roofy

4 Penn Plaza

Manhattan, NY 10001BBL 1-00781-0001Map

Owner of record: National Railroad Passenger Corp

4 Penn Plaza is an utility in Manhattan, 10001. The owner of record is National Railroad Passenger Corp. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
105
ECB violations
388
HPD complaints
22

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 105

  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jul 20, 2018

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jul 12, 2018

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jul 12, 2018

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jul 12, 2018

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jul 12, 2018

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jul 12, 2018

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jul 11, 2018

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jul 11, 2018

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jul 11, 2018

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jul 11, 2018

    Dob violation - resolved
Show 40 more ↓
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jul 11, 2018

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jul 11, 2018

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jul 11, 2018

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jun 21, 2017

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jun 20, 2017

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jun 20, 2017

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jun 24, 2015

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jun 24, 2015

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jun 24, 2015

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jun 24, 2015

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jul 31, 2013

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jul 30, 2013

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jul 25, 2013

    Dob violation - resolved
  • Elevator elevatorrequired

    E-elevator elevatorrequired

    Jul 24, 2013

    Dob violation - resolved
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 16, 2013

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jul 11, 2012

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    May 2, 2012

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Apr 18, 2012

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Mar 21, 2012

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Feb 22, 2012

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Feb 22, 2012

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 25, 2012

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 25, 2012

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 25, 2012

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 25, 2012

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 25, 2012

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 14, 2011

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 14, 2011

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 14, 2011

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 14, 2011

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Dec 14, 2011

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 5, 2011

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 5, 2011

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Sep 7, 2011

    Dob violation - dismissed
  • Construction other optional

    Fail to maintain bldg walls and appurtenances. upon inspection plywood decking @ roof location not properly secured. bldgs materials @ roof not properly secured or removed from roof

    Aug 26, 2011

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    May 18, 2011

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Feb 9, 2011

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Feb 9, 2011

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Feb 9, 2011

    Dob violation - dismissed
  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Jan 28, 2011

    Dob violation - dismissed

ECB violations · 388

  • Class - 2

    99m05: (99) cat 1 tag present on controller for 2021. no elv-3 report filed with nycdob for this cat 1 test

    Oct 21, 2022 · Penalty $1,562

    Resolve
  • Class - 2

    Job site fence not constructed or maintained pursuant to subsection: noted: upon inspection observed at location active permit m00383776 posted on temporary construction fence. the temporary construction fence

    Dec 18, 2020

    Resolve
  • Class - 1

    Failure to maintain the end of the street rock is sagging approximately 3 inches. this is in the cut through between 2 pennsylvania plaza & 4 pensylvania plaza between w31 + w33 street.

    Dec 22, 2019

    Resolve
  • Class - 1

    Outdoor advertising company sign not permitted in specified c district. sign displayed violates conditions set forth pursuant to zr 93-171 in city council resolution no. 1889 in that "#3 - netflix" not submitte

    Feb 24, 2015

    Resolve
  • Class - 1

    Outdoor advertising company sign not permitted in specified c district. sign displayed violates conditions set forth pursuant to zr 93-171 in city council resolution no. 1889 in that "#4 - netflix" not submitte

    Feb 24, 2015

    Resolve
  • Class - 1

    Outdoor advertising company sign not permitted in specified c district. sign displayed violates conditions set forth pursuant to zr 93-171 in city council resolution no. 1889 in that "#5 - red storm - st johns"

    Feb 24, 2015

    Resolve
  • Class - 2

    100l10-step demarcation lights defective repair.

    Jan 28, 2015

    Resolve
  • Class - 2

    100l10 step demaraction lights defective repair.

    Jan 28, 2015

    Resolve
  • Class - 2

    100l10 step demarcation light top defective repair.

    Sep 19, 2014 · Penalty $2,500

    Resolve
  • Class - 2

    100l10 demarcation light defective top landing repair.

    Sep 17, 2014 · Penalty $2,500

    Resolve
Show 40 more ↓
  • Class - 2

    100b07 - provide proper guarding betwen stairway and escalator,1e1639 (m6).

    Sep 30, 2013

    Resolve
  • Class - 2

    100b07 - provide proper guarding between stairway and escalator, 1e1636(m1)

    Sep 30, 2013

    Resolve
  • Class - 2

    105.12.1 work not in accordance w/site safety plan.note:construction gate @turner construction trailer located under taxiway gate has been chained & locked contrary to site safety plan.rem:remove lock & chain i

    May 22, 2013

    Resolve
  • Class - 2

    99bb07,12x10,60x10.99bb07:one year past due.12x10:replace defective light bulbs in car (elevator).60x10:repair lighting,pump room.

    Jan 3, 2013 · Penalty $2,500

    Resolve
  • Class - 1

    Sec. bc 3314.16.4. failure to perform pre-inspection of suspended angle scaffolds. noted: work in progress at w 32nd street exp from c-hook angle suspended scaffolds w/o pre-inspection by development. call ssu

    Oct 24, 2012

    Resolve
  • Class - 1

    Fail to safeguard all persons/prop affected by const ops.under permit #110463356 welding operation taken place @roof.@10th fl contractor failed to install fire blanket properly.sparks fr welding op falling behi

    Sep 19, 2012 · Penalty $2,400

    Resolve
  • Class - 2

    3301.2 fail to provide 3'6" guardrail or equivalent around all floor & perimeter openings. @10th fl under permit #110463356 obs inadequate guardrail system (no toe boards) at numerous locations.rem:provide code

    Sep 19, 2012 · Penalty $800

    Resolve
  • Class - 1

    Fail to safeguard all persons/prop affected by const ops.note:under permit #110463356 @8th fl tower b escalator work take place.contractor removed guardrails & left area unattended creating unsafe condition.imm

    Sep 19, 2012 · Penalty $2,400

    Resolve
  • Class - 1

    Bc3203.4.6-new installation of combustible materials note observed cardboard boxes stored covered with non fire rated plastic on 7th floor not according to nyc dob code (111.04.2) remedy: remove combustible ma

    Sep 12, 2012

    Resolve
  • Class - 1

    Failure to & safeguard all persons & property altered by construction operations at time of insp of observed no file guard present at working operations roof material loose 10x15 roof hatches left open no prote

    Sep 12, 2012 · Penalty $2,400

    Resolve
  • Class - 2

    Recent smoking refuse w/in construction site in violation of nyc fim con at time of insp observed cigarette butts at roof level * butts cigarette packs @ groot lvl rem: comply w/ notice

    Sep 12, 2012 · Penalty $1,200

    Resolve
  • Class - 2

    Failure to safeguard all persons & property affected by construction operations,work on going under permit 110463356. upon inspection numerour holes in floors at numerous locations on floors 7 & 8.

    Sep 5, 2012 · Penalty $1,200

    Resolve
  • Class - 2

    Service lines and cables constitute a tripping hazard: upon inspection as noted on active construction site approx 1,000 personnel on site on a daily basis there are welding cables, extension cord's laying

    Sep 5, 2012 · Penalty $3,000

    Resolve
  • Class - 1

    Failure to institute/maintain safety equipment measures or temporary construction: no guard rails. upon inspection as noted the guardrail system around the mechanical shafts is inadequate missing has material

    Sep 5, 2012 · Penalty $1,200

    Resolve
  • Class - 2

    Sec. 3307.6.5 failure to maintain proper sidewalk shed illumination. upon inspection contractor has failed to provide waterproof lighting fixtures for sidewalk shed. lighting fixtures are filled w/water at time

    Sep 5, 2012

    Resolve
  • Class - 1

    Erected or installed supported scaffold 40 feet or higher w/o a permit. noted: supported scaffold have been erected inside of elevator shaftat columns #21,#22,#26 running from 8th fl-10th fl,approx 45ft in heig

    Aug 29, 2012 · Penalty $1,200

    Resolve
  • Class - 1

    Failure to institute/maintain safety equipment measures or temporary construction. no guard rails. upon inspection as noted on active construction site the guard rail system at mechanical pipe shafts is missing

    Aug 29, 2012 · Penalty $2,400

    Resolve
  • Class - 1

    Work does not conform to approved construction documents &/or approvedamendments. upon inspection elevator p16 7th flr column line 45. contractor has failed to provide temporary platform according to approved d

    Aug 29, 2012 · Penalty $1,000

    Resolve
  • Class - 1

    Failure to institute/maintain safety equipment measures or temporary construction: no handrails: upon inspection as noted on active construction site there were no handrails on stairs leading to escalator

    Aug 22, 2012 · Penalty $1,000

    Resolve
  • Class - 2

    Service lines & cables constitute a tripping hazard during a joint inspection on an active construction site observed extension cords & welding cables laying across passageways & working floors on 7th & 8th fl

    Aug 22, 2012 · Penalty $400

    Resolve
  • Class - 2

    Work does not conform to approved construction documents/or amendmentsnoted:contrary to approved plans/amendments for installation of supported scaffold on lower lever of quik deck system for installing approx

    Aug 22, 2012 · Penalty $250

    Resolve
  • Class - 1

    Failure to safe guard all persons & property affected by construction operations. work on going under permit #110463356. observed a frame material kart being used to transport steel i beam at 8th flr. these a f

    Aug 22, 2012 · Penalty $3,000

    Resolve
  • Class - 2

    Failure to maintain adequate housekeeping per section requirements. during a joint inspection as noted on active construction site there were loose boxes,conduit,cables & ladder stored on top of shanties approx

    Aug 22, 2012

    Resolve
  • Class - 2

    Observed recent smoking refuse within construction/demo site in violation of nyc fire code. work on going under permit #110463356 observed smoking refuse at 5th flr shanty area. rem:comply notice making sure th

    Aug 22, 2012 · Penalty $1,200

    Resolve
  • Class - 2

    Work does not conform to approved construction documents. noted: installation of a temporary suspended quick deck platform is contrary to approved plans for extending platform from a quick deck to a plank

    Aug 16, 2012 · Penalty $250

    Resolve
  • Class - 2

    Failure to safeguard all persons & property affected by construction operations.observe recent smoking refuse within construction site in violation of nyc fire code.@ time of inspec i did observe several cigare

    Aug 15, 2012

    Resolve
  • Class - 2

    Material &/or debris shall not be stored on sidewalk shed unless shed has been designed for such use.@ time of inspec i did observe material & debris stored on sidewalk shed.rem:comply w/ notice.

    Aug 15, 2012 · Penalty $2,400

    Resolve
  • Class - 1

    Sec. 3301.7. failure to comply w/design drawing. partial swo on all temporary platforms/scaffold all levels that are not built as per designdrawings issued pursuant to 28.207.2 and posted at premises: during a

    Aug 15, 2012 · Penalty $400

    Resolve
  • Class - 1

    Sec. 3313.1. storage of all volatile flammable and comubstibule mixtures. upon inspection as noted during evening walk thru (multi unit) observed 10 gallons of liquid fuel in 2,5gallon cans stored in main arena

    Aug 15, 2012 · Penalty $1,600

    Resolve
  • Class - 2

    Failure to safeguard all persons & property affected by construction operations.@ time of inspec i did observe @ 5 flr a fire extinguisher that was discharged making it inoperable.its location was brought to at

    Aug 15, 2012

    Resolve
  • Class - 1

    Sec. 3301.2. failure to provide 3'6" guard rail or equivalent around all flrs and perimeter openings. work ongoing under permit. #110463356.contractor has failed to provide adequate guard rail system @ numerous

    Aug 8, 2012 · Penalty $1,600

    Resolve
  • Class - 1

    Failure to safeguard all persons and property affected by constructionoperation. upon inspection under permit #110463356. hot works operations taking place at 7th flr column 43. fire guard was not observing

    Aug 8, 2012 · Penalty $2,400

    Resolve
  • Class - 2

    Service lines and cables constitute a tripping hazard. during a joint inspection on active construction site noted, welding cables, compressed gas hoses,extension cords laying across 7th & 8th flr working decks

    Aug 8, 2012 · Penalty $400

    Resolve
  • Class - 1

    Sec. 3301.2. failure to institute/maintain safety equipment measures or temporary construction holes in flr: during a joint inspection as noted on active construction site there were approx 30 holes up to 8"

    Aug 8, 2012 · Penalty $1,600

    Resolve
  • Class - 2

    Sec. 3303.4.5.1. materials stored during construction: upon inspectionas noted on active construction, during a joint inspection observed construction equipment, planks, cement blocks, wood, steel mesh stored @

    Aug 8, 2012 · Penalty $400

    Resolve
  • Class - 2

    Smoking at construction/demo site during a joint inspection as noted on active construction site observed smoking refuse at 8th flr hoist ramp & platform the area is w/i construction site public has no access

    Aug 8, 2012 · Penalty $1,200

    Resolve
  • Class - 1

    Failure to safeguard all persons and property affected by constructionoperations. work ongoing under permit #110463356. observed contractor using a framed material kart that was excluded from the site for the

    Aug 8, 2012 · Penalty $1,200

    Resolve
  • Class - 2

    Failure to safeguard all persons & property affected by construction operations. observe recent smoke refuse w/i construction site in violation of nyc fire code 1404.1. at time of inspection i did observe

    Aug 1, 2012

    Resolve
  • Class - 2

    Work does not conform to approved construction documents and/or approved amendments. at time of inspection i did observe @ 8th flr column lines 30 & 31 a large length of structural steel being modified w/1 pe

    Aug 1, 2012

    Resolve
  • Class - 2

    Sec. 3301.7 failure to comply w/design drawing upon inspection as noted there is a temporary platform/scaffold being constructed around the escalator shafts on the 7th floor there is a design drawing by plan'b'

    Aug 1, 2012

    Resolve

Complaints

  • Paint/plaster

    Wall

    Aug 21, 2024 · Apt 3C

    Close
  • Door/window

    Window pane

    Aug 21, 2024 · Apt 3C

    Close
  • Paint/plaster

    Wall

    Aug 21, 2024 · Apt 3C

    Close
  • Paint/plaster

    Wall

    Aug 21, 2024 · Apt 3C

    Close
  • Flooring/stairs

    Floor

    Aug 21, 2024 · Apt 3C

    Close
  • Heat/hot water

    Apartment only

    Mar 30, 2021 · Apt ADDRES

    Close
  • Safety

    Fire escape

    Mar 30, 2021 · Apt ADDRES

    Close
  • Flooring/stairs

    Floor

    Mar 30, 2021 · Apt ADDRES

    Close
  • Paint/plaster

    Door/frame

    Mar 30, 2021 · Apt ADDRES

    Close
  • Water leak

    Heavy flow

    Mar 30, 2021 · Apt ADDRES

    Close
Show 12 more ↓
  • Plumbing

    Steam pipe/riser

    Mar 30, 2021 · Apt ADDRES

    Close
  • Flooring/stairs

    Floor

    Mar 30, 2021 · Apt ADDRES

    Close
  • Unsanitary condition

    Pests

    Mar 30, 2021 · Apt ADDRES

    Close
  • Electric

    No lighting

    Mar 30, 2021 · Apt ADDRES

    Close
  • Paint/plaster

    Window/frame

    Mar 30, 2021 · Apt ADDRES

    Close
  • Electric

    Power outage

    Oct 7, 2019 · Apt BRONXB

    Close
  • Safety

    Fire escape

    Oct 7, 2019 · Apt BRONXB

    Close
  • Heat/hot water

    Entire building

    Oct 7, 2019 · Apt BRONXB

    Close
  • General

    Janitor/super

    Oct 7, 2019 · Apt BRONXB

    Close
  • General

    Cooking gas

    Oct 7, 2019 · Apt BRONXB

    Close
  • Unsanitary condition

    Garbage/recycling storage

    Oct 7, 2019 · Apt BRONXB

    Close
  • Plumbing

    Water supply

    Oct 7, 2019 · Apt BRONXB

    Close

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Utility (U6)
Year built
—
Floors
—
Residential units
—
Building area
—
Lot area
237,724 ft²
Zoning
C6-4
Community board
105
Council district
3
Block / lot
781 / 1
Assessed value
—
Landmark / historic district
No

Questions about 4 Penn Plaza

Who owns 4 Penn Plaza?

The owner of record in NYC Department of City Planning PLUTO data is National Railroad Passenger Corp.

Does 4 Penn Plaza have violations?

NYC HPD has no housing violations on record for this property.

Is 4 Penn Plaza rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

Source: NYC Open Data (DCP PLUTO, HPD, DOB, ECB/OATH, DOF). Records can lag the city's systems. Data refreshed weekly.