022 · Penalty $2,500

    Resolve
  • Class - 1

    Work does not conform to approved construction documents and/or approved amendments-work contrary to site safety plan ssp-120.00 noted:at time of inspection of proposed 27 story nb at 6 floor level active site

    May 10, 2022 · Penalty $2,500

    Resolve
  • Class - 1

    Failure to maintain/institute safety measures or temporary construction or equipment-no toe boards at 5th floor exp #1.noted:at time of inspection of proposed 27 story nb active jobsite at 6 floor level observe

    May 10, 2022 · Penalty $5,030

    Resolve
  • Class - 2

    Failure to maintain/display onsite docs required by bcch33-no dob approved structural plans onsite noted:atoi of proposed 27stynb active jobsite@6fl level.upon request for dob approved plans for structural.none

    May 10, 2022

    Resolve
  • Class - 2

    Failure to maintain/display onsite docs required by bcch33-no manufacturer specs/insp log for fall arrest systems also no pe installation letter for bigfoot system noted:atoi of proposed 27stynb active jobsite.

    May 10, 2022

    Resolve
  • Class - 2

    Work doesnt conform to approved const docs &or approved amendments-work contrary to pe drawing&ssps noted:atoi of proposed 27stynb active site.workers on 6fl installing formwork for concrete pour.i observed wor

    May 10, 2022

    Resolve
  • Class - 1

    Bc3301.2 failure to institute/maintain safety measures onsite-no rebarcaps/inadequate control access zones/all persons to protect onsite noted:atoi of proposed 27stynb active site@6fl level performing concrete

    May 10, 2022 · Penalty $6,250

    Resolve
  • Class - 1

    Unsafe storage of materials during costruction or demolition.noted:at time of inspection of proposed 27 story nb active jobsite observed on 5th floor at exp #1 metal reshoring stored aprox 4 ft next to leading

    May 10, 2022 · Penalty $6,250

    Resolve
  • Class - 1

    Work doesnt conform to approved const docs &or approved amendments-no bridging for formwork reshores on plans/details noted:atoi of proposed27stynb 6fl active jobsite.i observed@1,2fl reshores (vert) 3 over hor

    May 10, 2022 · Penalty $2,500

    Resolve
  • Class - 1

    Respondent permitted tower crane cn#1045/20 cd#5555 to perform construction activities without ensuring faa light was operational; no faa, comply with code; add fix or maintain light

    Mar 3, 2022 · Penalty $2,500

    Resolve
  • Class - 1

    Tower crane cn#1045/20 cd#5554 erected and in operation respondent did not ensure faa light was operational; ., comply with code; fix faa light

    Mar 3, 2022 · Penalty $2,530

    Resolve
  • Class - 1

    Sec. 28-401.4 illegally engaging in any business or occupation w/o a license or other authorization(license expired). at time of my inspection,i observed a active jobsite w/approx 7 workers onsite performing

    Oct 18, 2021 · Penalty $5,000

    Resolve
  • Class - 1

    Failure to maintain onsite documents required by bc chapter 33. note: at time of my inspection at a active jobsite at excavation phase. i requested from ssm(s. mckay)vibration monotoring log book. as per ssm th

    Oct 18, 2021

    Resolve
  • Class - 1

    Work does not conforms to approved construction documents &/or approved amendments.at the time of inspection i observed 5 stories bldg,demolition in progress.going through the site safety plan.it calls for the

    Jun 16, 2021 · Penalty $6,250

    Resolve
  • Class - 1

    Bc3314.8 guardrail system & debris netting- inadequate scaffolding guardrails.at the time of inspection i observed demolition of 5 stories bldg.walking around the bldg i saw supported scaffolding on exp.#2,3,4

    Jun 16, 2021 · Penalty $6,250

    Resolve
  • Class - 1

    Foot bridge/ramp/walkway w/inadequate guardrails.at the time of inspection i observed demolition of 5 stories bldg.walking around the job i saw ramp on exp.#2 connecting the scaffolding & 2nd fl w/out the guard

    Jun 16, 2021 · Penalty $6,250

    Resolve

Complaints

  • Paint/plaster

    Wall

    Oct 15, 2026 · Apt 904

    Open
  • Water leak

    Damp spot

    Oct 15, 2026 · Apt 904

    Open
  • Water leak

    Heavy flow

    Sep 28, 2026 · Apt 1007

    Open
  • Plumbing

    Bathtub/shower

    Sep 28, 2026 · Apt 1007

    Open
  • Paint/plaster

    Wall

    Jul 25, 2026 · Apt 904

    Close
  • Water leak

    Damp spot

    Jul 25, 2026 · Apt 904

    Close
  • Heat/hot water

    Entire building

    May 6, 2026 · Apt BLDG

    Close
  • Heat/hot water

    Apartment only

    May 6, 2026 · Apt 20FLOO

    Close
  • Heat/hot water

    Apartment only

    Apr 30, 2026 · Apt 2008

    Close
  • Heat/hot water

    Apartment only

    Mar 2, 2026 · Apt 609

    Close
Show 9 more ↓
  • Paint/plaster

    Ceiling

    Feb 28, 2026 · Apt 705

    Close
  • Heat/hot water

    Apartment only

    Jan 29, 2026 · Apt 806

    Close
  • Heat/hot water

    Apartment only

    Jan 22, 2026 · Apt 508

    Close
  • Heat/hot water

    Entire building

    Dec 13, 2025 · Apt BLDG

    Close
  • Unsanitary condition

    Pests

    Jun 20, 2025 · Apt 806

    Close
  • Plumbing

    Bathtub/shower

    Jun 2, 2025 · Apt 902

    Close
  • Flooring/stairs

    Floor

    Jun 27, 2024 · Apt 1503

    Close
  • Paint/plaster

    Wall

    Jun 27, 2024 · Apt 1503

    Close
  • Unsanitary condition

    Mold

    Jun 27, 2024 · Apt 1503

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Elevator apartment building (D7)
Year built
2021
Floors
27
Residential units
200
Building area
218,695 ft²
Lot area
27,730 ft²
Zoning
M1-3/R8
Community board
201
Council district
8
Block / lot
2319 / 109
Assessed value
$16,187,400
Landmark / historic district
No

HPD registration #228793, last renewed Sep 19, 2025.

Questions about 2413 Third Avenue

Who owns 2413 Third Avenue?

The owner of record in NYC Department of City Planning PLUTO data is Rxr 2413 Third Owner LLC.

Does 2413 Third Avenue have violations?

Yes. NYC HPD has recorded 27 housing violations at this property.

Is 2413 Third Avenue rent stabilized?

NYC Department of Finance tax bills listed 175 rent-stabilized units here in 2024 (about 88% of its 200 apartments). To confirm a specific apartment, request its rent history from NYS Homes and Community Renewal.

When was 2413 Third Avenue built?

City records list 2021 as the year it was built.

How many apartments are in 2413 Third Avenue?

It has 200 residential units and 201 units in total.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.