roofy

416 8 Avenue

Manhattan, NY 10001BBL 1-00780-0073Map

Owner of record: 416 8th Owner, LLC

416 8 Avenue is a store building built in 1930 in Manhattan, 10001. The owner of record is 416 8th Owner, LLC. HPD has no housing violations on record for this property.

HPD violations
0
DOB violations
10
ECB violations
10
HPD complaints
0

What to know

Good
No open Class C

No open immediately-hazardous violations among recent records.

Good
No HPD violations

HPD has not cited this building.

Good
No unpaid ECB fines

No balance due on recent ECB violations.

Rent stabilization

No rent-stabilized units in 2018–2024 tax bills

Some apartments can still be regulated. Use the rent-stabilized checker or request the rent history from HCR.

Violations

Most recent first. Showing up to 50 per agency.

HPD housing violations · 0

No HPD violations on record

DOB building violations · 10

  • Fail to certify class 1 none

    Failure to certify correction on immediately hazardous (class 1) ecb violation

    Oct 30, 2024

    Dob violation - dismissed
  • Construction other optional

    The dept. of buildings orders that you stop all work under permits issued in connection with application #140950308. the application of record has informed the department that she or he has withdrawn from the project.stop all work immediately and make the site safe. unable to determine %of work completed.

    Nov 16, 2023

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Feb 27, 2001

    Dob violation - dismissed
  • Unsafe buildings none

    Ub-unsafe buildings none

    Sep 8, 2000

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Aug 15, 2000

    Vw-violation work without permit - active
  • Construction other optional

    C-construction other optional

    Aug 15, 2000

    Dob violation - dismissed
  • Construction other optional

    C-construction other optional

    Aug 15, 2000

    Vw*-violation - work w/o permit dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Feb 7, 2000

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    May 4, 1998

    Dob violation - dismissed
  • Boilers boiler required

    Ll6291-local law 62/91 - boilers boiler required

    Sep 16, 1997

    Dob violation - dismissed

ECB violations · 10

  • Class - 1

    At time of inspection at above address observed construction work under job# m00971702 illegally engaging without a required license or other authoriaztion. permit not valid, obtain permit

    Aug 29, 2024

    Resolve
  • Class - 2

    Failure to maintain bldg in code-compliant manner. lack of a system ofautomatic sprinklers where required per bc 903.2;27-954. 2nd flr sprinkler coverage inadequate. no sprinkler system covering front half of

    Jul 15, 2009 · Penalty $500

    Resolve
  • Class - 1

    Fgc404.1 gas piping shall not b installed in public corridors providing access to required exits observed exposed gas branch line in public stairway between 1st and 2nd fl of restaurant exitway remedy: comply

    Jul 15, 2009 · Penalty $1,600

    Resolve
  • Non-hazardous

    Operation of place of assembly w/o a current permit. occupancy - first fl - 86 persen 2nd fl - 80 persens remedy : obtain pa permit

    Dec 5, 2001 · Penalty $500

    Resolve
  • Non-hazardous

    A sidewalk shed shall be erected when hoisting materials or moving debris over sidewalk without first erecting a sides walk shed. remedy: stop all hoisting of materials immediately erect sidewalk after permit

    Feb 8, 2001 · Penalty $2,000

    Resolve
  • Hazardous

    Failure to maintain exterior building wall. defects are: missing bricks created opening 8"x12'-0" over door at w.31th street wall and 8:x16'-0" opening above the window lintel at 8th ave. street wall wiht the n

    Aug 15, 2000 · Penalty $800

    Resolve
  • Non-hazardous

    Work without a permit. work noted:demolition to interior walls on ground floor and basement without a permit. remedy:stop all work immediately. obtain permits and approvals from building department.

    Aug 15, 2000 · Penalty $500

    Resolve
  • Non-hazardous

    Work without a permit. work noted:demolition in procress to interior walls of the ground floor and cellar. no work permit. remedy:stop all work immediately. obtain permit and approvals from building department.

    Aug 15, 2000 · Penalty $500

    Resolve
  • Non-hazardous

    39 49 a dirty boiler room b boiler room being used as storage room

    Nov 12, 1998 · Penalty $180

    Resolve
  • Non-hazardous

    25a+b,36,49. a-flu pipe not properly sealed at chimney base. b-no rec-ords for existing boiler.

    Jul 30, 1996 · Penalty $400

    Resolve

Complaints

No HPD complaints in our records

Complaint data is still being backfilled from NYC Open Data.

Sales history

No recorded sales in our data

Sales come from the NYC Department of Finance rolling sales file.

Building details

Building type
Store building (K2)
Year built
1930
Floors
2
Residential units
—
Building area
4,600 ft²
Lot area
2,325 ft²
Zoning
C6-3X
Community board
105
Council district
3
Block / lot
780 / 73
Assessed value
$3,127,950
Landmark / historic district
No

Questions about 416 8 Avenue

Who owns 416 8 Avenue?

The owner of record in NYC Department of City Planning PLUTO data is 416 8th Owner, LLC.

Does 416 8 Avenue have violations?

NYC HPD has no housing violations on record for this property.

Is 416 8 Avenue rent stabilized?

No rent-stabilized units appear in its 2018–2024 tax bills. Individual apartments can still be regulated, so request the rent history from NYS Homes and Community Renewal if unsure.

When was 416 8 Avenue built?

City records list 1930 as the year it was built.