246 West 61 Street
Manhattan, NY 10023BBL 1-01152-0058Map
Owner of record: The Abraham Joshua Heschel School
246 West 61 Street is a school building built in 2011 in Manhattan, 10023. The owner of record is The Abraham Joshua Heschel School. HPD has no housing violations on record for this property.
- HPD violations
- 0
- DOB violations
- 22
- ECB violations
- 17
- HPD complaints
- 18
What to know
No open immediately-hazardous violations among recent records.
HPD has not cited this building.
No balance due on recent ECB violations.
Rent stabilization
No rent-stabilized units in 2018–2024 tax bills
Violations
Most recent first. Showing up to 50 per agency.
HPD housing violations · 0
No HPD violations on record
DOB building violations · 22
- Elevator elevatorrequired
E-elevator elevatorrequired
Sep 9, 2021
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Sep 9, 2021
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Sep 9, 2021
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Sep 9, 2021
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Sep 9, 2021
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jun 23, 2020
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jun 23, 2020
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jun 23, 2020
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jun 23, 2020
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
Jun 23, 2020
Dob violation - resolved
Show 12 more ↓
- Elevator elevatorrequired
E-elevator elevatorrequired
May 10, 2019
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
May 10, 2019
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
May 10, 2019
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
May 10, 2019
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
May 10, 2019
Dob violation - resolved - Elevator elevatorrequired
E-elevator elevatorrequired
May 7, 2015
Dob violation - resolved - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Jan 2, 2013
Dob violation - dismissed - Elevator annual inspection / test elevatorrequired
Violation issued to elevator-failure to file category 1 2011 inspection/test
Oct 1, 2012
Dob violation - dismissed - Fail to certify class 1 none
Failure to certify correction on immediately hazardous (class 1) ecb violation
Sep 7, 2011
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Mar 19, 2003
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Mar 26, 2002
Dob violation - dismissed - Boilers boiler required
Ll6291-local law 62/91 - boilers boiler required
Feb 27, 2001
Dob violation - dismissed
ECB violations · 17
- Class - 2
Failure to maintain bldg exterior facades&appurtenances.@west elevation,exp1 observed broken window [email protected] bldg exterior facades,provide safety measures,repair defected facadesas per 1rcny103-04.
Apr 23, 2021 · Penalty $620
Resolve - Class - 1
Failure to safeguard all persons & property affected by construction operations. partial stop work order: on all exterior (facade) work north west corner: upon inspection as noted sidewalk shed removed men
Aug 23, 2012 · Penalty $2,400
Resolve - Class - 1
Supervisory responsibilities of a licensed master rigger. noted:specially crew:the licensee and/or rigging foreman designated by a licensee may not perform or supervise rigging work for another person,corporati
Jan 5, 2012 · Penalty $1,600
Resolve - Class - 1
Bc3303.8)failure to provide stand pipe @ required height.upon inspec as noted on active construction site up to bulkhead(11th)the roof(10flr)has been poured workers are forming the shaft @ bulkhead there is no
Dec 5, 2011 · Penalty $1,600
Resolve - Class - 1
Bc3314.3.1)failure to provide design drawing.upon inspec as noted on active const site up to bulkhead(11 flr)partial swo on supported scaffold & extended platform(bicycles)on 8 flr exp#3 issued pursuant to 28-2
Dec 5, 2011 · Penalty $1,600
Resolve - Class - 1
Failure to provide adequate roof protection upon inspec as noted on active construction site up to bulkjead(11 fl).partial swo within 20' & above adjoining bldg roof exp#2(east side).issued pursuant to 28-207.2
Dec 5, 2011 · Penalty $1,600
Resolve - Class - 2
Failure to provide required vertical netting upon inspection as noted on active construction site up to bulkhead(11 flr)the vertical nets on 8 flr has been removed on exp#4 section missing @ columns & in genera
Dec 5, 2011
Resolve - Class - 2
Bc3301.2)failure to institute & maintain safety equipment measures or temp const holes in flr.upon inspec as noted on active construction site up to bulkhead(11 flr)there are approx 20 holes varying in size fro
Dec 5, 2011
Resolve - Class - 1
Failure to maintain/institute safety equipment measures or temporary construction - no guard rail. observed 3 flr openings are not protected by providing guard rail on 1st flr level. approx 200 sq ft opening
Jun 13, 2011 · Penalty $2,400
Resolve - Class - 2
Failure to safeguard all persons and property affected by constructionoperation. observed the sidewalk is closed on 61 st side and material handling in progress by truck on the sidewalk. no warning signs have
May 16, 2011 · Penalty $1,200
Resolve
Show 7 more ↓
- Class - 2
Sec. 3310.02. failure to maintain a log for concrete safety manager. @time of inspection foundation & retaining wall (concrete) completed. the respondent is a designated & concrete safety manager failed to
May 16, 2011 · Penalty $400
Resolve - Class - 2
Failure to safeguard public and property affected by construction operations - at time of inspection observed chain link fence used for separation & protection for pedestrian walkway and materials storage for
Feb 16, 2011 · Penalty $6,000
Resolve - Class - 1
Failure to institute/maintain safety equipment measures - no toe boards - at time of inspection. observed toe boards on north side 3 1/2" - dob code required - toe boards to be 5 1/2". remedy:provide proper toe
Feb 16, 2011 · Penalty $5,000
Resolve - Class - 2
Work does not conform to approved construction documents noted work on going under nb permit #120178994 concrete grade beam has been installed btwn two western most columns of existing structure at heschel sch
Feb 8, 2011
Resolve - Class - 1
Work does not conform to approved construction documents and or approved amendments - at time of inspection observed excavation in progress - site safety plan shows fence on east side separating site & adjacent
Dec 22, 2010 · Penalty $1,000
Resolve - Non-hazardous
Use of a two print suspension scaffold without a ribbon license. use of scaffold with defective rope. operatiion of a scaffold now unsafe manner by not having outrigger beams tied back. operation of a scaffold
Jun 16, 1994 · Penalty $12,000
Resolve - Non-hazardous
05j,15j,18l,35b,73o, 35-repair light motor room 74-adjust floorstops
Mar 21, 1991
Resolve
Complaints
- Water leak
Heavy flow
Oct 2, 2026 · Apt 3C
Close - Unsanitary condition
Pests
Oct 2, 2026 · Apt 3C
Close - Paint/plaster
Wall
Oct 2, 2026 · Apt 3C
Close - Unsanitary condition
Mold
Oct 2, 2026 · Apt 3C
Close - General
Cabinet
Oct 2, 2026 · Apt 3C
Close - Heat/hot water
Apartment only
Oct 2, 2026 · Apt 3C
Close - Appliance
Refrigerator
May 18, 2026 · Apt 3C
Close - Water leak
Slow leak
May 18, 2026 · Apt 3C
Close - Paint/plaster
Wall
May 18, 2026 · Apt 3C
Close - Unsanitary condition
Sewage
Dec 1, 2015 · Apt 1D
Close
Show 8 more ↓
- Unsanitary condition
Pests
Dec 1, 2015 · Apt 1D
Close - Door/window
Door
Dec 1, 2015 · Apt 1D
Close - Paint/plaster
Wall
Dec 1, 2015 · Apt 1D
Close - Paint/plaster
Wall
Mar 31, 2014 · Apt 3D
Close - Appliance
Electric/gas range
Mar 31, 2014 · Apt 3D
Close - Paint/plaster
Wall
Feb 19, 2009 · Apt 5B
Close - General
Mold
Feb 19, 2009 · Apt 5B
Close - Appliance
Refrigerator
Feb 19, 2009 · Apt 5B
Close
Sales history
No recorded sales in our data
Building details
- Building type
- School building (W8)
- Year built
- 2011
- Floors
- 9
- Residential units
- —
- Building area
- 158,943 ft²
- Lot area
- 17,531 ft²
- Zoning
- C4-7
- Community board
- 107
- Council district
- 6
- Block / lot
- 1152 / 58
- Assessed value
- $46,788,750
- Landmark / historic district
- No
Questions about 246 West 61 Street
Who owns 246 West 61 Street?
The owner of record in NYC Department of City Planning PLUTO data is The Abraham Joshua Heschel School.
Does 246 West 61 Street have violations?
NYC HPD has no housing violations on record for this property.
Is 246 West 61 Street rent stabilized?
No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.
When was 246 West 61 Street built?
City records list 2011 as the year it was built.
Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.