2480 Broadway is an elevator apartment building built in 1922 in Manhattan, 10025. It has 146 residential units across 15 floors. The owner of record is 215 Equities Corp. HPD has recorded 8 housing violations here, most recently on October 5, 2018. City tax records listed 6 rent-stabilized apartments here in 2024.
- HPD violations
- 8
- DOB violations
- 75
- ECB violations
- 21
- HPD complaints
- 42
What to know
No open immediately-hazardous violations among recent records.
Date of the most recent HPD inspection that found a problem.
No balance due on recent ECB violations.
Rent stabilization
Counts come from owners' rent-stabilization filings shown on NYC Department of Finance tax bills, as extracted by JustFix. They tell you a building has stabilized apartments, not which ones.
Think your apartment is stabilized? Request its rent history from HCR (free), then check your renewal with the renewal calculator.
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 8
- IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Oct 5, 2018
Closed — Violation dismissed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Nov 6, 2017
Closed — Violation dismissed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Oct 24, 2016
Closed — Violation dismissed - CImmediately hazardous
Provide adequate supply of cold water for the fixtures ,low water pressure in the bathroom located at apt 15h, 14th story, 1st apartment from east at south
Mar 31, 2016 · Apt 15H
Closed — Violation closed - CImmediately hazardous
Provide adequate supply of hot water for the fixtures ,low water presure at all fixtures in the bathroom located at apt 15h, 14th story, 1st apartment from east at south
Mar 31, 2016 · Apt 15H
Closed — Violation closed - CImmediately hazardous
Provide adequate supply of cold water for the fixtures ,low water pressure in the kitchen located at apt 15h, 14th story, 1st apartment from east at south
Mar 31, 2016 · Apt 15H
Closed — Violation closed - CImmediately hazardous
Provide adequate supply of hot water for the fixtures ,low water pressure in the kitchen located at apt 15h, 14th story, 1st apartment from east at south
Mar 31, 2016 · Apt 15H
Closed — Violation closed - IInformation / order
And is therefore subject to civil penalties, prohibited from certifying violations, and denied the right to recover possession of premises for nonpayment of rent until a valid registration statement is filed.
Oct 1, 2015
Closed — Violation dismissed
DOB building violations · 75
- Elevator elevatorrequired
E-elevator elevatorrequired
Oct 20, 2021
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Oct 20, 2021
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Oct 20, 2021
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Oct 20, 2021
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jul 20, 2020
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jul 20, 2020
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jul 20, 2020
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jul 20, 2020
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jun 19, 2018
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jun 19, 2018
Dob violation - resolved
Show 40 more ↓
- Construction other optional
The borough commissioner has placed an administrative stop work order for application/permit# 121637737 for intent to revoke approvals and p ermit. stop all work immediately and make site safe
Jun 19, 2017
Dob violation - dismissed - Elevator affirmation of correction elevatorrequired
Vio issued to elevator - fail to correct defects on 2014 cat 1 insp/tst
Nov 14, 2016
Dob violation - active - Elevator affirmation of correction elevatorrequired
Vio issued to elevator - fail to correct defects on 2014 cat 1 insp/tst
Nov 14, 2016
Dob violation - active - Elevator affirmation of correction elevatorrequired
Vio issued to elevator - fail to correct defects on 2014 cat 1 insp/tst
Nov 14, 2016
Dob violation - active - Elevator affirmation of correction elevatorrequired
Vio issued to elevator - fail to correct defects on 2014 cat 1 insp/tst
Nov 14, 2016
Dob violation - active - Elevator elevatorrequired
E-elevator elevatorrequired
Jul 1, 2015
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jul 1, 2015
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jun 18, 2014
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jun 18, 2014
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jun 18, 2014
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jun 18, 2014
Dob violation - resolved - Low pressure boiler boiler required
Violation issued for failure to file annual boiler 2012 inspection report
May 15, 2014
Dob violation - active - Elevator elevatorrequired
E-elevator elevatorrequired
Apr 25, 2013
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Apr 25, 2013
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Apr 25, 2013
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Apr 25, 2013
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jul 20, 2012
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jul 20, 2012
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jul 20, 2012
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jul 20, 2012
Dob violation - resolved - Failure to benchmark none
Failure to file benchmarking report of energy use as per ad. code sec. 28-309.4
May 3, 2012
Dob violation - active - Elevator elevatorrequired
E-elevator elevatorrequired
Jun 3, 2011
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jun 3, 2011
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jun 3, 2011
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jun 3, 2011
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jul 23, 2009
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jul 23, 2009
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jul 23, 2009
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jul 23, 2009
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jul 28, 2008
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jul 28, 2008
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jul 28, 2008
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jul 28, 2008
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Dec 18, 2007
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Dec 18, 2007
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Dec 18, 2007
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Dec 18, 2007
Dob violation - resolved - Facade facade required
L1198-local law 11/98 - facade facade required
Jun 25, 2007
Dob violation - dismissed - Elevator elevatorrequired
E-elevator elevatorrequired
Oct 12, 2005
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Oct 12, 2005
Dob violation - resolved
ECB violations · 21
- Class - 2
Sec. 3313.1 sec 3309.7.4.2 improper storage of flammable gases/materials. noted: i observed flammable propane & combustible materials storedwithin 20 feet of each other. there was no combustible storage case on
Dec 7, 2021
Resolve - Class - 2
Work contrary to aprove ssp,sws required from ss project w/out appointed request or approval.according to ssp-retrieval of sws & site safetymonitoring program-i said-removal of sws for a ss project requires an
Nov 4, 2021 · Penalty $1,250
Resolve - Class - 2
Work without permit.note at time of inspection at a 15 story building observed 4 workers on roof installing brick on parapet wall of the building.upon request to see for work permit,competent person did not pro
Aug 19, 2021 · Penalty $625
Resolve - Class - 2
At time of inspection,observed ongoing construction activities contrary to mayor's emergency order 120 and subsequent orders incorporating requirement of governor's executive order 202.34 and subsequent orders
Sep 16, 2020
Resolve - Class - 2
Failure to maintain exterior bldg facade and appurtenances.*north elevation exp 3,observed cracked and spalled masonry wall and stairs at bsmt level.rem:maintain exterior bldg facade,provide safety measures,rep
Feb 8, 2018 · Penalty $2,500
Active - Class - 1
Inadequate safety measures operationof hoisting equipment in an unsafe manner noted:at time of inspection found at 2 different drops missing/loose j-bolts for tieback connections for c-hooks suspended scaffolds
Oct 9, 2013
Resolve - Class - 2
3310.8.3 failure to comply rules promulgated by the commisioner(ssm log) noted:failure to maintained adequately site safety log site safety plan not kept in a binder as required remedy:comply with code
Oct 9, 2013
Resolve - Class - 1
Licensed rigger failed to ensure scaffold workers met minimum requirements noted:at time of inspetion the following workers working on 2 point suspended scaffold did not have ertificate of fitness 1.jose sandov
Oct 9, 2013
Resolve - Class - 1
3314.6.3 lifelines,tiebacks& suspension ropes shall each be attached to a different point of anchorage noted at time of inspection found at 2 locations at roof lifelines&tiebacks fastened to same anchorage poin
Oct 9, 2013
Resolve - Class - 1
3314.6.2 lifelines & tiebacks shall be protected from sharp edges & abrasion.noted:cables for anchorage point not protected from sharp edges. remedy:comply with code
Oct 9, 2013
Resolve
Show 11 more ↓
- Class - 1
No record of daily inspection of suspended scaffold performed by authorized person at site.noted:no records have been maintained for suspended scaffolds, for any days of active rigging remedy:maintain daily ins
Oct 9, 2013
Resolve - Hazardous
Cu21l1106i1121b01. (21l10) replace basement interlock (get stuck in made position) hazardous (06i11) replace gate switch roller (21b01) adj ust lobby interlock.
May 7, 2008 · Penalty $800
Resolve - Hazardous
06b11.17m07.21m07. 06b11 replace car gate roller 17m07 provide rear hoistway door gib 6 & 13 fls 21m07 provide missing 10 & 13 fl cover
May 7, 2008
Resolve - Hazardous
51h11. 51h11 replace worn hoist ropes
May 7, 2008
Resolve - Non-hazardous
Work w/o a permit. in nail salon installation of mez has taking place also new plumbing for pedicure stations.remedy:stop all work obtain permit.
Oct 20, 2006 · Penalty $2,500
Resolve - Non-hazardous
74d,61b,23b,33o,15i,50y, 74-secure overhead grading 61b-adjust tail rope 23b tag governor release carrier 33-clean o0ff eccessive grease 15i-repair lobby door 50y-seal main machine oil leak
May 5, 1998
Resolve - Non-hazardous
75u 22w 11q 05x 01m 57o 30o 05x block in gate contact
May 8, 1993 · Penalty $100
Resolve - Non-hazardous
22w 75u 01m 11q 57o 30o 30# 30# repair walls in hoistway no water pipr access in hoistway
May 8, 1993 · Penalty $100
Resolve - Hazardous
Use of suspension scaffold without a special license remedy:obtain license. no toe boards. remedy provide toe boards 5 scaffolds combined into one by bridging remedy discontinue use stirrups aprox 5' from end o
May 22, 1991 · Penalty $1,265
Resolve - Non-hazardous
22d,22m,18m,#18 covers
Feb 28, 1991 · Penalty $75
Resolve - Non-hazardous
22d,18m,#18 covers
Feb 28, 1991 · Penalty $75
Resolve
Complaints
- Appliance
Refrigerator
Nov 21, 2025 · Apt 11G
Close - Appliance
Refrigerator
Jan 24, 2024 · Apt 11G
Close - Appliance
Refrigerator
Dec 18, 2023 · Apt 11G
Close - Heat/hot water
Entire building
Feb 1, 2023 · Apt BLDG
Close - Heat/hot water
Apartment only
Jan 2, 2018 · Apt 6B
Close - Plumbing
Water supply
Mar 11, 2016 · Apt 15H
Close - Plumbing
Water supply
Mar 11, 2016 · Apt 15H
Close - Paint/plaster
Wall
Jan 4, 2012 · Apt 6B
Close - Heating
Heat related
Mar 2, 2011 · Apt 14D
Close - Heating
Heat related
Feb 24, 2011 · Apt 14D
Close
Show 32 more ↓
- Heating
Heat related
Feb 16, 2011 · Apt 14D
Close - Heating
Heat related
Jan 24, 2011 · Apt 14D
Close - Heating
Heat related
Jan 24, 2011 · Apt 14D
Close - Heating
Heat related
Jan 24, 2011 · Apt 14D
Close - Heating
Heat related
Jan 23, 2011 · Apt 14D
Close - General
Floor
Jun 5, 2009 · Apt 6B
Close - Appliance
Electric/gas range
Jun 5, 2009 · Apt 6B
Close - Appliance
Electric/gas range
May 14, 2009 · Apt 6B
Close - Plumbing
Basin/sink
Dec 17, 2008 · Apt 6B
Close - Paint/plaster
Wall
Dec 17, 2008 · Apt 6B
Close - Electric
Lighting
Dec 17, 2008 · Apt 6B
Close - Paint/plaster
Wall
Dec 17, 2008 · Apt 6B
Close - Plumbing
Basin/sink
Dec 17, 2008 · Apt 6B
Close - Plumbing
Basin/sink
Dec 17, 2008 · Apt 6B
Close - Plumbing
Basin/sink
Dec 17, 2008 · Apt 6B
Close - General
Windows
Dec 17, 2008 · Apt 6B
Close - General
Floor
Dec 17, 2008 · Apt 6B
Close - Plumbing
Bathtub/shower
Apr 18, 2008 · Apt 6B
Close - Plumbing
Bathtub/shower
Apr 18, 2008 · Apt 6B
Close - Electric
Lighting
Apr 18, 2008 · Apt 6B
Close - Paint/plaster
Wall
Apr 18, 2008 · Apt 6B
Close - Plumbing
Basin/sink
Apr 18, 2008 · Apt 6B
Close - Plumbing
Basin/sink
Apr 18, 2008 · Apt 6B
Close - Plumbing
Basin/sink
Apr 18, 2008 · Apt 6B
Close - General
Windows
Apr 18, 2008 · Apt 6B
Close - General
Floor
Apr 18, 2008 · Apt 6B
Close - Plumbing
Water supply
Jun 28, 2004 · Apt 11H
Close - Plumbing
Basin/sink
Jun 28, 2004 · Apt 11H
Close - Plumbing
Water supply
Jun 28, 2004 · Apt 11H
Close - Paint/plaster
Wall
Jun 28, 2004 · Apt 11H
Close - Paint/plaster
Wall
Mar 15, 2004 · Apt 11H
Close - Plumbing
Water supply
Mar 15, 2004 · Apt 11H
Close
Sales history
| Date | Price | Type | Units |
|---|---|---|---|
| Aug 20, 2026 | $1,200,000 | Coops - elevator apartments | — |
| Feb 17, 2026 | $990,000 | Coops - elevator apartments | — |
| Feb 17, 2026 | $675,000 | Coops - elevator apartments | — |
| Feb 10, 2026 | Non-market transfer | Coops - elevator apartments | — |
| Dec 18, 2025 | $810,000 | Coops - elevator apartments | — |
| Nov 19, 2025 | $1,325,000 | Coops - elevator apartments | — |
| Sep 26, 2025 | $742,500 | Coops - elevator apartments | — |
| Sep 9, 2025 | $1,962,500 | Coops - elevator apartments | — |
Building details
- Building type
- Elevator apartment building (D4)
- Year built
- 1922
- Floors
- 15
- Residential units
- 146
- Building area
- 196,293 ft²
- Lot area
- 17,624 ft²
- Zoning
- C4-6A
- Community board
- 107
- Council district
- 7
- Block / lot
- 1240 / 24
- Assessed value
- $19,380,150
- Landmark / historic district
- No
HPD registration #111612, last renewed Aug 6, 2025.
Questions about 2480 Broadway
Who owns 2480 Broadway?
The owner of record in NYC Department of City Planning PLUTO data is 215 Equities Corp.
Does 2480 Broadway have violations?
Yes. NYC HPD has recorded 8 housing violations at this property.
Is 2480 Broadway rent stabilized?
NYC Department of Finance tax bills listed 6 rent-stabilized units here in 2024 (about 4% of its 146 apartments). To confirm a specific apartment, request its rent history from NYS Homes and Community Renewal.
When was 2480 Broadway built?
City records list 1922 as the year it was built.
How many apartments are in 2480 Broadway?
It has 146 residential units and 155 units in total.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.